Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Summer postcards from the ITER worksite

    The latest harvest of ITER construction photos may be taken from the same point—the tallest crane on site—but there is always an abundance of new detail to be g [...]

    Read more

  • The ring fortress

    ITER'ssteel-and-concretebioshield has become the definingfeature of Tokamak Complex construction. Twolevels only remain to be poured (out of six). It is a 'rin [...]

    Read more

  • The wave factory

    A year ago, work was just beginning on the steel reinforcement for the building's foundation slab. The Radio Frequency Heating Building is now nearing the last [...]

    Read more

  • It's all happening inside

    Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has lookedfrom afar like a finished project. Butinside, tea [...]

    Read more

  • Along skid row

    They look like perfectly aligned emergency housing units. But of course they're not: the 18 concrete structures in the ITER cryoplant are massive pads that will [...]

    Read more

Of Interest

See archived articles

A wide angle on progress

Whether captured from the top of a crane or from a drone hovering at an altitude of a few dozen metres, the ITER site is always spectacular.
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level). (Click to view larger version...)
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level).
After almost seven years of construction most of the elements of the ITER scientific installation are visible, albeit in various stages of completion.

Progress has been strong in the centre of the Tokamak Complex, where the bioshield now rises two storeys above the level of the platform and has become one of the most noticeable features of the worksite from overhead. Construction progress is also evident in the zones reserved for the ITER cryoplant and the cooling towers/basins.

Other milestones have been achieved that aren't so visible from the sky, however. On 30 March, one of the four transformers for steady-state electrical network was briefly connected to the French grid—opening the way for full switchyard "energization" in the coming months.

And that's not all: inside the Poloidal Field Coils Winding Facility teams are about to start on the first production winding for poloidal field coil #5; in the Radio Frequency Building 80 percent of the steel structure of has been installed and the intermediate floor slabs realized; and in the magnet power conversion area the first "top beam" was installed on columns last week.

But better see it with your own eyes in the photo gallery below ...


return to the latest published articles