What's new @ ITERThis is our all brand new RSS stream to keep in touch with ITERFri, 18 Oct 2013 14:00:00 +0100http://www.iter.orgen-usFEATURED: Industrial milestone | Korea completes first vacuum vessel sectorhttps://www.iter.org/newsline/-/3433https://www.iter.org/newsline/-/34332020-04-28 00:00:00Tue, 28 Apr 2020 00:00:00 +0100 <div class="field-image"> <a href="https://www.iter.org/newsline/-/3433"><img typeof="foaf:Image" src="https://www.iter.org/img/crop-900-85/www/content/com/Lists/Stories/Attachments/3433/vv_sector_6-finalized.jpg" alt="" /></a> </div> <div class="field-body"><p>Just over a decade ago, the ITER Organization completed the build-to-print design of the ITER vacuum vessel—a 5,000-tonne steel chamber that would house the world's first reactor-scale fusion plasma. This month, engineering design became reality, as the first 40-degree sector came off the production line in Korea. &#160; In a series of factory acceptance tests carried out in March and early April, including the critical pneumatic pressure and helium leak tests¹, manufacturer Hyundai Heavy Industries and procuring Domestic Agency ITER Korea were able to demonstrate that vacuum vessel sector #6 fully met all ITER Organization technical specifications. The 440-tonne sector will now be packed for shipment. 'It is testimony to the ingenuity, skill, dedication and perseverance of the industrial contractors in Korea, of the Korean Domestic Agency in its oversight, and of the wider ITER Vacuum Vessel Project Team that this first-of-a-kind component—one of the most challenging of the ITER machine—has been successfully manufactured,' according to ITER Director-General Bernard Bigot. 'The pride and sense of accomplishment of all those involved is commensurate with the size and complexity of the challenge.' &#160; Korean manufacturers faced numerous challenges as they undertook the realization of the first sector of the vacuum vessel manufacturing program&#58; &#160; Nuclear vessel regulations&#58; As the first confinement barrier for plasma, the ITER vacuum vessel is subject to very specific codes and regulations covering material procurement, design and analysis, fabrication, welding, and examination. Seven permanent inspectors (five from the ITER Organization Vacuum Vessel Project Team² and two Agreed Notified Body³ inspectors representing the French Nuclear Safety Authority, ASN), as well as the Hyundai quality departments, controlled a total of 45,000 inspection points and 500 manufacturing documents. In December 2019, French nuclear experts travelled to Korea to perform a final in-depth inspection on the near-completed sector. &#160; 100% volumetric inspection of welds&#58; The vacuum vessel is a heavily welded structure, with steel plate thicknesses of up to 60 mm, a large number of permanent attachments, and many narrow areas and&#160;areas with difficult access. The team developed 60 special scanning techniques of phased array ultrasonic tests (PAUT) to verify gap welds of up to 21 mm with very reliable quality. The total length of full penetration welds on the sector is nearly 1,000 metres. &#160; Tight tolerances&#58;&#160; The prediction and control of welding stress and distortion is difficult with such a high density of welding joints. In order to increase confidence that the stringent tolerance requirements for the final geometry could be achieved, the Hyundai team in collaboration with the Vacuum Vessel Project Team pioneered a &quot;virtual fitting&quot; technique, in which the known 3D dimensional measurements of the segments were matched virtually with specialized software (SpatialAnalyzer) and reverse engineered according to the result. &#160; Beginning eight years ago, the teams began producing the first of four poloidal segments. Although different in design (see graph), each segment required the same step-by-step fabrication route&#58; contractors formed and welded the inner shell, attached inner ribs and support housings, installed in-wall shielding blocks, and—in the final activity to complete the segments—fitted and welded the outer shell. (See gallery below for more detail.) By September 2019, the segments were ready to be assembled into the final D-shaped sector, and upper and lower port stub extensions (procured by Russia and Korea respectively) could be attached through splice plates. &#160; 'Through all of these activities, the main point is that we pioneered traceability, recording all activities prior, during and post manufacturing with approved formats of documents,' affirms Chang Ho Choi, who leads the Vacuum Vessel Project Team. 'This is important because vacuum vessel procurement involves four ITER Members, and that final assembly will be carried out by ITER Organization contractors on site. Proper documentation, therefore, will make everyone's job easier. Our collaboration is very well established at this point, after 53 monthly meetings over the years and 10 on-site meetings that included a lot of knowledge sharing and visits to manufacturing facilities. This gives us confidence as we head toward the most important moment of all&#58; machine assembly.' &#160; When ITER vacuum vessel sector #6 arrives at ITER this summer, it will be brought into the Assembly Building and transferred by overhead crane to a laydown area. After a final helium leak test¹ and site acceptance test, the component will be ready for handover to ITER Organization assembly contractor responsible for the vessel (TAC2) for a series of installation activities (diagnostics, instrumentation and cable trays on the outer shell). &#160; A ceremony on 20 April&#160;at Hyundai Heavy Industries in Ulsan, Korea, was attended by Byungseon Jeong, First Assistant Minister, Ministry of Science and ICT; Young-seuk Han, President and CEO of Hyundai Heavy Industries; Sukjae Yoo, President of Korea's National Fusion Research Institute; Kijung Jung, Director General of ITER Korea; and more than 30 experts. &#160; 'Deep and close collaboration among ITER Korea, the European Domestic Agency Fusion for Energy, ITER Russia, and the ITER Vacuum Vessel Project Team is the key driving force of our achievement,' explained Kijung Jung. &quot;It allows the most challenging and complicated issues to be resolved and will lead our ITER Project to success.&quot; &#160; ¹ Due to international travel restrictions related to the global coronavirus crisis, the ITER Organization observer/quality control inspector could not be present for the pressure and leak tests. These acceptance activities will be performed again when the component reaches ITER.² The Vacuum Vessel Project Team reunites staff from the European, Korean, Indian and Russian Domestic Agencies with staff from the ITER Organization in regular meetings to improve the overall efficiency of vacuum vessel procurement execution.³ An Agreed Notified Body (ANB) is&#160;authorized by the French Nuclear Regulator ASN to assess the conformity of components in the pressure equipment category (ESPN). &#160; See the gallery below for more detail on the fabrication steps. &#160; View videos from Hyundai Heavy Industries (fabrication) and ITER Korea (final ceremony) on the completion milestone. &#160; &#160;</p></div> https://www.iter.org/img/crop-900-85/www/content/com/Lists/Stories/Attachments/3433/vv_sector_6-finalized.jpghttps://www.iter.org/doc/www/content/com/Lists/Stories/Attachments/3433/mag_vv_sector_6-after_hlt_2.jpgFEATURED: Last leg of a long journey | Japan delivers D-shaped coilhttps://www.iter.org/newsline/-/3434https://www.iter.org/newsline/-/34342020-04-28 00:00:00Tue, 28 Apr 2020 00:00:00 +0100 <div class="field-image"> <a href="https://www.iter.org/newsline/-/3434"><img typeof="foaf:Image" src="https://www.iter.org/img/crop-600-85/www/content/com/Lists/Stories/Attachments/3434/tf12_peyrolles_small.jpg" alt="" /></a> </div> <div class="field-body"><p>What makes a component unique, beyond its size and weight, is the sum of work and the sophistication of the technologies that go into its fabrication. In this respect, the ITER D-shaped toroidal field coils are in a league of their own: standing 17 metres high, weighing close to 350 tonnes, they are among the largest superconducting magnets ever built and their production, from initial design to finalization, spanned three decades, involved more than one thousand people and mobilized 50 different companies and institutions. Such exceptional components, which form the core elements of the ITER Tokamak, require exceptional care in their handling and transport. Every movement, whether during loading and unloading operations, sea voyage, or land journey, must be anticipated and carefully planned. The land journey along the 104-kilometre-long ITER Itinerary, between Marseille industrial harbour and the ITER site, is particularly challenging. Some of the country roads that the convoy travels are only a few centimetres wider than the steel frame that encases the coil; several turns are sharp; a few climbs are steep. Hauling such heavy loads (600 tonnes between component and transport vehicle) requires more horsepower than regular trucks can provide, and more gently distributed. For the ITER toroidal field coils and the other ultra-heavy loads that will follow, the Dutch transporter Mammoet, operating as a contractor to ITER global logistics provider DAHER, developed a prototype trailer whose twin 'power packs' deliver the horsepower equivalent of six conventional truck tractors. The prototype trailer made his first outing on 13 April to transport the first of the ITER D-shaped coils (TF#9), procured by Europe, from Marseille industrial harbour at Fos-sur-Mer to the ITER site. Having delivered the load on 17 April, it was back at Fos-sur-Mer the following day to load a second coil (TF#12) that had arrived from Japan ten days earlier. TF#12 travelled the last leg of its journey from the other side of the world during the night of Friday 24 to Saturday 25 April (see gallery below). By then, both coils were safely 'home' on the ITER site—TF#9 stored in a dedicated workshop; TF#12 being moved to temporary storage in the recently vacated Cryostat Workshop. A towering presence in their respective storage places, both coils will soon enter into 'mechanical preparatory activities' such as welding cooling pipes, attaching clamps, and welding interfaces) prior to being integrated into the assembly process. There will be several more occasions to be impressed by the sight of a D-shaped coil convoy snaking along narrow country roads and passing sleeping villages in a flurry of rotating light. There are still 17 such loads to be delivered to ITER over the next three years. The next in line, TF #13, left the Mitsubishi Heavy Industries facility in Futami, Japan, on 26 April. Click here to view a video of TF #12 delivery and the move into temporary storage.</p></div> https://www.iter.org/img/crop-600-85/www/content/com/Lists/Stories/Attachments/3434/tf12_peyrolles_small.jpghttps://www.iter.org/doc/www/content/com/Lists/Stories/Attachments/3434/tf12_peyrolles_small.jpgFEATURED: Deliveries | From Russia by roadhttps://www.iter.org/newsline/-/3437https://www.iter.org/newsline/-/34372020-04-28 00:00:00Tue, 28 Apr 2020 00:00:00 +0100 <div class="field-image"> <a href="https://www.iter.org/newsline/-/3437"><img typeof="foaf:Image" src="https://www.iter.org/img/crop-600-85/www/content/com/Lists/Stories/Attachments/3437/rf_trucks_electro-tech.jpg" alt="" /></a> </div> <div class="field-body"><p>Six trucks filled with electrotechnical equipment for the ITER installation have arrived from the Efremov Institute in Russia. Over several weeks in April, a convoy of tractor-trailers carrying DC busbars for the ITER magnets, resisters and other electrotechnical equipment for the ITER installation travelled the 3,000 kilometres separating Saint Petersburg, Russia, and the ITER site. Four other trucks are on their way. The equipment they contain was developed and manufactured at the Efremov Institute (NIIEFA) for Russia's State Atomic Energy Corporation ROSATOM. The fabrication and supply of switching equipment, busbars, energy absorbing resistors and control racks for the power supply and protection of the ITER superconducting magnets is the largest procurement package of 12 under ITER Russia's responsibility. Over five kilometres of steel-jacketed aluminium busbars insulated in epoxy wrapping and actively cooled by a constant flow of pressurized water are required to deliver DC power to the ITER magnets. The busbar network, along with the fast discharge and switching network units, will almost fully occupy two levels of the Diagnostics Building. The Russian Domestic Agency, the Efremov Institute, and the ITER Organization took all the necessary steps to have the equipment reach ITER on time and prevent any delay in the installation schedule. </p></div> https://www.iter.org/img/crop-600-85/www/content/com/Lists/Stories/Attachments/3437/rf_trucks_electro-tech.jpghttps://www.iter.org/doc/www/content/com/Lists/Stories/Attachments/3437/rf_trucks_electro-tech.jpgVIDEO: The story of vacuum vessel sector #6https://www.iter.org/news/videos/516https://www.iter.org/news/videos/5162020-04-27 11:11:59Mon, 27 Apr 2020 11:11:59 +0100 <div class="field-image"> <a href="https://www.iter.org/news/videos/516"><img typeof="foaf:Image" src="https://www.iter.org/media/all/img/dyn_vid_thmb/?frame=5&wd=500&id=516" alt="" /></a> </div> https://www.iter.org/img/crop-600-85/all/content/com/video/VV6_manufacturing_Korea_HyundaiHeavyIndustries.JPGPRESS: 핵융합연, 국제핵융합로 손상 막을 기술 검증 | 연합뉴스https://www.yna.co.kr/view/AKR20200428059200063https://www.yna.co.kr/view/AKR202004280592000632020-04-28 00:00:00Tue, 28 Apr 2020 00:00:00 +0100PRESS: Is Fusion Really Close To Reality? Yes, Thanks To Machine Learninghttps://www.forbes.com/sites/jeffmcmahon/2020/04/27/is-fusion-really-closer-to-reality-yes-thanks-to-machine-learning/#10e7e86d652bhttps://www.forbes.com/sites/jeffmcmahon/2020/04/27/is-fusion-really-closer-to-reality-yes-thanks-to-machine-learning/#10e7e86d652b2020-04-27 00:00:00Mon, 27 Apr 2020 00:00:00 +0100PRESS: Iter : au coeur d'un convoi de l'extrême (réservé aux abonnés)https://www.laprovence.com/article/edition-aix-pays-daix/5972065/iter-le-convoi-de-lextreme.htmlhttps://www.laprovence.com/article/edition-aix-pays-daix/5972065/iter-le-convoi-de-lextreme.html2020-04-27 00:00:00Mon, 27 Apr 2020 00:00:00 +0100PRESS: Россия передала электротехническое оборудование на площадку создания реактора ИТЭР https://nauka.tass.ru/nauka/8313365https://nauka.tass.ru/nauka/83133652020-04-23 00:00:00Thu, 23 Apr 2020 00:00:00 +0100PRESS: Le chantier Iter se poursuit, malgré le confinement (réservé aux abonnés)https://www.lemoniteur.fr/photo/le-chantier-iter-se-poursuit-malgre-le-confinement.2087526/des-ponts-roulants-manipulent-une-piece-de-plusieurs-tonnes-le-28-mars-2020.1https://www.lemoniteur.fr/photo/le-chantier-iter-se-poursuit-malgre-le-confinement.2087526/des-ponts-roulants-manipulent-une-piece-de-plusieurs-tonnes-le-28-mars-2020.12020-04-23 00:00:00Thu, 23 Apr 2020 00:00:00 +0100PRESS: Mastering the power of the sun: Europe delivers first magnet in the history of ITERhttps://ec.europa.eu/info/news/mastering-power-sun-europe-delivers-first-magnet-history-iter-2020-apr-22_enhttps://ec.europa.eu/info/news/mastering-power-sun-europe-delivers-first-magnet-history-iter-2020-apr-22_en2020-04-23 00:00:00Thu, 23 Apr 2020 00:00:00 +0100PRESS: 中核集团人造太阳"心脏"安装开启http://www.mei.net.cn/jxgy/202004/1587613942.htmlhttp://www.mei.net.cn/jxgy/202004/1587613942.html2020-04-23 00:00:00Thu, 23 Apr 2020 00:00:00 +0100PRESS: Fusion Energy Gets Ready to Shine—Finallyhttps://www.wired.com/story/fusion-energy-iter-reactor-ready-to-shine/https://www.wired.com/story/fusion-energy-iter-reactor-ready-to-shine/2020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: 섭씨 1억도 인공태양 담는 그릇 만들었다https://news.chosun.com/site/data/html_dir/2020/04/20/2020042002308.htmlhttps://news.chosun.com/site/data/html_dir/2020/04/20/2020042002308.html2020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: 국가핵융합연구소, 인공태양 '국제핵융합실험로(ITER)'진공용기 최초 섹터 완성https://www.etnews.com/20200420000237https://www.etnews.com/202004200002372020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: '국제핵융합실험로(ITER) 진공용기 최초 섹터 완성 기념식'https://news.v.daum.net/v/20200420160920932https://news.v.daum.net/v/202004201609209322020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: '인공태양 담을 그릇' 국제핵융합실험로 진공용기 첫 완성http://www.joongdo.co.kr/main/view.php?key=20200420010007112http://www.joongdo.co.kr/main/view.php?key=202004200100071122020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: Fusione, arrivato il primo supermagnete di Iterhttps://corrierequotidiano.it/scienze/fusione-arrivato-il-primo-supermagnete-di-iter/https://corrierequotidiano.it/scienze/fusione-arrivato-il-primo-supermagnete-di-iter/2020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: 현대重-핵융합硏, 국제핵융합실험로 진공용기 완성http://www.dt.co.kr/contents.html?article_no=2020042102101531731002http://www.dt.co.kr/contents.html?article_no=20200421021015317310022020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: 인공태양 'ITER' 핵심장치 국내 첫 완성...현대重서 기념식http://www.busan.com/view/busan/view.php?code=2020042014312480321http://www.busan.com/view/busan/view.php?code=20200420143124803212020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100PRESS: 정병선 제1차관, 국제핵융합실험로(ITER) 진공용기 최초 섹터 완성 기념식 참석http://www.portalnews.co.kr/news/article.html?no=136469http://www.portalnews.co.kr/news/article.html?no=1364692020-04-21 00:00:00Tue, 21 Apr 2020 00:00:00 +0100