Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

A perfect day for pouring

R.A.

It takes a fisheye lens, which makes the steel reinforcement appear a bit distorted, to take in the whole of the concrete pouring scene for the Tritium Building slab ... (Click to view larger version...)
It takes a fisheye lens, which makes the steel reinforcement appear a bit distorted, to take in the whole of the concrete pouring scene for the Tritium Building slab ...
In the scope of a regular building project, concrete pouring is a commonplace operation. For an ITER building, however, it is the culmination of months of calculations, modellization and painstaking preparation.

"It's a moment of great pleasure and relief," admits Laurent Patisson, Nuclear Buildings Section leader at ITER. "For a short time, the paperwork is over and we're into the real thing."

What added to his sense of satisfaction last Thursday 19 June, as a second segment of the Tritium Building slab was poured on the north side of the Tokamak Pit, was the weather. For both the workers and the concrete, the conditions were just perfect.

Unlike during pouring events scheduled mid-winter or high-summer, the concrete coming out of the on-site batching plant didn't require warming or cooling. Like a good wine, it was served at room temperature.

Operations began at 6:45 a.m. and followed a strict procedure detailed in a five-page program. Two giant 47-metre pumps, capable of delivering 50 cubic metres of concrete per hour, were guided from north to south, progressively filling the steel reinforcement structure with 1,155 cubic metres of specially formulated concrete.

Four layers were poured successively, each followed by vibrating operations, for a total height of 1.5 metres. By midnight, the 770 square metres of plot #12 were filled. The next morning, the surface of the new concrete was flooded to prevent dehydration and the possible creation of micro-cracks on the concrete "skin." The plot's surface will remain underwater for at least 10 days—a phase known as concrete curing.

The remaining, central segment of the Tritium Building slab should be poured in the coming week. Then, sometime in the summer, it will be time to celebrate an even bigger moment of "pleasure and relief": the pouring of the first segment of the Tokamak Building slab, following the green light to proceed from the French Nuclear Safety Authority.


return to the latest published articles