Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Image of the week | The platform's quasi-final appearance

    Since preparation work began in 2007 on the stretch of land that was to host the 42-hectare ITER platform, regular photographic surveys have been organized to d [...]

    Read more

  • Cryopumps | Preparing for the cold tests

    Before being delivered to ITER, the torus and cryostat cryopumps are submitted to a  comprehensive series of factory acceptance tests. This is not sufficie [...]

    Read more

  • Fusion technologies | Closing a fusion schism

    Historically, inertial confinement and magnetic confinement approaches to fusion have been parallel, separate processes. The ITER Private Sector Fusion Workshop [...]

    Read more

  • Toroidal field coil celebration | "A good day for the world"

    A little before 2:00 a.m. on 17 April 2020 a powerful transport trailer, accompanied by dozens of technical and security vehicles, passed the gates of the I [...]

    Read more

  • Press conference | New baseline to prioritize robust start to exploitation

    At a press conference on 3 July attended by approximately 200 journalists and key ITER stakeholders, ITER Director-General Pietro Barabaschi answered questions [...]

    Read more

Of Interest

See archived entries

Ballet in the sky (Part II)

Since ''acrobats'' began bolting together the pre-assembled arms of the pylons, work on the 400kV power line has provided some spectacular sights. © CEA/Corinne Guis (Click to view larger version...)
Since ''acrobats'' began bolting together the pre-assembled arms of the pylons, work on the 400kV power line has provided some spectacular sights. © CEA/Corinne Guis
Installing a 400kV power line requires, in the following order: a crane, a team of acrobats, a truck-mounted winch and, finally, a helicopter.

In difficult areas—such as the ridge that separates the ITER site from CEA-Cadarache to the east of the present Headquarters Building—helicopters are used to position temporary "pulling cables" that will later be attached to the actual power cables and pulled by a ground-based winch.

''Pulling cables'', positioned by the helicopter hovering above the ridge were safely attached to the temporary pulleys. © Agence ITER France (Click to view larger version...)
''Pulling cables'', positioned by the helicopter hovering above the ridge were safely attached to the temporary pulleys. © Agence ITER France
Such an operation was organized last Wednesday 1 February after the sky had cleared following the previous day's heavy snowfall. "Pulling cables" were installed between pylon 18, located at CEA-Cadarache's highest point, and pylon 15, located close to canteen n°2.

The same operation, this time between pylons 15 and 10, is scheduled for 28 February.

Work on the 400keV power line, which began in September, continues to provide spectacular entertainment.


return to the latest published articles