Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Toroidal field copper dummy ready in Europe

Aris Apollonatos, Fusion for Energy

The ITER toroidal field copper conductor dummy compacted and spooled. (Click to view larger version...)
The ITER toroidal field copper conductor dummy compacted and spooled.
The Italian Consortium for Applied Superconductivity (ENEA, Tratos Cavi, Criotec) has completed the commissioning of the jacketing line and the equipment needed for the manufacturing of conductors for ITER and JT-60SA in less than one year.

In the fields of Chivasso, 20 km outside Turin, a manufacturing facility has been erected to fabricate and carry out the rigorous qualification process for the conductors. Outside the facility, a platform measuring 800 metres has been assembled to guide the 10-tonne, 760-metre-long toroidal field copper dummy conductor into the facility. 

The jacketing was completed after assembling all the sub-components provided by contractors. Tratos Cavi produced the cable which was then handed over to Criotec to be inserted into stainless steel tube composed of 58 individual sections welded together. Subsequently, the dummy conductor was compacted and spooled.

Following the successful validation process, the conductor was packed into a 100-cubic-metre box for shipment to a facility in La Spezia (Italy), where the consortium responsible for the fabrication of the toroidal field winding packs will carry out trials. 

As part of the toroidal field conductor qualification, the Italian Consortium for Applied Superconductivity (ICAS) is expected to produce three toroidal field dummy conductors. After the successful completion of the copper conductor, two superconducting dummies will be fabricated within the first semester of this year. Once the qualification process is completed, ICAS will have to deliver 27 production lengths for the ITER toroidal field coils.

For more information click here.


return to the latest published articles