Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Safely stored

In the 257-metre-long Poloidal Field Coils Winding Facility, the newly installed tools occupy only half of the building's length. This leaves a lot of free space that can be used for other purposes, such as storing four 155-tonne, 47-metre long girders for the Assembly Hall overhead cranes.

 (Click to view larger version...)
Manoeuvring such long and heavy pieces of steel into storage is a slow and delicate process. Every movement of the 32-wheel modular trailer that carries each beam must be carefully planned and executed with utmost precision.

 (Click to view larger version...)
Twice last week, the operation was performed to perfection: the two girders that were delivered on 18 and 25 March are now safely stored inside the winding facility; two more will join them in April.

 (Click to view larger version...)
The storage will be of relatively short duration, however, as the girders and their trolleys will be installed in the Assembly Hall in June.


return to the latest published articles