Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • A world in itself

    From a height of some 50 metres, you have the entire ITER worksite at your feet. The long rectangle of the Diagnostics Building stands out in the centre, with [...]

    Read more

  • US completes toroidal field deliveries for ITER

    The US Domestic Agency achieved a major milestone in February by completing the delivery of all US-supplied toroidal field conductor to the European toroidal fi [...]

    Read more

  • Thin diagnostic coils to be fitted into giant magnets

    Last week was marked by the first delivery of diagnostic components—Continuous External Rogowski (CER) coils—from the European Domestic Agency to the ITER Organ [...]

    Read more

  • Addressing the challenge of plasma disruptions

    Plasma disruptions are fast events in tokamak plasmas that lead to the complete loss of the thermal and magnetic energy stored in the plasma. The plasma control [...]

    Read more

  • Blending (almost) seamlessly into the landscape

    Located in the foothills of the French Pre-Alps, the ITER installation blends almost seamlessly into the landscape. The architects' choice ofmirror-like steel c [...]

    Read more

Of Interest

See archived articles

Home away from home

It was only one year ago, on 19 April 2013, that the ITER Organization officially made a small tract of land on the ITER platform available to the Indian Domestic Agency to build a temporary workshop—a Little India where the ITER cryostat, part of India's in-kind contribution to the Project, would be assembled.

On 25 April, accompanied by ITER DDG Rem Haange (first from right), the head of the Indian Domestic Agency, Shishir Deshpande (second from left), paid a visit to the Cryostat Workshop. He's seen here with Michel Fayard, APAVE; Bharat Doshi, ITER and Ujjwal Baruah, Indian Domestic Agency (from left to right). (Click to view larger version...)
On 25 April, accompanied by ITER DDG Rem Haange (first from right), the head of the Indian Domestic Agency, Shishir Deshpande (second from left), paid a visit to the Cryostat Workshop. He's seen here with Michel Fayard, APAVE; Bharat Doshi, ITER and Ujjwal Baruah, Indian Domestic Agency (from left to right).
Three months later in June, coconuts were symbolically broken over the site, calling on the blessing of Ganesha, the elephant-headed deity "Remover of Obstacles."

From then on, things went amazingly fast. In September 2013, half of the steel columns forming the building's skeleton were in place; one month ago in March the 200-tonne gantry crane was installed inside the completed structure. And last week, when the head of the Indian Domestic Agency, Shishir Deshpande, paid a visit, the place had an almost homey feeling ...

There's still some work to be done before the building is fully completed in mid-July. Under supervision from Currie & Brown, the contract engineer for Larsen & Toubro (the company responsible for the construction of both cryostat and Cryostat Workshop), the French company Spie Batignolles is busy connecting the large heat pumps that will cool down the workshop and finalizing the electrical works.

The 110 metre long, 44 metre wide and 27 metre tall building is scheduled to be handed over to the Indian Domestic Agency in August. (Click to view larger version...)
The 110 metre long, 44 metre wide and 27 metre tall building is scheduled to be handed over to the Indian Domestic Agency in August.
The final layer of the concrete floor slab, an extra 20 cm, will be poured in the coming weeks to allow commissioning tests (HVAC, electrical) to begin. The 200-tonne gantry crane will be load-tested towards the end of May, before the building is handed over to the Indian Domestic Agency in August.


return to the latest published articles