  • Summer postcards from the ITER worksite

    The latest harvest of ITER construction photos may be taken from the same point—the tallest crane on site—but there is always an abundance of new detail to be g [...]

    Read more

  • The ring fortress

    ITER'ssteel-and-concretebioshield has become the definingfeature of Tokamak Complex construction. Twolevels only remain to be poured (out of six). It is a 'rin [...]

    Read more

  • The wave factory

    A year ago, work was just beginning on the steel reinforcement for the building's foundation slab. The Radio Frequency Heating Building is now nearing the last [...]

    Read more

  • It's all happening inside

    Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has lookedfrom afar like a finished project. Butinside, tea [...]

    Read more

  • Along skid row

    They look like perfectly aligned emergency housing units. But of course they're not: the 18 concrete structures in the ITER cryoplant are massive pads that will [...]

    Read more

Of Interest

See archived articles

Two out of five and standing tall already

Two levels out of five and the pillars already stand tall on the platform. As the Assembly Building's steel skeleton is progressively bolted into place, the massive size of the construction becomes more and more evident.

Bolting together column sections, weighing as much as 23 tonnes, is a delicate manual operation. All in all, 220 sections will be assembled to form the building's east and west walls. (Click to view larger version...)
Bolting together column sections, weighing as much as 23 tonnes, is a delicate manual operation. All in all, 220 sections will be assembled to form the building's east and west walls.

Work on the structure began in September 2014. In April, when columns on both side of the slab have reached half their nominal height, workers will begin assembling the roof on the ground.

Once the roof has been fully assembled and the columns have reached their full height (approximately 60 metres), the frame of the roof can be lifted and bolted to the structure.

The installation of the crane rails will follow. The delivery of the supersized cranes designed to handle the heaviest ITER components is planned for the end of the year.