Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Home at last

R.A.

Passing through Saint Paul-lez-Durance (pop. 987), the last village before arriving at ITER. (Click to view larger version...)
Passing through Saint Paul-lez-Durance (pop. 987), the last village before arriving at ITER.
There's a strange beauty to the transport of ITER components. It comes from the revolving lights piercing the night, from the slow progress of the trailer and its escort of a dozen vehicles, from the deserted roads and sleeping villages...

For three nights, from 4 to 7 May, the second Highly Exceptional Load (HEL) to be delivered to ITER made its way along the ITER Itinerary. A few minutes past 3:00 a.m., on Thursday 7 May, two large trailers—each loaded with a 79-ton cylindrical tank—passed the gate of the ITER site.

Five weeks after the US-procured components had embarked for their transatlantic voyage and 11 days after they were unloaded at Marseille's industrial harbour in Fos-sur-Mer, the tanks had reached their home at last.

The final leg of the voyage, from the village Meyrargues to the ITER site, was uneventful—which is the best possible result for such a delicate logistics operation. The schedule was respected and even improved by half an hour. By mid-afternoon both tanks had been unloaded and carefully stored into the large hangar at the entrance to ITER Headquarters.

Out in the open they resembled giant beer kegs. In the hangar, they looked like the segments of a star-bound rocket.


return to the latest published articles