Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Vacuum vessel| Windows with tailored appendages

    Each of the vacuum vessel's 44 openings will have custom-made 'extensions' to create the junction to the cryostat. The first link in the two-part chain—the port [...]

    Read more

  • Image of the week | Hooked!

    Big, powerful cranes need big, powerful hooks. The hook pictured in this image is one of four that belong to the double overhead bridge crane installed 43 metr [...]

    Read more

  • Project management | The elephant must be sliced

    Any way you cut it, ITER is fantastically complex. Whether you're counting components or the lines in the machine assembly schedule, or taking a closer look at [...]

    Read more

  • Open Doors Day | Front-row experience

    Craning their necks to take in the full size of what will be the ITER Tokamak, the crowd reacted spontaneously: 'This is much bigger than I thought.' 'Really im [...]

    Read more

  • Electrical system| Aiming for "zero fail"

    If something goes wrong in your electrical installation at home you might lose the contents of your freezer—an aggravating occurrence but not a disastrous one. [...]

    Read more

Of Interest

See archived articles

First plant components now in place

R.A.

A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit. (Click to view larger version...)
A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ITER installation have all reached the ITER site. The first one had been the first Highly Exceptional Load to travel along the ITER Itinerary in January; three more were delivered on 21 May in a single transport operation.

A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place—the first installed components of the ITER plant.

The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.

The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "ITER could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ITER Electrical Power Distribution section leader Joël Hourtoule.

The second pair of transformers will be installed in the coming weeks.

View a slide show of the convoy and transformer installation below.


return to the latest published articles