Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Written procedures are her game

Krista Dulon

 (Click to view larger version...)
As an international organization—and one applying for nuclear licensing in France—ITER is required to have a well-documented management system, with approved procedures describing the process flow for every area of the project.

Since 2008, the Quality Assurance Division has been developing the Management and Quality Program (MQP), a process-based system that organizes ITER's management documents into a structure governing relations, procedures, and working instructions.

"The written procedures contained in the MQP program basically instruct end users how to do their work," says Florence Tadjer, who joined the Division in April. "But of course it is not enough that these documents exist: they must also be well understood and applied throughout the project."

As MQP Liaison Officer for the Administration and Plasma Operation Directorates, Florence will work in an advisory role with process "owners" on management documents, ensuring that the proper rules are followed to write documents, and deciding whether the document contains the type of guidelines that should be incorporated into the MQP framework or not. "In fact, not every departmental document needs to be part of the MQP," says Florence. "On the other hand, it is also my role to identify those documents that should be incorporated."

Florence comes to ITER from the International Atomic Energy Agency (IAEA), where she was a quality manager in the laboratory responsible for analyzing safeguard samples from nuclear facilities. It was her responsibility to maintain the laboratory's quality certification by updating the quality management system and conducting regular audits in order to make sure that the quality system was well implemented in all areas of the laboratory.

"Training and auditing are part of the quality manager's job," insists Florence. At ITER, the team of Liaison Officers will work to improve the MQP documentation, and expend a lot of effort to communicate about the program and make sure that training is offered on the implementation of the system.

"ITER is a young organization and things are still evolving. A lot remains to be done and I know I'll enjoy the lack of routine!"