A long-expected letter

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Augmented reality | Assessing the future work environment

    As part of their collaboration within the Site Support Agreement*, ITER and its neighbour CEA are developing a novel approach to explore, analyze and assess the [...]

    Read more

  • Diagnostics and instrumentation | First welding on the vacuum vessel

    Beginning in 2035, ITER will open a window into "burning plasmas"—a state of matter that exists in the core of stars only. Observing, assessing and mo [...]

    Read more

  • Assembly | Machining workshop opens on site

    Construction of an on-site machining workshop began in December 2019 and was completed on schedule in September 2020.The new workshop will be operated by the D [...]

    Read more

  • Neutral Beam Test Facility | Power is ready for the prototype injector

    The European Domestic Agency has carried out successful site acceptance tests at the ITER Neutral Beam Test Facility on power supply equipment installed ov [...]

    Read more

  • In-vessel coils | First components arrive on site

    ITER has received the first shipments of mineral-insulated conductor for ITER's in-vessel coils. The first lengths are destined for winding and bending trials a [...]

    Read more

Of Interest

See archived entries

A long-expected letter

Licensing a nuclear installation requires the production of thousands of pages of technical documents, like the seven-volume, 5,243-page DAC files that provide an in-depth description of the ITER installation. (Click to view larger version...)
Licensing a nuclear installation requires the production of thousands of pages of technical documents, like the seven-volume, 5,243-page DAC files that provide an in-depth description of the ITER installation.
The official letter from the French Safety Authority (Agence de sûreté nucléaire - ASN) that the ITER Organization received on 20 June marks a major milestone in a lengthy, complex and demanding process that began a year and a half ago.

After months of in-depth technical examination, the ASN has judged that the ITER Organization's proposal on the operational conditions and design of the installation fulfils the expected safety requirements at this stage of the licensing process.

In simpler words, this is the long-expected green light meaning that the French government authorizes the construction of ITER. 

Licensing a nuclear installation takes considerable time, requires the production of thousands of pages of technical documents, and mobilizes scores of experts and institutions. ITER is the first fusion facility to undergo this licensing procedure in France.

As a consequence, at decisive stages in the procedure like the one announced this week, there is a feeling of deep satisfaction among all those who were involved in the process.

In practical terms, a peer committee of ASN and ITER Safety, Quality & Security experts will now work on drafting the decree that will be submitted to the French government's signature. This highly detailed document can be described as "the safety contract" that will bind the ITER Organization (as nuclear operator) and the French State for the whole duration of the installation's lifetime.

The final decree that should be signed by the French President or his Prime Minister is expected to be issued in the last months of 2012.


return to the latest published articles