Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The crown's jewels

    They are the jewels of the concrete crown that will support the combined mass of the Tokamak and its surrounding cryostat: 18 perfectly polished, chrome-plated [...]

    Read more

  • "Making the best of fusion installations in Europe"

    With the recent addition of the Ukraine's Kharkov Institute for Physics and Technology (KIPT), the EUROfusion consortium now encompasses 30 European fusion labo [...]

    Read more

  • New cryostat manufacturing milestone

    They all gathered—members of the ITER-India team and contractor Larsen & Toubro—to mark a portentous moment: the start of manufacturing on the upper cylinde [...]

    Read more

  • Key power supply elements pass tests in Russia

    Since the signature of a Procurement Arrangement in 2011 with Russia for switching networks, fast discharge units, DC busbars and instrumentation—all key elemen [...]

    Read more

  • First vessel subassembly achieved in Europe

    Nine massive steel sectors deliveredby the Domestic Agencies of Europe (five sectors) and Korea (four sectors) will be welded together on site during the assemb [...]

    Read more

Of Interest

See archived articles

Crane vs crane

As action will soon move toward the adjoining Assembly Building area, two of the four cranes that operated over the Pit were dismantled this week. (Click to view larger version...)
As action will soon move toward the adjoining Assembly Building area, two of the four cranes that operated over the Pit were dismantled this week.
With the 493rd and final antiseismic pad installed and the retaining walls finalized, a relative quiet has settled over the ITER Tokamak Pit.

As action will soon move toward the adjoining Assembly Building area, two of the four cranes that operated over the Pit were dismantled this week.

Crane C4, located on the northwest corner of the work site, was taken down on Monday 23 April. Two days later, a similar operation was performed on crane C3 in the south corner.

Dismantling a 50-metre-high tower crane is a delicate and spectacular operation. First, it's necessary to remove the concrete counterweights that balance the 65-metre-long boom. Once the 15 tonnes of counterweights have been lowered, crane dismantling specialists climb into the boom to begin the detachment process.

''The only real difficulty,'' explains a crane dismantling specialist ''is the wind. Also ... finding enough room to lay the boom on the ground ...'' (Click to view larger version...)
''The only real difficulty,'' explains a crane dismantling specialist ''is the wind. Also ... finding enough room to lay the boom on the ground ...''
With the boom hanging solidly from a mobile crane, specialists can begin unscrewing the large bolts that connect the 14.7-tonne boom to the tower. Once freed, the lifting crane slowly moves it down to the ground where it will await further dismantling.

"The only real difficulty," explains dismantling specialist Armand Depit of MAGSUD, based in Aix-en-Provence, "is the wind. Also ... finding enough room to lay the boom on the ground ..."

On Wednesday, as crane C3 was dismantled, the air was perfectly still on the ITER platform and there was still plenty of room—although not for long—in the Tokamak Pit work site perimeter.

The dismantling operation went smoothly and took less than one hour and a half.


return to the latest published articles