Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The crown's jewels

    They are the jewels of the concrete crown that will support the combined mass of the Tokamak and its surrounding cryostat: 18 perfectly polished, chrome-plated [...]

    Read more

  • "Making the best of fusion installations in Europe"

    With the recent addition of the Ukraine's Kharkov Institute for Physics and Technology (KIPT), the EUROfusion consortium now encompasses 30 European fusion labo [...]

    Read more

  • New cryostat manufacturing milestone

    They all gathered—members of the ITER-India team and contractor Larsen & Toubro—to mark a portentous moment: the start of manufacturing on the upper cylinde [...]

    Read more

  • Key power supply elements pass tests in Russia

    Since the signature of a Procurement Arrangement in 2011 with Russia for switching networks, fast discharge units, DC busbars and instrumentation—all key elemen [...]

    Read more

  • First vessel subassembly achieved in Europe

    Nine massive steel sectors deliveredby the Domestic Agencies of Europe (five sectors) and Korea (four sectors) will be welded together on site during the assemb [...]

    Read more

Of Interest

See archived articles

Remember when it was smooth?

The 42-hectare ITER platform used to be as smooth and as flat as a billiard table. These days it's hard to find a clear patch.

Site adaptation activities (modified entrances and roadworks), digging and pipe-laying for critical networks and galleries, portable office construction, and network installation for the new Contractors Area in the southwest corner of the site have resulted in deep trenches in some areas and mounds of dirt in others.

The "quietest" area of the site is 15-metres below the surface in the Seismic Isolation Pit. But not for long: GTM Construction will soon begin propping and formwork in preparation for concrete pouring for the B2 slab—the "upper basemat" and actual floor of the 360,000-tonne Tokamak Complex.

Work progresses on the Assembly Building basemat. Two sections of structural concrete, or plots, have been poured since November and reinforcement activities are ongoing. (Click to view larger version...)
Work progresses on the Assembly Building basemat. Two sections of structural concrete, or plots, have been poured since November and reinforcement activities are ongoing.


Workers dig galleries along the exterior of the Assembly Building to accommodate services (electricity, evacuation, piping ...) (Click to view larger version...)
Workers dig galleries along the exterior of the Assembly Building to accommodate services (electricity, evacuation, piping ...)


The foundations of the Assembly Building abut the retaining wall of the Tokamak Complex. The two buildings will be the tallest on the platform, rising to a height of 60 metres. (Click to view larger version...)
The foundations of the Assembly Building abut the retaining wall of the Tokamak Complex. The two buildings will be the tallest on the platform, rising to a height of 60 metres.


Propping and formwork will begin at the end of the month for the upper basemat of the Tokamak Pit: by late October 2013, the seismic protection system for the Tokamak Complex will be completely hidden from view. (Click to view larger version...)
Propping and formwork will begin at the end of the month for the upper basemat of the Tokamak Pit: by late October 2013, the seismic protection system for the Tokamak Complex will be completely hidden from view.


Critical network piping will crisscross the ITER site for precipitation drainage and cooling water release. In this section of the network, the pipes have been installed and backfilling is underway. (Click to view larger version...)
Critical network piping will crisscross the ITER site for precipitation drainage and cooling water release. In this section of the network, the pipes have been installed and backfilling is underway.




return to the latest published articles