Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Men of measure

    'Neither snow nor rain nor heat nor gloom of night stays these couriers from the swift completion of their appointed rounds.' [From the Greek historian Herodotu [...]

    Read more

  • The end of a nine-year journey

    In December, as toroidal field conductor unit length #133 came off the production line, the ITER community celebrated a major milestone—the end of a nine-year p [...]

    Read more

  • The little coupler that could

    Concrete and steel met at the end of the 19th century, never to part again. From their encounter a new material was born that revolutionized construction techni [...]

    Read more

  • The radio power house

    The steel structurethat's being erected against the northeast side of the Assembly Hall is for a large building that will be densely packed with power supplies [...]

    Read more

  • Spaceport ITER

    At nightfall, when buildings, work areas, roads and parking lots light up, the ITER site looks like an alien spaceport. Drenched in the yellow glow of sodium l [...]

    Read more

Of Interest

See archived articles

Concrete pouring begins for Tritium Building basemat

Close to 1,000 cubic meters of concrete were employed in filling a 638 square-metre plot (P14) in the north-east corner of the Tokamak Pit. (Click to view larger version...)
Close to 1,000 cubic meters of concrete were employed in filling a 638 square-metre plot (P14) in the north-east corner of the Tokamak Pit.
Concrete pouring for the basemat of the Tritium Building began on Wednesday 19 March. Close to 1,000 cubic meters of concrete were employed in filling a 638 square-metre plot (P14) in the north-east corner of the Tokamak Pit.

As for the Diagnostics Building basemat, the section of the slab that will support the Tritium Building will be poured in three separate segments. The next two, plots 12 and 15, are scheduled for pouring in April.

In the central area of the Tokamak Pit, where a combination of orthogonal and orthodradial rebar create a particularly tight and complex pattern, pouring should begin in late July and be completed in early October.


return to the latest published articles