Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • In-vessel electrical systems | What it takes to wire up a fusion reactor

    While the challenges of keeping cables operational in harsh environments such as jet engines and nuclear fission reactors have been understood for a long time, [...]

    Read more

  • Assembly preparation | Off goes the lid

    In the summer of 2017, a circular platform was installed inside of the large steel-and-concrete cylinder of the Tokamak pit. The 200-tonne structure was meant t [...]

    Read more

  • Deliveries | Two coils on their way

    For the past five years, 'highly exceptional loads' (HEL) have been successfully travelling along the ITER Itinerary to be delivered to the ITER site. As the pr [...]

    Read more

  • ITER NOW video | Ready for the big lifts

    This new video in our "ITER NOW" series provides an insider's view of the recent load tests performed as the ITER Organization prepares for the machin [...]

    Read more

  • Divertor | Far more than a fancy ashtray

    It has been likened to the filter of a swimming pool or an oversized ashtray. It has been called alien in shape and hellish in its affinity for heat. But whatev [...]

    Read more

Of Interest

See archived entries

Work on central rebar resumes

Eight months after being interrupted, rebar operations resumed on this all-important area of the Tokamak Complex concrete slab. (Click to view larger version...)
Eight months after being interrupted, rebar operations resumed on this all-important area of the Tokamak Complex concrete slab.
Designing the rebar arrangement for the concrete slab that will support the Tokamak Complex has proved an exceptionally challenging task.

The complexity has been at its peak in the centre of the Tokamak Complex worksite at the location of the future Tokamak Building, where orthoradial (circular) and orthogonal (right-angled) rebar arrangements interface.

In June 2013, as work was beginning on the first 2 layers of rebar out of 16, it appeared that the design in this area needed to be consolidated. Eight months later, the new design was accepted by all parties and rebar laying resumed on this all-important central area on 20 January 2014 .

Completing the complex rebar arrangements will take a few months. Concrete pouring operations in the central area of the Tokamak Building will follow shortly afterward.


return to the latest published articles