Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Ballet in the sky (Part II)

Since ''acrobats'' began bolting together the pre-assembled arms of the pylons, work on the 400kV power line has provided some spectacular sights. © CEA/Corinne Guis (Click to view larger version...)
Since ''acrobats'' began bolting together the pre-assembled arms of the pylons, work on the 400kV power line has provided some spectacular sights. © CEA/Corinne Guis
Installing a 400kV power line requires, in the following order: a crane, a team of acrobats, a truck-mounted winch and, finally, a helicopter.

In difficult areas—such as the ridge that separates the ITER site from CEA-Cadarache to the east of the present Headquarters Building—helicopters are used to position temporary "pulling cables" that will later be attached to the actual power cables and pulled by a ground-based winch.

''Pulling cables'', positioned by the helicopter hovering above the ridge were safely attached to the temporary pulleys. © Agence ITER France (Click to view larger version...)
''Pulling cables'', positioned by the helicopter hovering above the ridge were safely attached to the temporary pulleys. © Agence ITER France
Such an operation was organized last Wednesday 1 February after the sky had cleared following the previous day's heavy snowfall. "Pulling cables" were installed between pylon 18, located at CEA-Cadarache's highest point, and pylon 15, located close to canteen n°2.

The same operation, this time between pylons 15 and 10, is scheduled for 28 February.

Work on the 400keV power line, which began in September, continues to provide spectacular entertainment.


return to the latest published articles