Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Remember when it was smooth?

The 42-hectare ITER platform used to be as smooth and as flat as a billiard table. These days it's hard to find a clear patch.

Site adaptation activities (modified entrances and roadworks), digging and pipe-laying for critical networks and galleries, portable office construction, and network installation for the new Contractors Area in the southwest corner of the site have resulted in deep trenches in some areas and mounds of dirt in others.

The "quietest" area of the site is 15-metres below the surface in the Seismic Isolation Pit. But not for long: GTM Construction will soon begin propping and formwork in preparation for concrete pouring for the B2 slab—the "upper basemat" and actual floor of the 360,000-tonne Tokamak Complex.

Work progresses on the Assembly Building basemat. Two sections of structural concrete, or plots, have been poured since November and reinforcement activities are ongoing. (Click to view larger version...)
Work progresses on the Assembly Building basemat. Two sections of structural concrete, or plots, have been poured since November and reinforcement activities are ongoing.


Workers dig galleries along the exterior of the Assembly Building to accommodate services (electricity, evacuation, piping ...) (Click to view larger version...)
Workers dig galleries along the exterior of the Assembly Building to accommodate services (electricity, evacuation, piping ...)


The foundations of the Assembly Building abut the retaining wall of the Tokamak Complex. The two buildings will be the tallest on the platform, rising to a height of 60 metres. (Click to view larger version...)
The foundations of the Assembly Building abut the retaining wall of the Tokamak Complex. The two buildings will be the tallest on the platform, rising to a height of 60 metres.


Propping and formwork will begin at the end of the month for the upper basemat of the Tokamak Pit: by late October 2013, the seismic protection system for the Tokamak Complex will be completely hidden from view. (Click to view larger version...)
Propping and formwork will begin at the end of the month for the upper basemat of the Tokamak Pit: by late October 2013, the seismic protection system for the Tokamak Complex will be completely hidden from view.


Critical network piping will crisscross the ITER site for precipitation drainage and cooling water release. In this section of the network, the pipes have been installed and backfilling is underway. (Click to view larger version...)
Critical network piping will crisscross the ITER site for precipitation drainage and cooling water release. In this section of the network, the pipes have been installed and backfilling is underway.




return to the latest published articles