Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • A world in itself

    From a height of some 50 metres, you have the entire ITER worksite at your feet. The long rectangle of the Diagnostics Building stands out in the centre, with [...]

    Read more

  • US completes toroidal field deliveries for ITER

    The US Domestic Agency achieved a major milestone in February by completing the delivery of all US-supplied toroidal field conductor to the European toroidal fi [...]

    Read more

  • Thin diagnostic coils to be fitted into giant magnets

    Last week was marked by the first delivery of diagnostic components—Continuous External Rogowski (CER) coils—from the European Domestic Agency to the ITER Organ [...]

    Read more

  • Addressing the challenge of plasma disruptions

    Plasma disruptions are fast events in tokamak plasmas that lead to the complete loss of the thermal and magnetic energy stored in the plasma. The plasma control [...]

    Read more

  • Blending (almost) seamlessly into the landscape

    Located in the foothills of the French Pre-Alps, the ITER installation blends almost seamlessly into the landscape. The architects' choice ofmirror-like steel c [...]

    Read more

Of Interest

See archived articles

Concrete pouring begins for Tritium Building basemat

Close to 1,000 cubic meters of concrete were employed in filling a 638 square-metre plot (P14) in the north-east corner of the Tokamak Pit. (Click to view larger version...)
Close to 1,000 cubic meters of concrete were employed in filling a 638 square-metre plot (P14) in the north-east corner of the Tokamak Pit.
Concrete pouring for the basemat of the Tritium Building began on Wednesday 19 March. Close to 1,000 cubic meters of concrete were employed in filling a 638 square-metre plot (P14) in the north-east corner of the Tokamak Pit.

As for the Diagnostics Building basemat, the section of the slab that will support the Tritium Building will be poured in three separate segments. The next two, plots 12 and 15, are scheduled for pouring in April.

In the central area of the Tokamak Pit, where a combination of orthogonal and orthodradial rebar create a particularly tight and complex pattern, pouring should begin in late July and be completed in early October.


return to the latest published articles