Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • A world in itself

    From a height of some 50 metres, you have the entire ITER worksite at your feet. The long rectangle of the Diagnostics Building stands out in the centre, with [...]

    Read more

  • US completes toroidal field deliveries for ITER

    The US Domestic Agency achieved a major milestone in February by completing the delivery of all US-supplied toroidal field conductor to the European toroidal fi [...]

    Read more

  • Thin diagnostic coils to be fitted into giant magnets

    Last week was marked by the first delivery of diagnostic components—Continuous External Rogowski (CER) coils—from the European Domestic Agency to the ITER Organ [...]

    Read more

  • Addressing the challenge of plasma disruptions

    Plasma disruptions are fast events in tokamak plasmas that lead to the complete loss of the thermal and magnetic energy stored in the plasma. The plasma control [...]

    Read more

  • Blending (almost) seamlessly into the landscape

    Located in the foothills of the French Pre-Alps, the ITER installation blends almost seamlessly into the landscape. The architects' choice ofmirror-like steel c [...]

    Read more

Of Interest

See archived articles

Manufacturing milestones in Korea

-ITER Korea

Welding has begun in Korea on the first column segments for the 800-tonne Sector Sub-Assembly Tool. (Click to view larger version...)
Welding has begun in Korea on the first column segments for the 800-tonne Sector Sub-Assembly Tool.
During a recent tour of industrial contractors and sub-contractors, the head of the Korean Domestic Agency Kijung Jung and staff members were able to photograph manufacturing progress on two procurement packages that fall under Korean scope—assembly tooling and the ITER thermal shield.

The group first visited Taekyung Heavy Industry in Changwon, where manufacturing activities are underway on the Sector Sub-Assembly Tool. Six stories high, made of 800 tonnes of steel each, two Sector Sub-Assembly tools will work side by side in the ITER Assembly Building to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit. The contractor has finished all of the roll-bending procedures for the main columns of the first tool and has begun welding the first segments of bended rolls (pictured). Taekyung is a sub-contractor to SFA Engineering, which is main supplier of the Sector Sub-Assembly Tools.

The team from ITER Korea stands in front of a 40° sector of the ITER thermal shield. The Director of the Korean Domestic Agency, Kijung Jung, is fourth from right. (Click to view larger version...)
The team from ITER Korea stands in front of a 40° sector of the ITER thermal shield. The Director of the Korean Domestic Agency, Kijung Jung, is fourth from right.
The second visit was to Sam Hong Machinery in Changwon to verify manufacturing progress on the ITER thermal shield, which will be installed between the vacuum vessel and the cryostat to minimize heat loads transferred by thermal radiation. Sam Hong Machinery, which is working under contract with the main supplier SFA, is responsible for welding, machining, silver coating and pre-assembly activities. The fabrication is progressing simultaneously on all nine 40° thermal shield sectors.

Next month, the cooling tube will be welded on the inboard section of sector #6—one of the first components of the thermal shield scheduled for delivery to ITER. A special facility has also been constructed at Sam Hong Machinery for silver coating operations. Coating baths measuring 9 x 3 x 6 metres—the largest in the world—will be used to apply low-emissivity silver coating to both sides of the shield plates. Silver coating of the first sectors will begin in November.


return to the latest published articles