Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Men of measure

    'Neither snow nor rain nor heat nor gloom of night stays these couriers from the swift completion of their appointed rounds.' [From the Greek historian Herodotu [...]

    Read more

  • The end of a nine-year journey

    In December, as toroidal field conductor unit length #133 came off the production line, the ITER community celebrated a major milestone—the end of a nine-year p [...]

    Read more

  • The little coupler that could

    Concrete and steel met at the end of the 19th century, never to part again. From their encounter a new material was born that revolutionized construction techni [...]

    Read more

  • The radio power house

    The steel structure extension that's being erected on the northeast side of the Assembly Hall is for a large building that will be densely packed with power sup [...]

    Read more

  • Spaceport ITER

    At nightfall, when buildings, work areas, roads and parking lots light up, the ITER site looks like an alien spaceport. Drenched in the yellow glow of sodium l [...]

    Read more

Of Interest

See archived articles

Europe will manufacture 60 Divertor Cassettes

-Robert Arnoux

Featured here are Cassette Assembly CA #4 et CA #11. There are 19 variances in the diagnostics arrangements within the 54 ITER Divertor cassettes—and as many integration issues... (Click to view larger version...)
Featured here are Cassette Assembly CA #4 et CA #11. There are 19 variances in the diagnostics arrangements within the 54 ITER Divertor cassettes—and as many integration issues...
This is a place that will feel very much like the surface of the Sun. When deuterium-tritium operation begins, the ITER divertor will carry a heat load twenty thousand times higher than that of a hot July day in Provence.

As if that wasn't enough, the divertor structure will also have to withstand tremendous magnetic forces that will press and pull with a force on the order of one hundred tons.

An essential component of the ITER machine, the divertor is also one of the most challenging to build, assemble and install.

The ITER divertor acts as the Tokamak's exhaust system, running toroidally along the bottom of the vacuum vessel, extracting helium ash from the burning plasma. It is split into 54 cassettes, each containing a plasma-facing "dome", inner and outer "targets," and a number of diagnostic systems. There are 19 variances in the diagnostics arrangements and as many integration issues ...

 
Each nine-ton cassette will be installed inside the vacuum vessel through remote handling operations. The highly complex and delicate installation sequences are being demonstrated and validated at the ITER Divertor Test Platform Facility in Tampere, Finland.

The Procurement Arrangement for the Divertor Cassette and Assembly was signed on Tuesday, 19 April. From left to right, DG Motojima; Paola Miele, Procurement & Contracts senior administrative officer; Frédéric Escourbiac, Tungsten Divertor Section leader and Mario Merola, head of the Internal Components Division. (Click to view larger version...)
The Procurement Arrangement for the Divertor Cassette and Assembly was signed on Tuesday, 19 April. From left to right, DG Motojima; Paola Miele, Procurement & Contracts senior administrative officer; Frédéric Escourbiac, Tungsten Divertor Section leader and Mario Merola, head of the Internal Components Division.
The Procurement Arrangement for the Divertor Cassette and Assembly was signed on Tuesday, 19 April. It covers the manufacturing by Europe of 60 cassette bodies (54 cassettes plus 6 spares) and the integration of the components and diagnostics systems provided by other Domestic Agencies as part of different procurement packages.

"The key challenges in this PA are: one, the manufacturing tolerance to meet the interfaces (on the order of a fraction of a millimetre); and two, the assembly sequence of the different divertor components," explains Mario Merola, head of the Internal Components Division. "Planning and coordination will be paramount."

Following the production of a full-scale prototype for assembly trials, series production should begin in 2015. The present schedule plans for the installation of all 54 cassettes beginning in 2021 during the second phase of ITER assembly; the divertor will only be needed when hydrogen-helium operation begins in 2022.



return to the latest published articles