Careful insertion, perfect fit
				
													
					Critical infrastructure components are routed through ITER’s thick concrete bioshield with the help of a little human ingenuity and bespoke construction solutions.   
	
											
									
	In an elaborate nine-month operation that has involved laying temporary rail lines and setting up aerial buckets to avoid concrete drips, 18 openings in the bioshield reserved for tokamak cooling water system piping have been âpluggedâ ahead of schedule. Achieved in September 2025, this critical milestone opens the way for the start of work on the water piping infrastructure known as the âjungle gym.âA three-metre-thick concrete bioshield around the ITER machine provides essential nuclear safety functions such as confinement, fire sectorization and radiation shielding. However, openings, or âpenetrations,â are needed in the wall so everything from busbars to magnet feeders can feed into the tokamak. Once these critical infrastructure components are routed through, the penetrations need to be backfilled with concrete to meet the same safety standards as the rest of the wall structure.Among the most important openings are the 18 located at Level 3 of the Tokamak Building that are for the massive tokamak cooling water system pipes. Each opening requires a 6.5-tonne âpenetration assemblyâ designed to fit snugly into the bioshield opening and serve as a connecting point for the inlets and outlets that travel from the cooling plant, through the Tokamak Building, and into the tokamak. âWe had to find solutions to optimize the penetrations sequence and to overcome an exceptionally demanding schedule so we could move ahead with assembly as quickly as possible, and we achieved this,â says Raphael Hernandez, the Construction Coordination Manager who oversaw the project. âWe found the right synergies and managed the co-activity well.â
							
			
	
		
		
		
			
		
  							
  						
    
        
                  
  
	  		
			
		
              
      
    
  
										
				
			The penetration assemblies inside the concrete bioshield serve as the interfaces that connect the cooling pipes as they travel between the cooling plant and into the tokamak pit.
		
	
	
											
									
	The penetration assemblies are composed of outer sleeves maintained within support plates and separators. The sleeves will allow two families of pipes bundles to cross through the bioshieldâone providing cooling for the blanket, divertor and plasma-facing components (called the IBED set); and the other for the vacuum vessel sectors. The penetration assemblies also have bellows to deal with the movements of the cryostat and the pipes due to thermal expansion, as those pipes will carry pressurized water that can reach temperatures as high as 250 °C. Originally, the schedule provided a two-year installation window for the completion of tokamak cooling water bioshield penetrations, but in the end this schedule was accelerated. From the arrival of the first components in August 2024 to the completion of all 18 openings in September 2025, the work took just over one year.Two strategies were adopted that permitted the acceleration. First, instead of waiting for each penetration assembly to be fully complete, including pipe bundles, some were inserted with only the outer sleeves or just one of the two pipe families. The remaining components were installed while work was underway on other penetrations, which reduced the overall project time because the work was being done concurrently rather than sequentially.
							
			
	
		
		
		
			
		
  							
  						
    
        
                  
  
	  		
			
		
              
      
    
  
										
				
			To speed up installation, some of the penetration assemblies were inserted into the bioshield without their pipe bundles. Here, a pipe bundle is being carefully manoeuvred into the waiting sleeve. 
		
	
	
											
									
	The second time-saving strategy was to install the penetration assemblies based on other work being carried out in the tokamak pit. This required extensive logistics and resourcesâas the scaffolding had to be assembled and disassembled in different places around the tokamak pitâbut allowed for greater flexibility in scheduling than if the entire pit needed to be closed for bioshield penetration activities.Besides the schedule, the biggest challenge was how to safely and cleanly slide the 6.5-tonne penetration assemblies into place. Instead of lowering them by crane into the pit and placing them in the openings, it was decided to insert them from the other side of the bioshield, working from inside the Tokamak Building. The team installed a temporary rail system in the galleries around the bioshield to move the penetration assemblies and glide them into place. However, safeguards were required to avoid an accidental and uncontrolled trajectory that could cause damage.The penetration designer Pascal De Boe and his team came up with three levels of protection. First, there were chains and metal blocks to stop the penetration assemblies if they began to slide too quickly. Second, wedges would deploy so they would jam against the bioshield wall and not fall into the pit. As a final defence measure, a crush pipe at the end of the track would act as a bumper.âWe had to sharpen our pencils several times in order to optimize the installation strategy,â says De Boe, project leader for the In-Field Engineering team. âThatâs why we had so many precautions, but thankfully none were required because the operation was very well prepared.â
							
			
	
		
		
		
			
		
  							
  						
    
        
                  
  
	  		
			
		
              
      
    
  
										
				
			In this picture from May 2025, the progress on the penetration assemblies is visible. The first penetrations to be completed are situated where one vacuum vessel sector is installed and another is expected imminently. In the other areas of the pit, work continues behind the protective tents that hide the scaffolding from view.
		
	
	
											
									
	Once placed in the waiting openings, the penetration assemblies had to be aligned with a positioning tolerance of only five millimetres. Each one had fiducial markers for laser guidance and the engineers used trigonometry to make calculations against references in the building to ensure they were a perfect fit.After that, the backfilling of the openings with concrete was carried out to maintain the security requirements of the bioshield. Special formwork was built with Teflon and aluminium, and aerial buckets were rigged on cranes on the machine side of the bioshield to be sure no concrete spilled out and caused contamination. The coating of the pit-facing sides of the penetration assemblies with multi-fibre protective material and the removal of the scaffolding were completed in September.âFinishing the civil works on the penetrations clears the scaffolding in the tokamak pit and allows for the installation of the piping infrastructure on the other side of the bioshield,â says Jonathan Baker, the construction engineer for the tokamak cooling water system who managed the pipe assembly. âThis is a significant step forward.âWatch how penetration assemblies get (carefully) inserted into waiting openings in the time-lapse video below. (Video courtesy of 4TCC1.)