First plant components now in place

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • In-vessel coils | First components arrive on site

    ITER has received the first shipments of mineral-insulated conductor for ITER's in-vessel coils. The first lengths are destined for winding and bending trials a [...]

    Read more

  • Controlling divertor power fluxes in 3D | ITER Scientist Fellows make progress

    New research results open a path to an integrated solution for optimizing the control of stationary and transient power fluxes on ITER. Tokamak plasmas are b [...]

    Read more

  • Cooperation | Canada returns to the table

    Canada, one of the early participants in ITER, is back in the project. On Thursday 15 October, Bernard Bigot, on behalf of the ITER Organization, and Assistant [...]

    Read more

  • Heat rejection basins | A massive fill-up

    When the ITER Tokamak begins producing burning plasmas and auxiliary systems are operating at full capacity, the amount of heat to be removed from the installat [...]

    Read more

  • Fusion world | Teaching teachers about fusion

    The possibility to visit three fusion facilities, all in one afternoon. Welcome to the new virtual world! More than 300 science teachers recently seized the opp [...]

    Read more

Of Interest

See archived entries

First plant components now in place

R.A.

A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit. (Click to view larger version...)
A powerful crane and worker dexterity - that's what is needed to precisely position the 87-ton component onto the supports that span the gravel-covered pit.
The four US-procured transformers that will be needed to distribute power to the ITER installation have all reached the ITER site. The first one had been the first Highly Exceptional Load to travel along the ITER Itinerary in January; three more were delivered on 21 May in a single transport operation.

A mere two hours after arrival, one of the four transformers was readied for installation on the platform in the vicinity of the the 400 kV switchyard. A powerful crane was used to position the 87-ton component on its dedicated pad; the same operation was duplicated the following day. Two transformers are now place—the first installed components of the ITER plant.

The pad onto which each transformer is solidly anchored covers a 1.5-metre-deep, gravel-covered pit that has been dimensioned to receive the 44 cubic metres of oil the component contains (oil is used as an insulator) in case of a leak. Eight-metre walls stand between the pads to prevent a possible fire in one transformer from spreading to the others.

The four transformers will bring down the voltage from 400 kV to the standard 20 kV of industrial installations. "ITER could operate with only three transformers but for reasons of flexibility and redundancy, we have opted for four," explains ITER Electrical Power Distribution section leader Joël Hourtoule.

The second pair of transformers will be installed in the coming weeks.

View a slide show of the convoy and transformer installation below.


return to the latest published articles