Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Summer postcards from the ITER worksite

    The latest harvest of ITER construction photos may be taken from the same point—the tallest crane on site—but there is always an abundance of new detail to be g [...]

    Read more

  • The ring fortress

    ITER'ssteel-and-concretebioshield has become the definingfeature of Tokamak Complex construction. Twolevels only remain to be poured (out of six). It is a 'rin [...]

    Read more

  • The wave factory

    A year ago, work was just beginning on the steel reinforcement for the building's foundation slab. The Radio Frequency Heating Building is now nearing the last [...]

    Read more

  • It's all happening inside

    Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has lookedfrom afar like a finished project. Butinside, tea [...]

    Read more

  • Along skid row

    They look like perfectly aligned emergency housing units. But of course they're not: the 18 concrete structures in the ITER cryoplant are massive pads that will [...]

    Read more

Of Interest

See archived articles

A perfect day for pouring

-R.A.

It takes a fisheye lens, which makes the steel reinforcement appear a bit distorted, to take in the whole of the concrete pouring scene for the Tritium Building slab ... (Click to view larger version...)
It takes a fisheye lens, which makes the steel reinforcement appear a bit distorted, to take in the whole of the concrete pouring scene for the Tritium Building slab ...
In the scope of a regular building project, concrete pouring is a commonplace operation. For an ITER building, however, it is the culmination of months of calculations, modellization and painstaking preparation.

"It's a moment of great pleasure and relief," admits Laurent Patisson, Nuclear Buildings Section leader at ITER. "For a short time, the paperwork is over and we're into the real thing."

What added to his sense of satisfaction last Thursday 19 June, as a second segment of the Tritium Building slab was poured on the north side of the Tokamak Pit, was the weather. For both the workers and the concrete, the conditions were just perfect.

Unlike during pouring events scheduled mid-winter or high-summer, the concrete coming out of the on-site batching plant didn't require warming or cooling. Like a good wine, it was served at room temperature.

Operations began at 6:45 a.m. and followed a strict procedure detailed in a five-page program. Two giant 47-metre pumps, capable of delivering 50 cubic metres of concrete per hour, were guided from north to south, progressively filling the steel reinforcement structure with 1,155 cubic metres of specially formulated concrete.

Four layers were poured successively, each followed by vibrating operations, for a total height of 1.5 metres. By midnight, the 770 square metres of plot #12 were filled. The next morning, the surface of the new concrete was flooded to prevent dehydration and the possible creation of micro-cracks on the concrete "skin." The plot's surface will remain underwater for at least 10 days—a phase known as concrete curing.

The remaining, central segment of the Tritium Building slab should be poured in the coming week. Then, sometime in the summer, it will be time to celebrate an even bigger moment of "pleasure and relief": the pouring of the first segment of the Tokamak Building slab, following the green light to proceed from the French Nuclear Safety Authority.


return to the latest published articles