Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The crown's jewels

    They are the jewels of the concrete crown that will support the combined mass of the Tokamak and its surrounding cryostat: 18 perfectly polished, chrome-plated [...]

    Read more

  • "Making the best of fusion installations in Europe"

    With the recent addition of the Ukraine's Kharkov Institute for Physics and Technology (KIPT), the EUROfusion consortium now encompasses 30 European fusion labo [...]

    Read more

  • New cryostat manufacturing milestone

    They all gathered—members of the ITER-India team and contractor Larsen & Toubro—to mark a portentous moment: the start of manufacturing on the upper cylinde [...]

    Read more

  • Key power supply elements pass tests in Russia

    Since the signature of a Procurement Arrangement in 2011 with Russia for switching networks, fast discharge units, DC busbars and instrumentation—all key elemen [...]

    Read more

  • First vessel subassembly achieved in Europe

    Nine massive steel sectors deliveredby the Domestic Agencies of Europe (five sectors) and Korea (four sectors) will be welded together on site during the assemb [...]

    Read more

Of Interest

See archived articles

A wide angle on progress

Whether captured from the top of a crane or from a drone hovering at an altitude of a few dozen metres, the ITER site is always spectacular.
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level). (Click to view larger version...)
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level).
After almost seven years of construction most of the elements of the ITER scientific installation are visible, albeit in various stages of completion.

Progress has been strong in the centre of the Tokamak Complex, where the bioshield now rises two storeys above the level of the platform and has become one of the most noticeable features of the worksite from overhead. Construction progress is also evident in the zones reserved for the ITER cryoplant and the cooling towers/basins.

Other milestones have been achieved that aren't so visible from the sky, however. On 30 March, one of the four transformers for steady-state electrical network was briefly connected to the French grid—opening the way for full switchyard "energization" in the coming months.

And that's not all: inside the Poloidal Field Coils Winding Facility teams are about to start on the first production winding for poloidal field coil #5; in the Radio Frequency Building 80 percent of the steel structure of has been installed and the intermediate floor slabs realized; and in the magnet power conversion area the first "top beam" was installed on columns last week.

But better see it with your own eyes in the photo gallery below ...


return to the latest published articles