  • 23rd ITER Council | Pace and performance on track

    Working as an integrated team, the ITER Organization and seven Domestic Agencies are continuing to meet the project's demanding schedule to First Plasma in 2025 [...]

    Read more

  • Fusion Doctors | ITER hosts the future

    For three days last week, the ITER building was brimming with energy, inspiration and enthusiasm. One hundred and thirty-five young fusion aficionados took over [...]

    Read more

  • Fusion world | What's next for the stellarator?

    Earlier this year, the Wendelstein 7-X stellarator fusion project reported record achievements from its most recent experimental campaign. Newsline spoke with t [...]

    Read more

  • Metrology and the ITER machine | Perfectly planned points

    Inside of the Tokamak Complex, a network of 2,000 small 'fiducial target nests' will provide the reference datum for the dimensional control and alignment of ma [...]

    Read more

  • Breaking news | First component installed next week

    In the third week of November, the ITER Organization will be installing the first component of the machine in the basement of the Tokamak Building. The 10-met [...]

    Read more

Of Interest

See archived entries

Welcome on board!

R.A.

On Friday 28 March on a remote wharf at the Fos-sur-Mer industrial harbour, the loading of the ITER mockup convoy onto the barge took more than eight hours. It was the first time the maritime leg of the ITER Itinerary had been tested. (Click to view larger version...)
On Friday 28 March on a remote wharf at the Fos-sur-Mer industrial harbour, the loading of the ITER mockup convoy onto the barge took more than eight hours. It was the first time the maritime leg of the ITER Itinerary had been tested.
It's like driving a car onto a ferry. But it takes much, much longer and it's incomparably more delicate and complicated.

On Friday 28 March, on a remote wharf at the southwest end of the Fos-sur-Mer industrial harbour near Marseille, the loading of the ITER mockup convoy onto a barge took more than eight hours.

Progress was measured millimetre by millimetre as the weight of the 800-tonne monster trailer was gradually transferred from the solid ground to the water-borne combination of barge and pontoon.

Axle line after axle line (and there are 22 double pairs of them!) the trailer and its dummy load of stacked concrete blocks were slowly driven onto the pontoon as electronic calculators adjusted the barge's ballast in real-time.

Personnel from ITER logistics provider DAHER and the Compagnie Fluviale de Transport monitored every millimetre of progress as the trailer crossed onto the barge. (Click to view larger version...)
Personnel from ITER logistics provider DAHER and the Compagnie Fluviale de Transport monitored every millimetre of progress as the trailer crossed onto the barge.
Each time an axle line transferred its load from the ground to the barge a long pause (5-20 minutes) ensued. Balance was checked and calculators activated the filling and emptying of the ballast tanks to compensate the imperceptible, but potentially dangerous, pitching, tossing and rolling of the barge.

By the time the sun had set on the wharf, the trailer had progressed approximately 40 metres and its load had been safely transferred to the barge.

"This last phase is the most delicate," explained Alain Spatafora, the maritime expert commissioned by the ITER Organization and logistics provider DAHER, and Bernard Bon, DAHER head of convoy. "The centre of gravity of the trailer must now be perfectly aligned with the centre of buoyancy of the barge."

The last phase was the most delicate. The centre of gravity of the 800-tonne load must be perfectly aligned with the centre of buoyancy of the barge.<br /><br /> (Click to view larger version...)
The last phase was the most delicate. The centre of gravity of the 800-tonne load must be perfectly aligned with the centre of buoyancy of the barge.

On board, as bubble levels were laid on the deck to verify the perfect horizontality of the barge, the crew was busy making the last adjustments. Captains and sailors of the Compagnie Fluviale de Transports (CFT) are used to transporting exceptionally heavy loads, but at 800 tonnes this one exceeded anything they had experienced.

The night was falling when, in conformity with port regulations, Marseille harbour stevedores climbed on board to lash down the trailer and its load, marking the end of the operation.

The barge spent the weekend in protected docking (a strong north wind was expected during the night) and on Monday afternoon, weather permitting, it is expected to leave Fos, navigate into the narrow Caronte Canal through the town of Martigues and cross the inland sea Étang de Berre.

The trailer will then be unloaded at Port-de-la-Pointe on the north-western shore of the Étang, before commencing its slow progression towards the ITER site where it is expected at around 6:00 a.m. on Friday 4 April.

Click here for more images.