Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Five years later...

Five years ago, on Wednesday 4 August 2010, a lone power shovel began removing the first cubic metres of rock and top soil from the northern side of the ITER platform. In six months, some 230,000 cubic metres of material were excavated for the Tokamak Complex.

In five years, the moonlike landscape of 2010 has turned into a bustling environment of tall cranes, concrete and rebar, and steel columns rising as high as a 15-storey building.<br /><br /> (Click to view larger version...)
In five years, the moonlike landscape of 2010 has turned into a bustling environment of tall cranes, concrete and rebar, and steel columns rising as high as a 15-storey building.

In parallel, 250 metres away, bulldozers and scrapers were levelling the ground at the site of a large winding facility for some of ITER's largest magnets. After creating a smooth "sub-base," the concrete floor slab was poured and, within 18 months, a 257-metre-long steel structure erected.

Since then, the anti-seismic foundations of the Tokamak Complex have been set into place, drainage and precipitation networks finalized, a 400 kV electrical substation installed, and progress made on the Assembly Building—the 60-metre-high edifice that will host the pre-assembly operations for ITER machine components.

In five years, the moonlike landscape of 2010 has turned into a bustling environment of tall cranes, concrete and rebar, and steel columns rising as high as a 15-storey building.

The number of workers on the construction site will increase from 400 to 1,000 by the end of the year as the pace of construction accelerates and a number of ancillary buildings begin to rise. More than EUR 4 billion worth of contracts signed for ITER construction are acquiring a tangible shape on the ITER platform... (See the slideshows in this issue.)

As Newsline closes for its traditional summer recess, work inside of the offices and on the platform will continue at a determined pace, providing us with plenty of stories to report.
 
We'll be back in late August with our next issue!



return to the latest published articles