Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The crown's jewels

    They are the jewels of the concrete crown that will support the combined mass of the Tokamak and its surrounding cryostat: 18 perfectly polished, chrome-plated [...]

    Read more

  • "Making the best of fusion installations in Europe"

    With the recent addition of the Ukraine's Kharkov Institute for Physics and Technology (KIPT), the EUROfusion consortium now encompasses 30 European fusion labo [...]

    Read more

  • New cryostat manufacturing milestone

    They all gathered—members of the ITER-India team and contractor Larsen & Toubro—to mark a portentous moment: the start of manufacturing on the upper cylinde [...]

    Read more

  • Key power supply elements pass tests in Russia

    Since the signature of a Procurement Arrangement in 2011 with Russia for switching networks, fast discharge units, DC busbars and instrumentation—all key elemen [...]

    Read more

  • First vessel subassembly achieved in Europe

    Nine massive steel sectors deliveredby the Domestic Agencies of Europe (five sectors) and Korea (four sectors) will be welded together on site during the assemb [...]

    Read more

Of Interest

See archived articles

ITER Council endorses updated project schedule

-ITER Communication

During the Nineteenth Meeting of the ITER Council held last week from 16 to 17 November, representatives of the ITER Members reviewed the complete updated project schedule as proposed by the ITER Organization. The schedule, which covers the period up to First Plasma in 2025 and on to Deuterium-Tritium Operation in 2035, was approved by all Members.

During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035. (Click to view larger version...)
During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035.
Building on renewed confidence achieved through the past 18 months of sustained strong performance in construction and manufacturing, the updated 2016-2035 schedule reflects the consensus and integrated efforts of the ITER Organization and the seven Domestic Agencies.

The overall project schedule was approved by all ITER Members, and the overall project cost was approved ad referendum, meaning that it will now fall to each Member to seek approval of project costs through respective governmental budget processes.

The Council stressed that the successful completion of all 19 project milestones for 2016, on time and on budget, provides tangible evidence of full adherence to commitments by all Members. These milestones had been approved by the ITER Council one year ago as a way to track project momentum while discussions were underway on the long-term schedule.

The updated schedule through Deuterium-Tritium Operation (2035) selects a "staged approach" after First Plasma as a way to increase confidence and minimize risk. In the staged approach to assembling ITER, assembly phases will alternate with periods of operation.

Read the full press release in English or French.
View the photo gallery from the Nineteenth ITER Council (IC-19) below.