Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Fusion world | Mobilizing for long-pulse operation

    One of the key operational challenges in the development of fusion energy is the achievement, simultaneously, of high fusion performance and long-pulse operatio [...]

    Read more

  • ITER science | What is burning plasma?

    The dream of fusion power depends first and foremost on a self-sustaining fusion reaction, with most of the heating power needed coming from within the reaction [...]

    Read more

  • Plasma modelling | New SOLPS-ITER code version launched

    The widely used SOLPS-ITER tool for plasma edge modelling has evolved since its launch in 2015. At recent workshop at KU Leuven in Belgium, European specialists [...]

    Read more

  • Open Doors Day | Accessing the very heart of ITER

    Small or tall, knowledgeable or neophyte, from near or far ... the 600 people who took part in ITER's latest Open Doors Day all departed with the sense that som [...]

    Read more

  • Local | A question and answer session

    Nuclear safety policy in France requires that a local information commission (Commission locale d'information, CLI) be established every time a nuclear installa [...]

    Read more

Of Interest

See archived entries

Propping and formwork on both slab and mockup

Take in the view and enjoy it while you can. In a couple months, the spectacular pattern formed by the 493 columns in the Tokamak Complex Seismic Pit—the emblematic image of ITER construction—will have vanished from view.

The lone scaffolding that was erected two weeks ago at the centre of the pit has already been joined by dozens of others. "Everything will be covered," says ITER Nuclear Buildings Section Leader Laurent Patisson. Once the structures are in place, a steel rebar skeleton will be installed on top of them and pouring of the 1.5-metre-thick B2 slab will begin plot by plot (or "pour by pour") —a process which should take about nine months.

Propping has begun in the Tokamak Complex Seismic Pit. Concrete and rebar included, a load of approximately 37,500 tons will rest on the 493 seismic pads when work on the B2 slab is completed. (Click to view larger version...)
Propping has begun in the Tokamak Complex Seismic Pit. Concrete and rebar included, a load of approximately 37,500 tons will rest on the 493 seismic pads when work on the B2 slab is completed.
"The propping and formwork structures will support the weight of the rebar and concrete until the hardening of the concrete makes it possible to transfer the effort onto the seismic pads," adds Laurent. "A total of 15,000 m³ of concrete will be poured, which—added  to the weight of the rebar (~ 4,000 tonnes)—will amount to a load of some 37,500 tonnes."

Creating a reinforced slab over formwork structures that are supported by braced scaffoldings is a common technique. The very same process was implemented, two years ago, on the nuclear research reactor Jules-Horowitz (RJH) that is being constructed at CEA-Cadarache.

Every installation has its own geometry, however, which is reflected in the complex pattern of the steel reinforcement bars. "We have to demonstrate constructability prior to pouring the actual slab," explains Laurent. "We also have to qualify the concrete and test the efficiency of the vibration techniques."

To that effect, a 150 m² mockup has been created on the platform to the west of the Seismic Pit. "Although 3D models of the rebar arrangements have been produced, we need a hands-on experience of the difficulties we may encounter." Four different areas of rebar, presenting specific challenges (density, complexity), will be reproduced at 1:1 scale in the mockup. Work on the mockup began last week.

The mockup will also allow the practice installation and testing of the anchor plates that will be embedded into the concrete. These thick steel plates of various sizes, all dotted with long spikes (see picture), will reach deep into the concrete.

''We have to demonstrate constructability prior to pouring the actual slab,'' explains ITER Nuclear Buildings Section Leader Laurent Patisson. The 150 m2 mockup will serve this purpose. (Click to view larger version...)
''We have to demonstrate constructability prior to pouring the actual slab,'' explains ITER Nuclear Buildings Section Leader Laurent Patisson. The 150 m2 mockup will serve this purpose.
Once embedded into the concrete mass, the plates form an exceptionally solid base onto which equipment such as magnet feeders, drain tanks or cubicles can be welded. The Tokamak Complex will contain some 60,000 such plates.

"What is at stake beyond the B2 slab," summarizes Laurent, "is the robustness of the whole Tokamak support, from the cryostat bearing down to the ground."

Work progressed steadily last week on propping operations inside the Tokamak Pit and on its smaller mockup sibling nearby.


return to the latest published articles