Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Computer-Aided Design | A new platform with Australia

    In September 2016, the signature of a Cooperation Agreement between the Australian Nuclear Science and Technology Organisation (ANSTO) and the ITER Organization [...]

    Read more

  • Ten years later | A prodigious adventure

    ITER began its existence as an aspiration in the early 1980s, as actors in the fusion community called for the joint machine that would demonstrate the feasibil [...]

    Read more

  • Image of the week | An impromptu visit

    Afteraddressing the UN Climate Change Conference on 15 November, French President Emmanuel Macron toured thecolourful COP23 exhibition zone. It was towards the [...]

    Read more

  • Cryoplant | How to install a compressor

    In order to properly install a helium compressor skid on its concrete pad, you need to start with a large push broom to sweep away the dust that inevitably accu [...]

    Read more

  • Magnetic system | Nine rings to fight the force

    Work on the pre-compression ringsof the ITER magnet system progresses in Europe, where work on a full-scale prototype is underway. These technically challenging [...]

    Read more

Of Interest

See archived articles

W7-X stellarator : the step-by-step march toward first plasma

Isabella Milch, Max-Planck-Institut für Plasmaphysik

Preparing a fusion device for first plasma is a step-by-step, carefully monitored process. In the last two months at Wendelstein 7-X, superconducting temperatures of 4 K were achieved, the vessel was sealed tight, and evacuation (to create a vacuum) began. In May, the magnets will be tested for the first time under power. Photo: IPP, Torsten Bräuer (Click to view larger version...)
Preparing a fusion device for first plasma is a step-by-step, carefully monitored process. In the last two months at Wendelstein 7-X, superconducting temperatures of 4 K were achieved, the vessel was sealed tight, and evacuation (to create a vacuum) began. In May, the magnets will be tested for the first time under power. Photo: IPP, Torsten Bräuer
Preparations for the operation of the Wendelstein 7-X fusion device in Greifswald, Germany are in full swing. In advance of the decisive magnet cooling stage many preparatory steps have been carried out, including the cleaning and flushing of the numerous helium cooling pipes and the start-up of the cryoplant (which had undergone thorough testing at an earlier date). 

On 13 February the gradual cooling of the cryoplant got off to a start. All systems were carefully monitored during the step-by-step process, with particular attention to checking for leaks in the piping or cooling systems.

Four weeks later, on 10 March, the target temperature of 4 K was attained—an essential milestone, as well as a prerequisite, for superconductivity in the magnets. Verifications will still take some time yet; presumably in May the magnets will be tested for the first time under power.

On 12 March the last ports in the plasma vessel were sealed vacuum-tight and evacuation of the vessel could begin. In addition to readying diagnostic equipment and working on switchgear and cabling, the verification of leak-tightness in the numerous connections and seals is proceeding. 

A "first plasma" in Wendelstein 7-X is expected by the end of 2015, at the latest.

Read the original article on the IPP website.


return to the latest published articles