Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Safety regulator scrutinizes ongoing works

On Thursday 25 April, the French nuclear safety regulator ASN inspected the ITER construction site for the sixth time since July 2011. (Click to view larger version...)
On Thursday 25 April, the French nuclear safety regulator ASN inspected the ITER construction site for the sixth time since July 2011.

In the realm of nuclear safety, no detail is too small to overlook. An imprecise document, an incomplete procedure, a misplaced bolt or a slight deviation from the approved design can have serious consequences on the overall safety of the installation.

It is the duty of the ITER Organization, as nuclear operator, to ascertain that the safety requirements are understood and implemented throughout the whole chain of its suppliers and contractors, and that the procedures in application of the 1984 Quality Order are respected. And it is the mission of the French Nuclear Safety Agency ASN, in conformity with the 2007 ITER Headquarters Agreement, to verify that this duty is properly performed.

For their sixth visit to the ITER site, last Thursday 25 April, the ASN inspectors, accompanied by one expert from the French Radioprotection and Nuclear Safety Institute (IRSN), had decided to direct their scrutiny to the ongoing civil works on the ITER platform.

After a meticulous review of documents and procedures in the morning, the inspectors spent most of the afternoon onsite, focusing their attention on the B2 slab mockup (rebar arrangements and concrete formulation) and inside the Tokamak Seismic Pit, where formwork activity is progressing at a spectacular pace.

A letter summarizing the outcome of the inspection will be addressed to the ITER Director-General in the coming days and also made available to the public on the ASN web site. In nuclear safety, transparency is key.

The ASN inspectors focused their attention on the B2 slab mockup and on the Tokamak Seismic Pit, where formwork activity is progressing at a spectacular pace. (Click to view larger version...)
The ASN inspectors focused their attention on the B2 slab mockup and on the Tokamak Seismic Pit, where formwork activity is progressing at a spectacular pace.


return to the latest published articles