Logo
You're currently reading the news digest published from 24 June 2024 to 3 July 2024.
Featured (3)
Video (1)
Press (28)
Featured

"A good day for the world"

A little before 2:00 a.m. on 17 April 2020 a powerful transport trailer, accompanied by dozens of technical and security vehicles, passed the gates of the ITER site. On the trailer's flatbed, tightly wrapped in protective material, sat a massive D-shaped load—the first of the 19 toroidal field coils (including one spare) required for the ITER tokamak. The nature of the component was familiar. For close to ten years we had watched it slowly come to life, from the early manufacturing of the superconducting niobium-tin strands, to the cabling and jacketing of conductor and the machining of radial plates, up until the final insertion into steel cases. But being confronted by that mighty presence was a whole different experience. The size of the component brought home just how exceptionally large the ITER tokamak would be. This first toroidal field coil (TF9) was procured by Europe and had travelled a relatively short distance from its manufacturing site in Italy. Eight days later, on Saturday 25 April, a second coil (TF12) arrived at the ITER site, having completed a 10,000-kilometre journey from Japan. Over the following three-and-a-half years all 19 coils (10 from Europe, 9 from Japan) were to be faultlessly manufactured and delivered. It is this unique industrial and logistical achievement that was celebrated on Monday 1 July, in the presence of some of the "historical figures" of the great toroidal field coil venture and the high representatives of the ITER stakeholders involved in this strategic project-within-the-project. Masahito Moriyama, the Japanese Minister of Education, Culture, Sports, Science and Technology (MEXT), placed the first-of-a-kind achievement in the broader context of fusion's ''potential to solve global energy and environmental problems simultaneously.'' Indeed, as ITER Director-General Pietro Barabaschi said in his opening address, the 17-metre-tall ITER toroidal field coils "look like science-fiction." Forty times the mass of CERN's Atlas magnets, presently the largest operating magnets in the world, they represent "a huge step forward" in superconducting magnet technology. "Created by human minds and hands," these technological marvels are more than "the backbone of the ITER machine." Having brought together "essentially all the ITER Members" in their design and fabrication process they represent "the very soul" of the project. International collaboration, "the integrated effort," and the "technological breakthroughs" that led to the successful procurement of the 19 ITER toroidal field coils was also highlighted by Masahito Moriyama, the Japanese Minister of Education, Culture, Sports, Science and Technology (MEXT), and Gilberto Pichetto Fratin, the Italian Minister of Environment and Energy Security. Both placed the first-of-a-kind achievement in the broader context of fusion's "potential to solve global energy and environmental problems simultaneously" (Moriyama) and a "future of clean, safe and practically inexhaustible energy" (Pichetto Fratin). Like his counterpart at the Japanese Domestic Agency, Norikiyo Koizumi, Alessandro Bonito-Oliva, who oversaw the European procurement of the ITER toroidal field coils, received a symbolic award for his contribution. "A good day for the world" is how Kadri Simson, the European Union Commissioner for Energy characterized this first day of July. "The toroidal field coils have long been considered amongst the most complex components to manufacture," she said in a video address. "In Europe, under the leadership of Fusion for Energy, more 40 companies and 700 people were involved in coil fabrication. Some of the companies involved now apply the technologies and know-how they developed for ITER to other projects. This demonstrates the added value of working for ITER." For the Chinese Ambassador to France, Shaye Lu, who recalled the signature of the conductor Procurement Arrangement in 2008 and its completion eight years later, "ITER [...] embodies humanity's hope for peace and sustainable development. It is the "little sun that will shine upon the shared future of the human community." The scope and complexity of manufacturing the ITER toroidal field coils, the multiple technological and organizational challenges faced by the industry in Europe and in Japan were perfectly illustrated by the 8-minute film that was projected to the audience. As fabrication processes unfolded, from strands to cable-in-conduct conductor, from "double pancakes modules" winding to case insertion, from final machining to shipping and delivery, one took the full measure of what had been accomplished. Fabrication of the toroidal field coils "required top expertise, large facilities with special equipment, a lot of coordination between the different interfaces and a procurement strategy that could provide all the above," said Marc Lachaise, Director of the European Domestic Agency Fusion for Energy. "From the outset, it could have seemed impossible... Our teams made it possible." ''A good day for the world'' is how Kadri Simson, the European Union Commissioner for Energy, characterized this first day of July. ''I'm very pleased to see how this project inspires numerous private initiatives in fusion and creates benefits for all involved actors,'' she said in her video address. Like Fusion for Energy in Europe, QST—Japan's National Institutes for Quantum Science and Technology—organized the Japanese procurement of the ITER toroidal field coils. Its President, Shigeo Koyasu, expressed his gratitude to "all the previous ITER Director-Generals" and to all the men and women of ITER whose efforts are contributing to the realization of "a peaceful and prosperous society."A few of these emblematic contributors, whether engineers or scientists, logistics specialists or industry representatives, were then called on stage. First among them, Michel Huguet was introduced by Director-General Barabaschi as "the father of these coils." The physicist, who had joined the French fusion program in 1969 and had headed for more than ten years (1992-2003) the ITER Joint Work Site in Naka, Japan, reminded the audience that the achievement that was being celebrated originated 32 years ago, with the launch of the Engineering Design Activities (EDA), the founding moment in the long history of the project.The presence onstage of Kiyoshi Okuno, Neil Mitchell, Alessandro Bonito Oliva and Norikiyo Koizumi was a potent symbol of what Michel Huguet once called the "multi-generation chain of fusion builders," which he compared to "medieval cathedral builders" engaged in a project of "unprecedented timescale." On 1 July, the ITER cathedral was far from completed, but 18 of its key elements were. And that was definitely worth celebrating.See a video on the making of the ITER toroidal field coils here. See a video of the event here.

Family day at ITER

Whether partners, children, parents or close relatives, they probably hear about ITER every day. But few of them, until last Sunday, ever had the opportunity to see ITER with their own eyes, experience the expanse of the construction site, the size of the components, the "pulse" (even on a Sunday) of one the largest and most enthralling science projects in the world. On Sunday 30 June the "Family Day" that ITER Communication organized provided just that opportunity to 650 ITER personnel and their relatives. The program included "self guided'' visits, presentations in the amphitheatre, plasma, magnet and vacuum experiments, and a spectacular immersion in virtual reality. Partners, children, parents and close relatives of ITER personnel will continue to hear about ITER every day. Having experienced the reality behind the words and the stories, one can safely bet they will ask for more...

New baseline to prioritize robust start to exploitation

At a press conference on 3 July attended by approximately 200 journalists and key ITER stakeholders, ITER Director-General Pietro Barabaschi answered questions about the new project plan—the "baseline"—that is under evaluation by the ITER Organization's governing body. The top-line messages were: ITER's programmatic goals have not changed; and the first experimental phase of the machine, although delayed, will be much more consequential than originally planned.  The new baseline replaces the plan that had been used as a reference since 2016, and which for some time had been publicly acknowledged to be no longer "feasible, practical or optimal." The major drivers of delay—the Covid pandemic that slowed factory work and inspections and added delay to the supply chain, and the repair required on key machine components—also created new opportunities to reconsider ITER's path to assembly and operation. Whereas the 2016 plan made a low-energy, low-current first plasma the first major milestone—to be immediately followed by a multiyear assembly period to install major in-vessel components—the delay offered the project a new way forward: starting operations with a more complete machine. The new baseline has been designed to prioritize a robust start to scientific exploitation. With a divertor, blanket shield blocks and other key components and systems in place, ITER's first operational phase, Start of Research Operation, will feature hydrogen and deuterium-deuterium plasmas that culminate in the operation of the machine in long pulses at full magnetic energy and plasma current. "Instead of a symbolic first plasma that I liken to a 'machine test' achieved with a relatively 'naked' machine," says ITER Director-General Barabaschi, "in the new plan we will start by performing real research with plasma, leading to the demonstration of integrated commissioning at full magnetic energy and current. This is a robust start that will allow us to make up for some of the delay the project has accumulated, and also provide for better risk mitigation on the way to achieving project goals." The new baseline also includes more time for integrated commissioning, the testing of some magnet coils at 4 K (minus 269 ° C), additional heating, and the availability of disruption mitigation. The material for the plasma-facing blanket first wall is also changing from beryllium to tungsten. "You will not find a fusion reactor project that plans to use beryllium," says the Director-General. "This modification makes our experiment more relevant to next-phase devices." In the new plan, the achievement of full magnetic energy in 2036 represents a delay of three years relative to the 2016 reference, while the start of the deuterium-tritium operation phase in 2039 represents a delay of four years. The Director-General was careful to stress that the "mission elements" of the project will not be modified—demonstrating the integration of systems needed for industrial-scale fusion operations; achieving a burning plasma with 500 MW of thermal fusion power for 50 MW input heating power (Q≥10); and 400-second pulses, reaching thermal equilibria (in plasma and structures). As for the cost of the new plans, the ITER Director-General said that the additional cost for the ITER Organization amounts to EUR 5 billion—a figure that is still under review by the ITER Members. ITER costs historically have been difficult to estimate precisely because the bulk of financial contributions are provided in-kind by ITER Members in the form of components, for most of which Member governments are not required to publish their actual costs. Read the summary document that was provided to journalists here.  Some questions and answers from the press conference: Is ITER still relevant in the context of the immediate pressure of climate change and the emergence of fusion startups? Fusion cannot arrive in time to solve the problems our planet faces today, and investment in other technologies, known and unknown, is absolutely needed," said Barabaschi. "But I expect fusion will make a difference when it arrives, and let's not forget that there is not just the problem of solving global warming ... energy is also needed for life on Earth. Fusion commercialization will require new ideas to make things simpler and cheaper, as well as a number of enabling technologies that ITER will not resolve. I very much welcome the new ideas that are popping up around the globe. Fusion should be thought of as an innovation program, and we all have our part to play. Can ITER compete with startups announcing shorter timescales to fusion deployment? We cannot comment on the timescales of other projects; we can only be transparent about our own. We have committed to helping other projects to achieve their goals. Fusion has long been a science where international cooperation is the norm. And I consider that we have to give back to the private sector what we have achieved with the public money of our stakeholders. We hosted a Private Sector Fusion Workshop at ITER in May as a start, and we will work to fulfil the needs that were expressed to us. We also welcome the recent statement by the G7 in support of fusion, and the support that we receive from the International Atomic Energy Agency. Is changing the first wall material at this stage a risky decision? There is no such thing as an "easy" first wall material. Research on this topic is absolutely essential and new ideas are welcome. That said, we have a lot of tokamak results in tungsten from around the world that gives us confidence that at ITER we can reach our Q=10 programmatic goal.
Video

ITER magnet completion event

Press

ITER: In Search of the Holy Grail of Energy

https://www.renewablematter.eu/en/ITER-nuclear-fusion-In-Search-of-the-Holy-Grail-of-Energy

ITER fusion reactor hit by massive decade-long delay and €5bn price hike

https://physicsworld.com/a/iter-fusion-reactor-hit-by-massive-decade-long-delay-and-e5bn-price-hike/

World's largest nuclear reactor to make magnetic field 250,000x stronger than Earth's

https://interestingengineering.com/energy/worlds-largest-fusion-reactor-iter

Costs Jump at World's Biggest Nuclear-Fusion Project With Delays

https://www.bloomberg.com/news/articles/2024-07-03/costs-jump-at-world-s-biggest-nuclear-fusion-project-with-delays

The sun in the jar: A W&M summer school helps lead the way toward AI-powered nuclear fusion

https://news.wm.edu/2024/06/24/the-sun-in-the-jar-a-wm-summer-school-helps-lead-the-way-towards-ai-powered-nuclear-fusion/

Multinational fusion energy project marks completion of its most complex magnet system

https://phys.org/news/2024-07-multinational-fusion-energy-complex-magnet.html

Nucleare, dieci 10 maxi bobine italiane a Caradache per Iter prodotte da Asg Superconductors

https://genova.repubblica.it/cronaca/2024/07/01/news/nucleare_dieci_10_maxi_bobine_italiane_a_caradache_per_iter_prodotte_da_asg_superconductors-423345759/

RWE Nuclear und Focused Energy vor Absichtserklärung

https://www.faz.net/aktuell/wirtschaft/unternehmen/rwe-nuclear-und-focus-energy-unterzeichnen-absichtserklaerung-19826681.html

Fusionsexperiment Iter: Der stärkste Magnet aller Zeiten wird fertig

https://www.derstandard.at/consent/tcf/story/3000000226604/fusionsexperiment-iter-der-staerkste-magnet-aller-zeiten-wird-fertig

Historic ITER International Fusion Energy Project Marks Completion of its Most Complex Magnet System

https://apnews.com/press-release/ein-presswire-newsmatics/north-korea-japan-9fd11e2db36a090e3a6d2d1edf32feaa

Why is ITER valuable for the U.S.?

https://www.ans.org/news/article-6149/why-is-iter-valuable-for-the-us/

Focus on Fusion: July 2024, Volume 67, Number 8 (paywall)

https://www.ans.org/pubs/magazines/nn/

Pichetto Fratin: "Italy shares and supports the commitment towards nuclear fusion"

https://www.agenzianova.com/en/news/pichetto-fratin-litalia-shares-and-supports-the-commitment-towards-nuclear-fusion/

Pichetto Fratin : « L'Italie partage et soutient l'engagement en faveur de la fusion nucléaire »

https://www.agenzianova.com/fr/news/pichetto-fratin-litalia-partage-et-soutient-l%27engagement-en-faveur-de-la-fusion-nucl%C3%A9aire/

Strom aus Kernfusion? • Vom Lawson Kriterium zu ITER und Laserfusion (audio 40'05")

https://www.spektrum.de/video/strom-aus-kernfusion/2221607

Mitigating tokamak plasma disruption bags "Plasma Physics and Controlled Fusion" Outstanding Paper Prize

https://physicsworld.com/a/mitigating-tokamak-plasma-disruption-bags-plasma-physics-and-controlled-fusion-outstanding-paper-prize/

Building Trust in Fusion Energy

https://cfs.energy/news-and-media/building-trust-in-fusion-energy

Is the world's biggest fusion experiment dead after new delay to 2035?

https://www.newscientist.com/article/2437314-is-the-worlds-biggest-fusion-experiment-dead-after-new-delay-to-2035/

JT-60SA: Transitioning from Construction to Scientific Exploitation

https://euro-fusion.org/eurofusion-news/jt60sa_01/

Fusion Future Accelerates With DOE Funding

https://eepower.com/news/fusion-future-accelerates-with-doe-funding/#

Is Nuclear fusion always 20 years away? (audio 25'30")

https://player.fm/series/all-things-policy/is-nuclear-fusion-always-20-years-away

Using supercomputer researchers discover new clues to improving fusion confinement

https://www.ornl.gov/news/using-ornls-frontier-supercomputer-researchers-discover-new-clues-improving-fusion-confinement

ITER fusion project sets new 2035 start date

https://www.neimagazine.com/news/iter-fusion-project-sets-new-2035-start-date/

한국형 핵융합연구로 'KSTAR', 16년 운전에도 '건재' 확인

https://news.zum.com/articles/91457265

IAEA Supports Fusion Research with a New Comprehensive Database

https://www.iaea.org/newscenter/news/iaea-supports-fusion-research-with-a-new-comprehensive-database

FIA Launches "Commercializing Fusion Energy" Paper

https://www.fusionindustryassociation.org/fia-launches-commercializing-fusion-energy-paper/

Fusion 2030 — A Roadmap for Canada

https://www.cns-snc.ca/about-cns/divisions/fusion/fusion-energy-science-and-technology-cns-fest/fusion-2030-a-roadmap-for-canada/

ITER leaders propose a decade of work before D-D operations in 2035

https://www.ans.org/news/article-6156/iter-leaders-propose-a-decade-of-work-before-dd-operations-in-2035/