Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Upper ports | A very international effort

    The 18 upper ports of the ITER vacuum vessel are procured by Russia, manufactured in Germany, and mounted (in part) on the vessel sectors by contractors in Ital [...]

    Read more

  • Paint job | One level done, five to go

    The job is done and the effect is spectacular. At the deepest basement level (B2) of the Tokamak Building, the floors, walls, and ceilings are now perfectly whi [...]

    Read more

  • On site | Through the eyes of a crane operator

    Sitting in his cabin 80 metres above the ground, Alex Dumonteil enjoys a most spectacular view. To the north, on a clear day, he can see as far as the Alpine ri [...]

    Read more

  • Poloidal field coil #6 | The home stretch

    In Hefei, China, a 400-tonne ring magnet procured by the European Domestic Agency is entering the final phase of production—resin impregnation. In just over one [...]

    Read more

  • Neutral Beam Test Facility | SPIDER gets a beam for its first birthday

    Just one year ago, on 11 June 2018, the world's largest negative ion source was inaugurated at the ITER Neutral Beam Test Facility with the ignition of a brief [...]

    Read more

Of Interest

See archived entries

Closing in on the centre

Joëlle Elbez-Uzan, head of the Nuclear Safety, Licensing & Environmental Protection Division

A major milestone was reached on the Tokamak Complex worksite on 10 July, on the eve of European President Barroso and French Minister Fioraso's visit to ITER.

Some 940 cubic metres of specially formulated concrete were used in the first segment of the central part of the B2 slab. (Click to view larger version...)
Some 940 cubic metres of specially formulated concrete were used in the first segment of the central part of the B2 slab.
Following months of exchanges with the French Nuclear Safety Authority (ASN) and its technical experts at the Institute for Radioprotection and Nuclear Safety (IRSN), the hold point on the Tokamak Building slab (part of the Tokamak Complex slab) was lifted and pouring operations were allowed to proceed.

A 627-square-metre segment, adjacent to the Diagnostics Building slab on the north side of Seismic Pit, was the first of nine plots to be poured to complete the central area of the slab. The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August.

The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August. (Click to view larger version...)
The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August.
Last week's milestone was made possible by the mobilization of all stakeholders: the ITER Organization, the European agency Fusion for Energy and the Architect-Engineer Engage who, together, form the B2 Slab Task Force.

Integrated team work has once again demonstrated its efficiency. So let us continue toward success!


return to the latest published articles