Every day, Metéo France delivers a special forecast for the ITER construction site. "Our main interest is to know if a thunderstorm is forecasted or not," Guy reports. "If that is the case, we have to stop the works and evacuate the site."
If the weather report permits, a surface area of 500 m² is poured in one go—a procedure that will be repeated 21 times over the next weeks and months to fill in the Seismic Pit basemat, which can be compared in size to a football stadium. Each pour represents approximately 800 m³ of concrete, produced in the two batching plants located on site.
The Seismic Pit basemat will be the first level of reinforcement for the ITER Tokamak Complex. On top of this first level, workers are currently pouring 493 concrete plinths at regular distances: these are the 1.7-metre-high pillars that will support the anti-seismic bearings. The flexible structure of these bearings, made alternately of layers of metal and rubber, will serve as "shock absorbers" in the case of seismic motion.
The basemat concrete is a special mixture that offers the durability required for nuclear installations (70 years instead of the standard 50). "We use only the smallest possible proportion of cement plus additives that reduce the chemical heating of the concrete as it dries," explains Thierry Lebault, project director for GTM, part of the French consortium Vinci that is in charge of the concrete works for ITER. "If the concrete becomes too hot and dries too quickly, you risk internal cracking."
As we said ... concrete is a delicate material.