Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.
If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.
30th ITER Council: Progress in a time of challenge and transition
The Council chamber on the fifth floor of the ITER Headquarters building resonated once again with the sound of voices as Member representatives gathered for th [...]
After more than two years, ITER has resumed a tradition that dates back to 2007—Open Doors Day. On Saturday 18 June, more than 50 "volunteers," staff [...]
ITER Robots | Cultivating curiosity and creativity
Robotics are everywhere. As technology develops, robots are playing an increasing role in industry, medicine, agriculture and many other fields. In ITER, the op [...]
Twelve years after construction work began on the ITER platform, the installation has acquired its near-final appearance. More than 85 percent of civil works ar [...]
In the days and weeks to come, the sector module that was installed in the Tokamak assembly pit on 11-12 May will be moved closer to its final position. Hydraul [...]
A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ITER installation have all reached the ITER site. The first one had been the first Highly Exceptional Load to travel along the ITER Itinerary in January; three more were delivered on 21 May in a single transport operation.
A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place—the first installed components of the ITER plant.
The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.
The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "ITER could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ITER Electrical Power Distribution section leader Joël Hourtoule.
The second pair of transformers will be installed in the coming weeks.
View a slide show of the convoy and transformer installation below.