Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Vacuum vessel | First segment completed in Korea

    The technically challenging fabrication of the ITER vacuum vessel is progressing in Korea, where Hyundai Heavy Industries has completed the first poloidal segme [...]

    Read more

  • Project progress | How do we know where we stand?

    If ITER were an ordinary project, like the building of a bridge, the construction of a highway or even the launching of a satellite into space, it would be rela [...]

    Read more

  • Radial walls| Thickest rebar and most intricate geometry

    The combined mass of the ITER Tokamak and its enveloping cryostat is equivalent to that of three Eiffel Towers. But not only is it heavy (23,000 tonnes) ... it [...]

    Read more

  • Next step | Japan revises its DEMO strategy

    In light of recent progress on the construction of ITER and developments in domestic fusion research, the Science and Technology Committee on Fusion Energy—part [...]

    Read more

  • Monaco-ITER Fellows | Campaign opens for the 6th generation

    The ink has only just dried on the second Monaco-ITER Partnership Arrangement. Funded by the Principality of Monaco, the Arrangement allows the ITER Organizatio [...]

    Read more

Of Interest

See archived articles

First plant components now in place

R.A.

A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit. (Click to view larger version...)
A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ITER installation have all reached the ITER site. The first one had been the first Highly Exceptional Load to travel along the ITER Itinerary in January; three more were delivered on 21 May in a single transport operation.

A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place—the first installed components of the ITER plant.

The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.

The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "ITER could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ITER Electrical Power Distribution section leader Joël Hourtoule.

The second pair of transformers will be installed in the coming weeks.

View a slide show of the convoy and transformer installation below.


return to the latest published articles