Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Thermal shield repair | Where are we at?

    Fitting the vacuum vessel sectors like a jacket, lining the inner wall of the cryostat, or covering the sides of vertical coil gravity supports, ITER's thermal [...]

    Read more

  • Assembly prep | Reviewing plans for in-vessel installation

    A thorough review of all 'in-vessel' assembly scope was organized by the ITER Machine Assembly Program in early February, with the active participation of senio [...]

    Read more

  • Image of the week | Last measurements before campaign

    In order to precisely identify the bevel regions that need to be rectified, metrologists from the SIMANN (SIMIC-Ansaldo) consortium are performing ultra-precise [...]

    Read more

  • Neutral Beam Test Facility | After upgrades, SPIDER testbed set to restart

    After a two-year shutdown for upgrades, the SPIDER testbed at the ITER Neutral Beam Test Facility in Padua, Italy, is preparing for commissioning and operation. [...]

    Read more

  • ITER Research Plan | Jointly preparing a new blueprint

    As part of work underway to update the ITER Project Baseline, a group of experts nominated by the Members met in February to evaluate the new blueprint for achi [...]

    Read more

Of Interest

See archived entries

A perfect day for pouring

It takes a fisheye lens, which makes the steel reinforcement appear a bit distorted, to take in the whole of the concrete pouring scene for the Tritium Building slab ... (Click to view larger version...)
It takes a fisheye lens, which makes the steel reinforcement appear a bit distorted, to take in the whole of the concrete pouring scene for the Tritium Building slab ...
In the scope of a regular building project, concrete pouring is a commonplace operation. For an ITER building, however, it is the culmination of months of calculations, modellization and painstaking preparation.

"It's a moment of great pleasure and relief," admits Laurent Patisson, Nuclear Buildings Section leader at ITER. "For a short time, the paperwork is over and we're into the real thing."

What added to his sense of satisfaction last Thursday 19 June, as a second segment of the Tritium Building slab was poured on the north side of the Tokamak Pit, was the weather. For both the workers and the concrete, the conditions were just perfect.

Unlike during pouring events scheduled mid-winter or high-summer, the concrete coming out of the on-site batching plant didn't require warming or cooling. Like a good wine, it was served at room temperature.

Operations began at 6:45 a.m. and followed a strict procedure detailed in a five-page program. Two giant 47-metre pumps, capable of delivering 50 cubic metres of concrete per hour, were guided from north to south, progressively filling the steel reinforcement structure with 1,155 cubic metres of specially formulated concrete.

Four layers were poured successively, each followed by vibrating operations, for a total height of 1.5 metres. By midnight, the 770 square metres of plot #12 were filled. The next morning, the surface of the new concrete was flooded to prevent dehydration and the possible creation of micro-cracks on the concrete "skin." The plot's surface will remain underwater for at least 10 days—a phase known as concrete curing.

The remaining, central segment of the Tritium Building slab should be poured in the coming week. Then, sometime in the summer, it will be time to celebrate an even bigger moment of "pleasure and relief": the pouring of the first segment of the Tokamak Building slab, following the green light to proceed from the French Nuclear Safety Authority.


return to the latest published articles