Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • First toroidal field coil case: on target in Japan

    At Mitsubishi Heavy Industries' Kobe plant in western Japan, one of the world's largest milling machines is turning out sub-segments for ITER'storoidal field co [...]

    Read more

  • Tokamaks of the world, contribute!

    The annual end-of-year meeting of the International Tokamak Physics Activity (ITPA) was held at ITER Headquarters from 6 to 8 December. There are dozens of to [...]

    Read more

  • Vacuum vessel component passes pressure equipment tests

    Extending out from the openings in the ITER vacuum vessel (or "ports") are components called port stub extensions that will be welded to the vacuum ve [...]

    Read more

  • A home for (oversized) hobbits?

    In the realm of the (plasma) ring one shouldn't be too surprised to find structures closely resembling the door to a hobbit's hole. But in this case, these lar [...]

    Read more

  • Progress in pictures

    The 2016 edition of the ITER Photobook has just been released─58 pages that cover progress in construction and manufacturing and some of the highlights in the l [...]

    Read more

Of Interest

See archived articles

First plant components now in place

-R.A.

A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit. (Click to view larger version...)
A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ITER installation have all reached the ITER site. The first one had been the first Highly Exceptional Load to travel along the ITER Itinerary in January; three more were delivered on 21 May in a single transport operation.

A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place — the first installed components of the ITER plant.

The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.

The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "ITER could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ITER Electrical Power Distribution section leader Joël Hourtoule.

The second pair of transformers will be installed in the coming weeks.

View a slide show of the convoy and transformer installation below.
 

 



return to the latest published articles