Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

  • Education | 13th ITER International School announced

    The 13th ITER International School (IIS) will be held from 9 to 13 December in Nagoya hosted by National Institute for Fusion Science (NIFS), Japan. The subject [...]

    Read more

  • Open Doors Day | Having fun while discovering ITER

    A public event on Saturday 13 April draws a big crowd. It was a beautiful, summer-like day on Saturday 13 April. Perfect for a journey into ITER. Nearly 800 mem [...]

    Read more

  • Fusion world | Increased awareness in a changing landscape

    The world of fusion research is changing fast, and world leaders are taking notice. The large public projects that occupied centre stage for the past decades ar [...]

    Read more

Of Interest

See archived entries

Project management

The elephant must be sliced

Any way you cut it, ITER is fantastically complex. Whether you're counting components or the lines in the machine assembly schedule, or taking a closer look at the project's vast procurement sharing scheme ... complexity needs to be managed in ITER. Hans-Henrich Altfeld, head of the Project Control Office, tells us how it's done.

ITER is complexity to be managed and the best way to do it is by ''slicing the elephant,'' explains Hans-Henrich Altfeld, head of the ITER Project Control Office. (Click to view larger version...)
ITER is complexity to be managed and the best way to do it is by ''slicing the elephant,'' explains Hans-Henrich Altfeld, head of the ITER Project Control Office.
From a lay person's view, what makes the ITER Project stand out is the sheer scale of the undertaking in terms of size and budget, its level of scientific and technological innovation and, not least, its relevance to critical global issues.


A project manager looks at it differently. With costs of EUR 20 billion, millions of parts, supply chains spanning the entire globe and a multi-cultural workforce coming from 35 different countries, ITER is complexity to be managed. Altfeld has experience in the domain, having worked as a senior project manager for Airbus and in the automotive industry. His experience in mega projects is serving him now.

"Whereas at Airbus, 79,000 design drawings were needed for the development of the A380, at ITER we stand at 250,000 design drawings."

Why is it important to address complexity? "What we ultimately want to achieve is control over the project," Altfeld explains. "We do this by reducing its complexity. This will give us better control of the project, which is a precondition for success."

 (Click to view larger version...)
Hans-Henrich Altfeld has thirty years of international experience in program and project management. He worked for over twelve years at Airbus and four years at Johnson Controls Automotive Seating. He has led large production plants, managed various business transformation projects and been responsible for the building of entire factories.

Since January 2017 he heads the Project Control Office. 

Recognizing complexity is the first step to addressing and ultimately reducing it. But, how is this done with a project of this magnitude? "You have to slice the elephant," says Altfeld. Slicing the elephant? "You essentially cut the project into smaller units. This allows you to address the project in incremental steps that you manage individually."


At ITER, the "slicing of the elephant" follows the contour lines of other highly complex projects. "The ITER Project is not particularly unique in this sense," says Altfeld. It includes breaking down the entire project into systems, sub-systems and components; breaking down all required work into work packages; establishing and cascading requirements along with dedicated verification and validation plans; establishing a schedule governance which incorporates the activities of the Domestic Agencies, and developing a coordinate system for the ITER site.

"Slicing the elephant" requires tight management and strict control of the interfaces and interdependencies between the separate "slices."

"There is still room for improvement in this area," says Altfeld. "For ITER—as a first-of-a-kind experiment—it was impossible to identify all interfaces and interdependencies right from the beginning. It is learning by doing."

One example of the need for stricter interface control surfaced at a recent workshop. Considering the number of components the ITER machine will consist of and the extended time frame for construction, clear and understandable coding of components will ensure their correct placement in the machine. In previous years, not all components were coded early in the process, during the design phase. Now, these parts need to be coded retroactively—a situation that new procedures will correct in the future.

Another lesson learned from other mega projects is the importance of identifying and prioritizing risks and opportunities. These can be of a technical nature, or relating more to the project control issues of schedule or cost. New risk and opportunity management practices are helping the project to anticipate challenges in critical-path areas such as Tokamak Building construction and vacuum vessel manufacturing.

"Identifying the potential risks to delivery allows the project to develop and implement response actions," concludes Altfeld. "In the same way, it is of utmost importance to 'hunt' for opportunities—to proceed more quickly or optimize assembly sequences, for example—to make sure they can be cashed in on."



return to the latest published articles