Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Right on time for the eclipse

Arriving from Santander, Spain, the convoy passed the gate to the ITER storage area at the very moment the eclipse reached its maximum. As a dull, ashen light fell on the surrounding countryside, the truck and its load came to a halt—the first equipment procured by the European Domestic Agency had safely reached its destination.

The load that was delivered on Friday 20 March is one of two emergency tanks that will collect tritiated water in the case of an abnormal situation during operation (the second will be delivered in April). (Click to view larger version...)
The load that was delivered on Friday 20 March is one of two emergency tanks that will collect tritiated water in the case of an abnormal situation during operation (the second will be delivered in April).
Manufactured by the Spanish company ENSA, the load consisted of a 20-tonne, 100 m³ tank destined for the ITER detritiation system. It is one of two "emergency tanks" that will collect the tritiated water in case an abnormal situation develops during operations (the second will be delivered in April).

The tank that was delivered on 20 March will be the first Safety Important Component to be installed in the Tokamak Complex. "The fact that the emergency tanks are being delivered now means that we will be able to install them before the next level is poured," explained Manfred Glugla, head of the ITER Fuel Cycle Engineering Division.

Representatives of the European Domestic Agency, ITER Organization, and ENSA celebrating the arrival of the 20-tonne tank at the ITER site. (Click to view larger version...)
Representatives of the European Domestic Agency, ITER Organization, and ENSA celebrating the arrival of the 20-tonne tank at the ITER site.
Five other tanks (one other emergency tank and 4 four-tonne, 20 m³ storage tanks) manufactured by ENSA will be delivered in the coming months on behalf of the European Domestic Agency to equip ITER's water detritiation system.

Read more about the function of the water detritiation tanks on the European Domestic Agency website.



return to the latest published articles