Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | A vertical displacement event

    Three vertical storage tanks have been installed since last week outside of the cryoplant. The operation requires two powerful cranes working in tandem but also [...]

    Read more

  • Science in Texas | ITER draws enthusiasm

    At its Annual Meeting in Austin, Texas, the American Association for the Advancement of Science, AAAS, invited participants to illustrate how investment in basi [...]

    Read more

  • Image of the week | In the belly of the (flying) whale

    On 15 February, 'Isabelle' and 'Jeanne,' the last of the ten toroidal field coils manufactured in France for the EU-Japan tokamak JT-60SA, were swallowed into t [...]

    Read more

  • Nuclear safety | "A pragmatic and creative approach"

    Safety is at the core of all nuclear activities. Over the past seven decades—since the first experimental reactor was brought to criticality in 1942—codes, stan [...]

    Read more

  • Intellectual property | Modernizing processes and practices

    'A wise man will always allow a fool to rob him of ideas without yelling 'Thief.' If he is wise, he has not been impoverished,' says Ben Hecht in A Child of the [...]

    Read more

Of Interest

See archived articles

Closing in on the centre

Joëlle Elbez-Uzan, head of the Nuclear Safety, Licensing & Environmental Protection Division

A major milestone was reached on the Tokamak Complex worksite on 10 July, on the eve of European President Barroso and French Minister Fioraso's visit to ITER.

Some 940 cubic metres of specially formulated concrete were used in the first segment of the central part of the B2 slab. (Click to view larger version...)
Some 940 cubic metres of specially formulated concrete were used in the first segment of the central part of the B2 slab.
Following months of exchanges with the French Nuclear Safety Authority (ASN) and its technical experts at the Institute for Radioprotection and Nuclear Safety (IRSN), the hold point on the Tokamak Building slab (part of the Tokamak Complex slab) was lifted and pouring operations were allowed to proceed.

A 627-square-metre segment, adjacent to the Diagnostics Building slab on the north side of Seismic Pit, was the first of nine plots to be poured to complete the central area of the slab. The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August.

The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August. (Click to view larger version...)
The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August.
Last week's milestone was made possible by the mobilization of all stakeholders: the ITER Organization, the European agency Fusion for Energy and the Architect-Engineer Engage who, together, form the B2 Slab Task Force.

Integrated team work has once again demonstrated its efficiency. So let us continue toward success!


return to the latest published articles