Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • FEC2020 | Seeking sponsors for 28th IAEA Fusion Energy Conference

    For only the third time since 1961, the International Atomic Energy Agency's Fusion Energy Conference will be taking place in France—hosted jointly by the Frenc [...]

    Read more

  • Nuclear safety | Under constant scrutiny

    Because one of the elements involved in the fusion reaction is the radioactive isotope tritium, and because the hydrogen fusion reaction itself generates a high [...]

    Read more

  • Power conversion | Alien structures and strange contraptions

    There are places in ITER that seem to belong to another world, places full of alien structures and strange contraptions. The feeling—a mixture of awe and puzzle [...]

    Read more

  • Tokamak Complex | A changing landscape

    For the past three years, the view from the top of the highest worksite crane has not changed much. Inside of the Tokamak Complex, 80 metres below, concrete gal [...]

    Read more

  • Ion cyclotron heating | How to pump 20 MW of power into 1 gram of plasma

    To power the ion cyclotron system, the ITER Organization and its partners are designing not only new antennas, which will be housed in the tokamak vessel, but a [...]

    Read more

Of Interest

See archived entries

Central solenoid : 11 tooling stations to commission

Lynne Degitz, US ITER

A partial view of the General Atomics module fabrication line, with two winding station tables visible behind a yellow rail. Photo: GA (Click to view larger version...)
A partial view of the General Atomics module fabrication line, with two winding station tables visible behind a yellow rail. Photo: GA
With winding of the first production module for ITER's central solenoid well underway, the US Domestic Agency (US ITER) and its contractor, General Atomics, are now commissioning all of the necessary tooling stations for the 13 Tesla, 1,000-metric-ton electromagnet. Eleven unique stations will form the module manufacturing line at the GA Magnet Technologies Center in Poway, California.

One challenge to commissioning the unique stations is coming up with an appropriate coil that does not use any production conductor. The commissioning process requires a variety of trials to assure that the tooling will perform specific fabrication tasks as predicted. After commissioning, the workstation undergoes a manufacturing readiness review.

"General Atomics has been very clever," said US ITER central solenoid systems manager David Everitt. "They made what we call a 'Frankenstein coil' to test and commission numerous stations. This commissioning coil is made out of qualification samples of real conductor which were coupled with other samples such as empty jacket material."

The commissioning coil is two layers high with real conductor on a portion of one layer of the coil.

At the turn insulation station, fiberglass insulation tape will be wrapped around the wound conductor coils. Photo: GA (Click to view larger version...)
At the turn insulation station, fiberglass insulation tape will be wrapped around the wound conductor coils. Photo: GA
"When you see everything that happens at General Atomics every day, you appreciate that they have a very talented crew out there. We have an innovative team who is highly invested in the project," said Everitt.

So far, the coil has been used for commissioning activities at stations for joint and terminals preparation, stacking, joining plus helium penetrations, reaction heat treatment and part of turn insulation. All or part of ten of eleven stations are now in place at General Atomics and eight of these stations have completed some or all acceptance testing and commissioning activities.

One of the more complex stations to install and commission handles turn insulation. This workstation wraps insulating fiberglass tape and Kapton around the conductor after the coils have been wound and heat treated. In order to wrap the conductor, the coil must be "un-sprung" for insulation wrapping and then reassembled. After insulation is completed, the coils move down the production line to the vacuum pressure impregnation station, where a three-part epoxy mixture is injected under vacuum to impregnate the previously applied turn and ground insulation materials that surround the coil. The epoxy provides both electrical insulation and structural support to the 110-metric-ton magnet module.

A major investment has been the construction of a cold testing facility for the final testing of each module at 4 Kelvin, comparable to ITER's operating temperature for the central solenoid. Commissioning of the cold testing facility is planned for early 2016, and equipment installation has begun.

As the home of the DIII-D National Fusion Facility, General Atomics has a half-century long history with fusion. The Magnet Technologies Center has not only a 4 Kelvin cryogenic system needed for superconducting magnets, but also a large vacuum cryostat for testing magnets, a 50 kA, 10 V power supply, and a fast discharge dump circuit for magnet protection.

See the original article here.



return to the latest published articles