Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Also in this issue

  • Cross-section of a niobium-tin "billet" produced in Korea for ITER's toroidal field coils. Billets are drawn down to strands of less than one millimetre in diameter to form the building blocks of the superconductors. © Peter Ginter

    Superconductivity: it gets the current flowing

    To create the optimal conditions for fusion in a tokamak, the hot gas (plasma) must be confined in the centre of the vessel. This is the job of powerful magnet [...]

    Read more

  • Whatever their age or their knowledge of science and technology, the 1,300 visitors to ITER during the Open Doors Day 4 October were able to measure the scale of the project, its challenges and its potential.

    1,300 visitors "at home" at ITER

    When preparation work began on the platform in Saint-Paul-lez-Durance more than seven years ago, ITER was a mystery for many people in neighbouring towns and v [...]

    Read more

  • Six storyes high, made of 800 tons of steel, the Sector Sub-Assembly tools will work in concert to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit.

    Twin giants to pre-assemble the vacuum vessel

    As the doors of the Assembly Building open to admit the first vacuum vessel sectors shipped from manufacturing sites in Europe or Korea, two imposing custom-bu [...]

    Read more

  • By reflecting the hues of the passing seasons, the mirror-like stainless steel will express, according to ENIA, "the precision of the research work being performed inside of the buildings."

    Mirror, mirror on the platform

    How much latitude does an architect have when considering how best to integrate the ITER buildings into the surrounding landscape? Not a lot, says architect S [...]

    Read more

Mag Archives

Last pour, first delivery

Two milestones in ITER construction were achieved as summer 2014 drew to a close—the last pour of the Tokamak Complex basemat on 27 August and the delivery of the first completed components on 4 September.

It was the last of fifteen "segments" poured to complete the 9,300 m² concrete basemat that will support the Tokamak Complex and its 400,000 tons of building, machinery and equipment—a perfectly circular, central plot that will support the ITER machine.

14,000 m³ of concrete, 3,600 tons of rebar, 8 months of work—the ''floor'' of the Tokamak Complex was finalized on 27 August 2014. (Click to view larger version...)
14,000 m³ of concrete, 3,600 tons of rebar, 8 months of work—the ''floor'' of the Tokamak Complex was finalized on 27 August 2014.
Well before dawn on 27 August, the team was in place to prepare the worksite and position the concrete pumps. Ahead was a 12-hour continuous pour—some 865 m³ of concrete formulated to penetrate in and around the tight weave of rebar, particularly dense in this area of the basemat.

The completion of the Tokamak Complex basemat has opened the way to a new phase of ITER construction: with the "floor" in place, work will now start on the walls. The 80 x 120 metre Complex, housing the Tokamak, Diagnostic and Tritium buildings, is a seven-storey structure that will reach 60 metres at its tallest point.

Shipped from New York on 5 August 2014, the 12 surge arrestors that were delivered to ITER on 4 September had a high symbolic value. As the first completed components to reach the site, they usher in a new phase on the road to building ITER. (Click to view larger version...)
Shipped from New York on 5 August 2014, the 12 surge arrestors that were delivered to ITER on 4 September had a high symbolic value. As the first completed components to reach the site, they usher in a new phase on the road to building ITER.
Early September, another ITER milestone was celebrated as the very first completed components—12 high voltage surge arrestors shipped from the United States—were delivered to the site and stored. Destined for the installation's steady state electrical system, they'll take their place between the 400 kV switchyard and the transformers that will feed power to the ITER plant systems and components in order to provide protection from the type of major voltage surge that can be caused by lightning.

One truck, just a few crates ... but a delivery with important symbolic value, as it kicks off a new phase for ITER. Over the next years thousands of components will be shipped from around the world for installation into the ITER Tokamak and plant. This first delivery was the opportunity to test the administrative, technical, industrial and regulatory procedures that will accompany the procurement of all of these machine and plant components.