  • Cryolines | Another day, another spool

    Having wedged his body and equipment into the cramped space between the ceiling and the massive pipe, a worker is busy welding two cryolines spools. A few metre [...]

    Read more

  • Image of the week | Bearings unveiled

    The construction teams are in the last stages of preparing the Tokamak pit for the first major operation of ITER machine assembly: the lowering of the cryostat [...]

    Read more

  • Technology | Perfecting tritium breeding for DEMO and beyond

    While ITER will never breed tritium for its own consumption, it will test breeding blanket concepts—the tools and techniques that designers of future DEMO react [...]

    Read more

  • Fusion world | Japan and Europe complete the assembly of JT-60SA

    The JT-60SA fusion experiment in Naka, Japan, is designed to explore advanced plasma physics in support of the operation of ITER and next-phase devices. After s [...]

    Read more

  • Manufacturing | Thermal shield milestone in Korea

    Six years after the start of fabrication, Korean contractor SFA has completed the last 40° sector of vacuum vessel thermal shield. The stainless steel panels, c [...]

    Read more

Of Interest

See archived entries

Second test convoy, with maritime leg this time

R.A.

Pushed by a tug boat, the 80-metre barge coupled with a 65-metre pontoon will ferry the trailer and dummy load across the inland sea Étang de Berre. (Click to view larger version...)
Pushed by a tug boat, the 80-metre barge coupled with a 65-metre pontoon will ferry the trailer and dummy load across the inland sea Étang de Berre.
In September last year, at the time of the first ITER Itinerary test convoy, the crossing of the inland sea Étang de Berre had to be cancelled: the barge that was to ferry the trailer and its 600-tonne dummy load was stranded in Turkey because of weather conditions.

A second test convoy campaign, focusing this time on the rehearsal of logistics and timing, is scheduled from 31 March to 4 April. Weather permitting, the maritime leg of the journey should be one of the most spectacular parts of the operation.

In order to ferry the components from Fos harbour, on the Mediterranean Sea, to Port-de-la-Pointe, on the north-eastern shore of the Étang de Berre, a combination of conventional barge and heavy-lift pontoon will be used. The 26-kilometre voyage will take four hours.

On Wednesday 12 March, a representative of DAHER, ITER's Global Transport, Logistics and Insurance Service Provider, presented a captivating animation to the ITER community on how the barge and pontoon will operate, and how the trailer and its 600-tonne dummy load will be loaded and unloaded (see attached video).

François Genevey is the project director for the ITER contract at DAHER. "The crucial moments in the port operations are when the ITER loads are rolled onto and off of the barge. An electronic ballasting system will ensure that the barge and the pontoon maintain their full stability during the transfer of the charge."

Once the maritime leg of the journey is past, the trailer will commence its slow and careful ride to the ITER site just as it did six months ago.

This time, instead of verifying how critical points along the Itinerary hold up under the load, operators from DAHER and Agence Iter France will test the complex logistics involved (more than 200 people will take part in the operation) and validate the projected timing for the transportation of the most taxing of the ITER components in terms of size and weight.

Of a projected 250 Highly Exceptional Loads (HELs) to be delivered to the ITER site, approximately 30 belong in that category.

But HELs are not all—close to 2,500 Conventional Exceptional Loads (CEL), and several thousand container-sized loads will travel the regular roads to the ITER site between mid-2014 and end-2020.