Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Pre-compression ring facility | Ready to exert serious pressure

    The tool is ready; the first prototypes are on their way. Soon, a specialized test bench at CNIM (France) will enter into service to verify the resistance of th [...]

    Read more

  • Internal auditor | A partner in identifying solutions

    ITER's new internal auditor Friedrich Lincke goes where his expertise is needed to make a difference. Armed with valuable experience from many years of service [...]

    Read more

  • Sub-assembly tools | A 12-tonne beam, a crane and a little push

    There is nothing remarkable about lifting a 12-tonne beam. Except when it happens in the spectacular setting of the ITER Assembly Hall, and the beam needs to be [...]

    Read more

  • Hiring | Skilled candidates wanted

    In 2018 the number of staff members employed by the ITER Organization increased to 858, as skilled and qualified candidates joined from each of the seven ITER M [...]

    Read more

  • Toroidal field coils | First ITER magnet arrives this year

    A major milepost is projected for 2019 as the first of ITER's powerful, high-field magnets is scheduled to arrive from Japan. Let's take a look behind the scene [...]

    Read more

Of Interest

See archived entries

Qualification activities to start on ITER's "ring" magnets

K.D.

The clean area on the south side of the building will host two winding tables, where lengths of niobium-titanium conductor will be fed from two spools simultaneously (''two-in-hand'' winding), insulated, and wound into double pancakes. Dummy conductor for tooling qualification is stored in the crates, at left. (Click to view larger version...)
The clean area on the south side of the building will host two winding tables, where lengths of niobium-titanium conductor will be fed from two spools simultaneously (''two-in-hand'' winding), insulated, and wound into double pancakes. Dummy conductor for tooling qualification is stored in the crates, at left.
In ITER's largest on-site manufacturing facility, work has begun to prepare for the start of industrial activities.

The Poloidal Field Coils Winding Facility, a 257-metre-long facility on the ITER platform inaugurated in 2012, will house the fabrication and assembly activities for the largest ring-shaped magnets. Since July, two clean areas have been framed out for coil winding activities and the first crates of equipment have been delivered and stored in preparation for the installation of full winding tooling in November.

Six poloidal field coils will encircle the ITER vacuum chamber like so many parallels of latitude to shape the plasma and contribute to its stability by "pinching" it away from the walls. The smallest poloidal field coil (PF1) situated at the top of the machine will be supplied by Russia; the five others are under the procurement responsibility of Europe.

Due to the impressive size and weight of the middle coils (24 metres in diameter for the largest, 400 tonnes for the heaviest), Europe will carry out the successive stages of coil manufacture—winding and insulation, resin impregnation, stacking and assembly—on-site. PF6 (at the bottom of the machine) will be manufactured in China, according to the terms of an agreement concluded with the European Domestic Agency.

Overhead cranes will travel the length of the 257-metre building to transport the double pancake windings from station to station. The complete process, from winding to finished coil, will take between two and three years per coil. (Click to view larger version...)
Overhead cranes will travel the length of the 257-metre building to transport the double pancake windings from station to station. The complete process, from winding to finished coil, will take between two and three years per coil.
The European agency has divided the manufacturing process for poloidal field coils 2-5 into a number of work packages to cover overall engineering integration, tooling equipment, site and infrastructure, manufacturing and cold testing. Four of six contracts have now been signed, including those for winding tooling (SEA ALP, Italy), site and infrastructure (Dalkia-Veolia, France), and engineering integration (ASG Superconductors, Italy).

At the SEA ALP factory in Italy, the winding table and associated auxiliary equipment has been manufactured, assembled and tested, and the first batch of equipment is now on its way to the ITER site. The winding contractor will now be responsible for the installation and commissioning of the equipment in the winding facility as well as for training personnel in its use.

The first activity on the winding line will be to use "dummy" conductor made of copper (instead of the real superconducting materials) to commission the winding line; China has delivered two batches of dummy conductor for this purpose that are currently stored in the Poloidal Field Coils Winding Facility. Following this qualification phase, the series production of double pancakes (flat, spiralled coils that are stacked in up to nine layers to form the coil winding packs) can begin.

A short video on in-factory equipment testing is available on the European Domestic Agency website.


return to the latest published articles