Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Worksite | First pillars for the crane hall

    For the overhead cranes to deliver machine components into the Tokamak assembly pit, the rails that carry them need to be extended some 80 metres beyond the tem [...]

    Read more

  • Transport | 300 tonnes of equipment on its way to ITER

    A specially designed assembly tool and elements of the cryostat and vacuum vessel thermal shields are part of the shipments travelling now from Korea to ITER. W [...]

    Read more

  • Fusion world | A new tokamak in town

    After EAST in China and WEST in France, another of the cardinal points of the compass has been chosen to name a tokamak. Introducing NORTH—the NORdic Tokamak de [...]

    Read more

  • Opportunities | Bringing the ITER Business Forum to Washington

    Every second year, a two-day ITER Business Forum is held to invite existing and potential suppliers for the ITER Project—laboratories, universities, and compani [...]

    Read more

  • World Energy Congress | Fusion "at a time of transition"

    In the United Arab Emirates, Abu Dhabi is often referred to as a tourism hotspot that combines luxury and ancient traditions. In September, Abu Dhabi was in the [...]

    Read more

Of Interest

See archived entries

Ballet in the sky (Part II)

Since ''acrobats'' began bolting together the pre-assembled arms of the pylons, work on the 400kV power line has provided some spectacular sights. © CEA/Corinne Guis (Click to view larger version...)
Since ''acrobats'' began bolting together the pre-assembled arms of the pylons, work on the 400kV power line has provided some spectacular sights. © CEA/Corinne Guis
Installing a 400kV power line requires, in the following order: a crane, a team of acrobats, a truck-mounted winch and, finally, a helicopter.

In difficult areas—such as the ridge that separates the ITER site from CEA-Cadarache to the east of the present Headquarters Building—helicopters are used to position temporary "pulling cables" that will later be attached to the actual power cables and pulled by a ground-based winch.

''Pulling cables'', positioned by the helicopter hovering above the ridge were safely attached to the temporary pulleys. © Agence ITER France (Click to view larger version...)
''Pulling cables'', positioned by the helicopter hovering above the ridge were safely attached to the temporary pulleys. © Agence ITER France
Such an operation was organized last Wednesday 1 February after the sky had cleared following the previous day's heavy snowfall. "Pulling cables" were installed between pylon 18, located at CEA-Cadarache's highest point, and pylon 15, located close to canteen n°2.

The same operation, this time between pylons 15 and 10, is scheduled for 28 February.

Work on the 400keV power line, which began in September, continues to provide spectacular entertainment.


return to the latest published articles