Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • ITER Council: project metrics confirm performance

    The governing body of the ITER Organization, the ITER Council, met for the twenty-first time on 15 and 16 November 2017 under the chairmanship of Won Namkung (K [...]

    Read more

  • COP 23 | Placing ITER on the global scene

    On the western bank of theRhine and not far from the seat of the UN Climate Change Secretariat, world leaders are discussing how to push ahead for international [...]

    Read more

  • Japan's MEXT Minister | Seeing is believing

    On 4 November, ITER received Yoshimasa Hayashi, the Japanese Minister of MEXT—the Ministry of Education, Culture, Sports, Science and Technology with oversight [...]

    Read more

  • Architect Engineer | ENGAGE receives prestigious award

    Since 2006, the French 'Grand Prix de l'Ingénierie' has recognized engineering projects and/or teams that are remarkable in terms of scope, innovation, complexi [...]

    Read more

  • Sub-assembly tools | One foot inside

    The twin Korean giants already have a foot inside the Assembly Hall—literally. The foot—or 'bottom inboard column' in ITER parlance—is a 4.4-metre-long steel [...]

    Read more

Of Interest

See archived articles

First plant components now in place

R.A.

A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit. (Click to view larger version...)
A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ITER installation have all reached the ITER site. The first one had been the first Highly Exceptional Load to travel along the ITER Itinerary in January; three more were delivered on 21 May in a single transport operation.

A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place—the first installed components of the ITER plant.

The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.

The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "ITER could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ITER Electrical Power Distribution section leader Joël Hourtoule.

The second pair of transformers will be installed in the coming weeks.

View a slide show of the convoy and transformer installation below.


return to the latest published articles