featured story
A power shovel removes the first of some 230,000 cubic metres from the Tokamak Pit.
The first days of August in southern France are usually very quiet. This is the heart of the summer holiday season; half the shops and businesses are closed and every serious decision has to be postponed until la rentrée, the first weeks of September when life finally gets back to normal.

On a small, 42 hectare-wide area of southern France, however, the first week of August was marked by renewed activity.

Bulldozers, scrapers and power shovels were back on the ITER platform: under the responsibility of the European Domestic Agency F4E, work was being started in the Tokamak pit and on the 14,000 square-metre area that will host the huge PF Coils Assembly Building.

On Wednesday 4 August , after some preparatory works had been done during the previous week, a lone power shovel began removing the top soil from the Tokamak pit — the first of some 230,000 cubic metres that will have to be extracted  in order to make room for the installation.

In a little more than three weeks, blasting specialists will move in for two months. Explosives will be used to blast some of the rock layer at an average rate of 4,000 cubic metres per day.

Some 250 metres away, bulldozers and scrapers were busy levelling the PF Coils Assembly Building area and preparing a smooth "sub-base" on top of which a 30 to 40 centimetre-thick concrete floor slab will be poured in about a month from now.

Operations on the ITER Platform are being carefully coordinated under the authority of the Engage Consortium and, as far as Health & Safety are concerned, by the French company APAVE.

Coordination will be crucial starting at the end of the month, when rock will be blasted here and concrete poured there... It has been decided that blasting will be performed during lunch break and concrete poured in the afternoon, then left to harden during the night.

"This is the first actual work en route to First Plasma", says Ben Slee, Deputy Head of Site Building and Power Supplies at F4E. "It is essential to keep the schedule..."

While actual work on the future ITER Headquarters and related buildings will only start in September, preliminary earthworks have been ongoing for a couple of days below the north-east corner of the platform.

Agence Iter France, who is responsible for construction, expects to deliver the buildings (co-financed by France and F4E) by mid-2012.

slideshow: iter progress
ITER: Looking toward the north-east ITER: Looking toward the north-east

Looking north-east over the ITER construction site. ©Altivue.AIF
First ITER components transported First ITER components transported

The first conductors produced for ITER's toroidal field coils were transported by truck and then boat in March 2010 between the manufacturer, Nippon Steel in Kyushu, Japan and Toshiba in Yokohama where trial winding will be performed.
ITER Platform ITER Platform

Work will begin this year on excavation for the Tokamak Complex and construction of the first buildings. The ITER platform is ready; perfectly flat, it measures 400 x 1000 metres. Credit AIF VDC.
International School opens International School opens

Work has ended on the first phase of the International School of Manosque. In October, 2009, 150 elementary school students moved into their new quarters. Photo: ISM
Prototype for ITER Prototype for ITER

A prototype cryogenic vacuum pump is inspected at the Karlsruhe Institute of Technology, Germany. Photo: Peter Ginter
Pulling together for ITER Pulling together for ITER

Employees manipulate a length of stainless steel cable jacket at ASIPP, Institute of Plasma Physics, in Hefei, China. This facility was designed to handle 900 metre lengths of superconducting cable for ITER's magnet system. Photo: Peter Ginter
ITER: Looking toward the north-east First ITER components transported ITER Platform International School opens Prototype for ITER Pulling together for ITER