  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Parking and more in JWS3 area

Surveys and levelling of the area around JWS3 are complete and a whole set of operations, among which storm basin excavation, is now underway. (Click to view larger version...)
Surveys and levelling of the area around JWS3 are complete and a whole set of operations, among which storm basin excavation, is now underway.
Work has been ongoing for the past three weeks to create a new lot that will provide 347 parking spaces for both ITER and Fusion for Energy staff working at JWS3, and also for worksite workers.

Surveys and levelling of the area around JWS3 have been completed and a whole set of operations is now underway: embankments (3,700 square metres) are being seeded with vegetation; roadways and underground storm basins are being created; manifolds for the drinking water network are being installed and three access gates are being opened in the 200-metre-long fence that secures the area.

Finishing work will follow, including exterior lighting.

All in all, some forty people from six companies, most of them local, are at work on this project.



return to the latest published articles