Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • FEC2020 | Seeking sponsors for 28th IAEA Fusion Energy Conference

    For only the third time since 1961, the International Atomic Energy Agency's Fusion Energy Conference will be taking place in France—hosted jointly by the Frenc [...]

    Read more

  • Nuclear safety | Under constant scrutiny

    Because one of the elements involved in the fusion reaction is the radioactive isotope tritium, and because the hydrogen fusion reaction itself generates a high [...]

    Read more

  • Power conversion | Alien structures and strange contraptions

    There are places in ITER that seem to belong to another world, places full of alien structures and strange contraptions. The feeling—a mixture of awe and puzzle [...]

    Read more

  • Tokamak Complex | A changing landscape

    For the past three years, the view from the top of the highest worksite crane has not changed much. Inside of the Tokamak Complex, 80 metres below, concrete gal [...]

    Read more

  • Ion cyclotron heating | How to pump 20 MW of power into 1 gram of plasma

    To power the ion cyclotron system, the ITER Organization and its partners are designing not only new antennas, which will be housed in the tokamak vessel, but a [...]

    Read more

Of Interest

See archived entries

Welcome on board!

R.A.

On Friday 28 March on a remote wharf at the Fos-sur-Mer industrial harbour, the loading of the ITER mockup convoy onto the barge took more than eight hours. It was the first time the maritime leg of the ITER Itinerary had been tested. (Click to view larger version...)
On Friday 28 March on a remote wharf at the Fos-sur-Mer industrial harbour, the loading of the ITER mockup convoy onto the barge took more than eight hours. It was the first time the maritime leg of the ITER Itinerary had been tested.
It's like driving a car onto a ferry. But it takes much, much longer and it's incomparably more delicate and complicated.

On Friday 28 March, on a remote wharf at the southwest end of the Fos-sur-Mer industrial harbour near Marseille, the loading of the ITER mockup convoy onto a barge took more than eight hours.

Progress was measured millimetre by millimetre as the weight of the 800-tonne monster trailer was gradually transferred from the solid ground to the water-borne combination of barge and pontoon.

Axle line after axle line (and there are 22 double pairs of them!) the trailer and its dummy load of stacked concrete blocks were slowly driven onto the pontoon as electronic calculators adjusted the barge's ballast in real-time.

Personnel from ITER logistics provider DAHER and the Compagnie Fluviale de Transport monitored every millimetre of progress as the trailer crossed onto the barge. (Click to view larger version...)
Personnel from ITER logistics provider DAHER and the Compagnie Fluviale de Transport monitored every millimetre of progress as the trailer crossed onto the barge.
Each time an axle line transferred its load from the ground to the barge a long pause (5-20 minutes) ensued. Balance was checked and calculators activated the filling and emptying of the ballast tanks to compensate the imperceptible, but potentially dangerous, pitching, tossing and rolling of the barge.

By the time the sun had set on the wharf, the trailer had progressed approximately 40 metres and its load had been safely transferred to the barge.

"This last phase is the most delicate," explained Alain Spatafora, the maritime expert commissioned by the ITER Organization and logistics provider DAHER, and Bernard Bon, DAHER head of convoy. "The centre of gravity of the trailer must now be perfectly aligned with the centre of buoyancy of the barge."

The last phase was the most delicate. The centre of gravity of the 800-tonne load must be perfectly aligned with the centre of buoyancy of the barge.<br /><br /> (Click to view larger version...)
The last phase was the most delicate. The centre of gravity of the 800-tonne load must be perfectly aligned with the centre of buoyancy of the barge.

On board, as bubble levels were laid on the deck to verify the perfect horizontality of the barge, the crew was busy making the last adjustments. Captains and sailors of the Compagnie Fluviale de Transports (CFT) are used to transporting exceptionally heavy loads, but at 800 tonnes this one exceeded anything they had experienced.

The night was falling when, in conformity with port regulations, Marseille harbour stevedores climbed on board to lash down the trailer and its load, marking the end of the operation.

The barge spent the weekend in protected docking (a strong north wind was expected during the night) and on Monday afternoon, weather permitting, it is expected to leave Fos, navigate into the narrow Caronte Canal through the town of Martigues and cross the inland sea Étang de Berre.

The trailer will then be unloaded at Port-de-la-Pointe on the north-western shore of the Étang, before commencing its slow progression towards the ITER site where it is expected at around 6:00 a.m. on Friday 4 April.

Click here for more images.