Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • A world in itself

    From a height of some 50 metres, you have the entire ITER worksite at your feet. The long rectangle of the Diagnostics Building stands out in the centre, with [...]

    Read more

  • US completes toroidal field deliveries for ITER

    The US Domestic Agency achieved a major milestone in February by completing the delivery of all US-supplied toroidal field conductor to the European toroidal fi [...]

    Read more

  • Thin diagnostic coils to be fitted into giant magnets

    Last week was marked by the first delivery of diagnostic components—Continuous External Rogowski (CER) coils—from the European Domestic Agency to the ITER Organ [...]

    Read more

  • Addressing the challenge of plasma disruptions

    Plasma disruptions are fast events in tokamak plasmas that lead to the complete loss of the thermal and magnetic energy stored in the plasma. The plasma control [...]

    Read more

  • Blending (almost) seamlessly into the landscape

    Located in the foothills of the French Pre-Alps, the ITER installation blends almost seamlessly into the landscape. The architects' choice ofmirror-like steel c [...]

    Read more

Of Interest

See archived articles

The road to assembly is now open

-R.A.

Alarm clocks rang early on Tuesday 8 April as the second ITER test convoy was completing the last leg of its 104-kilometre journey along the ITER Itinerary. But for many, it wasn't early enough: the convoy reached the ITER site nearly two hours ahead of schedule.

The last leg of the journey between the village of Meyrargues and the ITER site had gone smoothly. With the exception of the triple crossing of the A51 thruway, the 26-kilometre stretch doesn't present major difficulties or obstacles—only one roundabout to negotiate, no steep climb and no speed bumps.

As billions of fusion furnaces glittered in the pre-dawn light, the ITER convoy came to a halt near the Poloidal Field Coils Building ... nearly two hours ahead of schedule. (Click to view larger version...)
As billions of fusion furnaces glittered in the pre-dawn light, the ITER convoy came to a halt near the Poloidal Field Coils Building ... nearly two hours ahead of schedule.
As the two diesel power packs purred reassuringly, the trailer progressed at a good speed. Unlike the two first nights of the test campaign, no incident occurred to slow or stop the convoy. Expected at 6:00 a.m., it passed the ITER gates at 4:00 a.m.

For the second time in eight months, the 800 tonnes of trailer and mock load had been safely delivered to the ITER site.

"For the duration of this test campaign you have mastered uniquely complex logistics and overcome some serious technical difficulties," said ITER Director-General Osamu Motojima as he addressed those who had participated in the operation.

''The part you play in the ITER Project is essential [...] Without you, there can be no ITER,'' said ITER Director-General Osamu Motojima to the French authorities and representatives of Agence Iter France and logistics provider DAHER. From left to right: Colonel Laurent Phélip, François Genevey and Bernard Bon, of DAHER; General David Galtier, head of the PACA region Gendarmerie forces; Préfet Jean-René Vacher, secretary-general of the South Defence Command; Pierre-Marie Delplanque and Jérôme Paméla of Agence ITER France. (Click to view larger version...)
''The part you play in the ITER Project is essential [...] Without you, there can be no ITER,'' said ITER Director-General Osamu Motojima to the French authorities and representatives of Agence Iter France and logistics provider DAHER. From left to right: Colonel Laurent Phélip, François Genevey and Bernard Bon, of DAHER; General David Galtier, head of the PACA region Gendarmerie forces; Préfet Jean-René Vacher, secretary-general of the South Defence Command; Pierre-Marie Delplanque and Jérôme Paméla of Agence ITER France.
To the French authorities Jean-René Vacher, prefect and head of the Southern Defence Command, and General David Galtier, head of the Gendarmerie forces in the PACA Region; to Jérôme Pamela and Pierre-Marie-Delplanque, respectively director and managing director of Agence Iter France; and to the representatives of logistics provider DAHER including Project Director François Genevey, he said: "The part you play in the ITER Project is essential. The convoys are the vital link between the manufacturing of the components in factories throughout the world and their assembly here on the ITER site. Without you, there can be no ITER."

A well-deserved breakfast! (Click to view larger version...)
A well-deserved breakfast!
The safe arrival of the second ITER test convoy was just the beginning of this great, common adventure. From 2014 to 2020, as ITER components are progressively delivered by the Domestic Agencies, the achievement will have to be replicated some 250 times.

Read the press release in English or in French.


return to the latest published articles