Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

Building ITER

Building ITER

Construction

Construction of the ITER scientific installation began in 2010. In the centre of the platform, in the Tokamak Complex, the ITER machine is taking shape. (Photo: ITER Organization/EJF Riche, September 2023) (Click to view larger version...)
Construction of the ITER scientific installation began in 2010. In the centre of the platform, in the Tokamak Complex, the ITER machine is taking shape. (Photo: ITER Organization/EJF Riche, September 2023)
The ITER Project is currently under construction on a 180-hectare site in southern France.
 
Thirty-nine buildings and technical areas house the ITER Tokamak and its plant systems. The heart of the facility—the Tokamak Building—is a seven-storey structure in reinforced concrete that sits 13 metres below the platform level and 60 metres above. Pre-assembly of Tokamak components takes place in the adjacent Assembly Hall. Other auxiliary buildings in the vicinity of the Tokamak Building include cooling towers, electrical installations, a control room, facilities for the management of waste, and the cryogenics plant that will provide liquid helium to cool the ITER magnets.
 
Europe, as part of its commitments to the project, is building nearly all of the platform buildings and site infrastructure.
 
Each building, once structurally complete, is handed over to the ITER Organization for the installation and assembly of equipment. According to the European Domestic Agency, the number of workers involved in site construction peaked in 2017-2018 at approximately 2,000 people. Now, although there are still European construction teams on site, a large additional workforce is contributing to machine and plant assembly and installation operations.  An estimated 5,000 people are regularly present on the worksite, including management, engineering and supervisory teams from the ITER Organization, the European Domestic Agency, and their contractors.

The successful integration and assembly of over one million components (ten million parts) built in the ITER Members' factories around the world and delivered to the ITER site constitutes a tremendous logistics and engineering challenge. 
 
For more information (and images) about machine and plant assembly, please see these pages.
 
Main construction milestones:
 
2006            Signature of the ITER Agreement
2007-2009    Land clearing and levelling
2010-2014    Ground support structure and seismic foundations for the Tokamak Complex
2010-2024    Construction of ITER plant and auxiliary buildings (excepting the Hot Cell Facility)
2020             Machine assembly begins
2023             Completion of Tokamak Building civil works
2024             Announcement of updated ITER Baseline schedule
 
Take a virtual tour of ITER construction here.