Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Crane operator | A cabin in the sky

    There are times, at dusk, when the ITER construction platform resembles an airport, with roads and buildings illuminated by yellow and white lights. From their [...]

    Read more

  • Assembly | A colossal task made manageable

    For the execution of work during the next project phase—machine and plant assembly up to First Plasma—the ITER Organization has chosen a contractual approach th [...]

    Read more

  • Neutral Beam Test Facility | A new agreement for a new era

    The ITER Organization and the Italian consortium Consorzio RFX* have signed a new agreement governing the construction and operation of the ITER Neutral Beam Te [...]

    Read more

  • Load tests | Heavyweight champion

    The Assembly Hall, with its two giant tools towering 20 metres above ground, is one of the most spectacular locations on the ITER site. When a dummy load weighi [...]

    Read more

  • Fusion's new pioneers | How to go fast enough to make a difference

    Last month in New York, the Stellar Energy Foundation and the Fusion Industry Association co-hosted an invitation-only workshop: 'Roadmap to the Fusion Energy E [...]

    Read more

Of Interest

See archived entries

Closing in on the centre

Joëlle Elbez-Uzan, head of the Nuclear Safety, Licensing & Environmental Protection Division

A major milestone was reached on the Tokamak Complex worksite on 10 July, on the eve of European President Barroso and French Minister Fioraso's visit to ITER.

Some 940 cubic metres of specially formulated concrete were used in the first segment of the central part of the B2 slab. (Click to view larger version...)
Some 940 cubic metres of specially formulated concrete were used in the first segment of the central part of the B2 slab.
Following months of exchanges with the French Nuclear Safety Authority (ASN) and its technical experts at the Institute for Radioprotection and Nuclear Safety (IRSN), the hold point on the Tokamak Building slab (part of the Tokamak Complex slab) was lifted and pouring operations were allowed to proceed.

A 627-square-metre segment, adjacent to the Diagnostics Building slab on the north side of Seismic Pit, was the first of nine plots to be poured to complete the central area of the slab. The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August.

The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August. (Click to view larger version...)
The final foundation operations for the 400,000-tonne Tokamak Complex will be finalized when the perfectly circular last segment is poured before the end of August.
Last week's milestone was made possible by the mobilization of all stakeholders: the ITER Organization, the European agency Fusion for Energy and the Architect-Engineer Engage who, together, form the B2 Slab Task Force.

Integrated team work has once again demonstrated its efficiency. So let us continue toward success!


return to the latest published articles