Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

  • Component logistics | Consistency "from the cradle to the grave"

    There's a fun and easy way to demonstrate the importance of having all ITER parts properly tagged and identified in storage—organize a workshop and ask four com [...]

    Read more

  • Image of the week | Brewing storm

    In Provence, one gets tired of blue skies... so when the opportunity arises to capture the ITER site plunged in the darkness of an approaching storm, we rush to [...]

    Read more

  • Toroidal field coils | First cold test in Europe

    The first ITER toroidal field coil winding pack has spent nearly 20 days in a specially conceived cryostat at minus 193 °C (80 K), in a cold testing operation t [...]

    Read more

  • Central solenoid | All conductor received

    Officials from the US and Japanese fusion energy programs were at General Atomics' Magnet Technologies Center in California in early May to celebrate the delive [...]

    Read more

Of Interest

See archived articles

W7-X stellarator : the step-by-step march toward first plasma

Isabella Milch, Max-Planck-Institut für Plasmaphysik

Preparing a fusion device for first plasma is a step-by-step, carefully monitored process. In the last two months at Wendelstein 7-X, superconducting temperatures of 4 K were achieved, the vessel was sealed tight, and evacuation (to create a vacuum) began. In May, the magnets will be tested for the first time under power. Photo: IPP, Torsten Bräuer (Click to view larger version...)
Preparing a fusion device for first plasma is a step-by-step, carefully monitored process. In the last two months at Wendelstein 7-X, superconducting temperatures of 4 K were achieved, the vessel was sealed tight, and evacuation (to create a vacuum) began. In May, the magnets will be tested for the first time under power. Photo: IPP, Torsten Bräuer
Preparations for the operation of the Wendelstein 7-X fusion device in Greifswald, Germany are in full swing. In advance of the decisive magnet cooling stage many preparatory steps have been carried out, including the cleaning and flushing of the numerous helium cooling pipes and the start-up of the cryoplant (which had undergone thorough testing at an earlier date). 

On 13 February the gradual cooling of the cryoplant got off to a start. All systems were carefully monitored during the step-by-step process, with particular attention to checking for leaks in the piping or cooling systems.

Four weeks later, on 10 March, the target temperature of 4 K was attained—an essential milestone, as well as a prerequisite, for superconductivity in the magnets. Verifications will still take some time yet; presumably in May the magnets will be tested for the first time under power.

On 12 March the last ports in the plasma vessel were sealed vacuum-tight and evacuation of the vessel could begin. In addition to readying diagnostic equipment and working on switchgear and cabling, the verification of leak-tightness in the numerous connections and seals is proceeding. 

A "first plasma" in Wendelstein 7-X is expected by the end of 2015, at the latest.

Read the original article on the IPP website.


return to the latest published articles