Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Crane operator | A cabin in the sky

    There are times, at dusk, when the ITER construction platform resembles an airport, with roads and buildings illuminated by yellow and white lights. From their [...]

    Read more

  • Assembly | A colossal task made manageable

    For the execution of work during the next project phase—machine and plant assembly up to First Plasma—the ITER Organization has chosen a contractual approach th [...]

    Read more

  • Neutral Beam Test Facility | A new agreement for a new era

    The ITER Organization and the Italian consortium Consorzio RFX* have signed a new agreement governing the construction and operation of the ITER Neutral Beam Te [...]

    Read more

  • Load tests | Heavyweight champion

    The Assembly Hall, with its two giant tools towering 20 metres above ground, is one of the most spectacular locations on the ITER site. When a dummy load weighi [...]

    Read more

  • Fusion's new pioneers | How to go fast enough to make a difference

    Last month in New York, the Stellar Energy Foundation and the Fusion Industry Association co-hosted an invitation-only workshop: 'Roadmap to the Fusion Energy E [...]

    Read more

Of Interest

See archived entries

First hardware afloat from China

Liu Sheng, Fan Xue and Wang Min, ITER China

The last batch of dummy conductor (out of three) is lifted on board the ship which is due to arrive in France early June. (Click to view larger version...)
The last batch of dummy conductor (out of three) is lifted on board the ship which is due to arrive in France early June.
On Thursday 25 April, the morning silence at the Institute of Plasma Physics (ASIPP) in Hefei, China, was broken by the noise of a high powered trailer. Inside the superconductor shop of ASIPP, workers were busy preparing to load the 737 metres of dummy conductor for ITER's Poloidal Field Coil number five (PF5)—this represents the first delivery from China to the ITER construction site in France.
 
According to the Procurement Arrangement signed between the Chinese Domestic Agency and the ITER Organization, China will fabricate 64 conductors for ITER's poloidal field coils, including four dummy conductors for cabling and coil manufacturing process qualification. ASIPP is responsible for all the poloidal field conductor fabrication in China. The fabrication of the PF5 dummy was completed in by ASIPP in 2011.
 
Workers at ASIPP are busy preparing to load the 737 metres of dummy conductor for ITER's poloidal field coil number five. (Click to view larger version...)
Workers at ASIPP are busy preparing to load the 737 metres of dummy conductor for ITER's poloidal field coil number five.
"This is the very first batch of ITER items to be shipped from China to the ITER site in Cadarache," said Luo Delong, Deputy Director-General of ITER China. Before, conductors for the toroidal field coils had been shipped to Japan and Europe. "This milestone is a further step for the ITER Project. According to our schedule, we will now start massive production of conductors this year. Our goal is that all procurement items from China be supplied consistent with the ITER schedule and with ITER quality requirements."

According to the shipment schedule the PF5 dummy conductors, which left Shanghai on 30 April, will arrive at the ITER site on 5 June.


return to the latest published articles