Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • In-vessel electrical systems | What it takes to wire up a fusion reactor

    While the challenges of keeping cables operational in harsh environments such as jet engines and nuclear fission reactors have been understood for a long time, [...]

    Read more

  • Assembly preparation | Off goes the lid

    In the summer of 2017, a circular platform was installed inside of the large steel-and-concrete cylinder of the Tokamak pit. The 200-tonne structure was meant t [...]

    Read more

  • Deliveries | Two coils on their way

    For the past five years, 'highly exceptional loads' (HEL) have been successfully travelling along the ITER Itinerary to be delivered to the ITER site. As the pr [...]

    Read more

  • ITER NOW video | Ready for the big lifts

    This new video in our "ITER NOW" series provides an insider's view of the recent load tests performed as the ITER Organization prepares for the machin [...]

    Read more

  • Divertor | Far more than a fancy ashtray

    It has been likened to the filter of a swimming pool or an oversized ashtray. It has been called alien in shape and hellish in its affinity for heat. But whatev [...]

    Read more

Of Interest

See archived entries

Manufacturing milestones in Korea

ITER Korea

Welding has begun in Korea on the first column segments for the 800-tonne Sector Sub-Assembly Tool. (Click to view larger version...)
Welding has begun in Korea on the first column segments for the 800-tonne Sector Sub-Assembly Tool.
During a recent tour of industrial contractors and sub-contractors, the head of the Korean Domestic Agency Kijung Jung and staff members were able to photograph manufacturing progress on two procurement packages that fall under Korean scope—assembly tooling and the ITER thermal shield.

The group first visited Taekyung Heavy Industry in Changwon, where manufacturing activities are underway on the Sector Sub-Assembly Tool. Six stories high, made of 800 tonnes of steel each, two Sector Sub-Assembly tools will work side by side in the ITER Assembly Building to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit. The contractor has finished all of the roll-bending procedures for the main columns of the first tool and has begun welding the first segments of bended rolls (pictured). Taekyung is a sub-contractor to SFA Engineering, which is main supplier of the Sector Sub-Assembly Tools.

The team from ITER Korea stands in front of a 40° sector of the ITER thermal shield. The Director of the Korean Domestic Agency, Kijung Jung, is fourth from right. (Click to view larger version...)
The team from ITER Korea stands in front of a 40° sector of the ITER thermal shield. The Director of the Korean Domestic Agency, Kijung Jung, is fourth from right.
The second visit was to Sam Hong Machinery in Changwon to verify manufacturing progress on the ITER thermal shield, which will be installed between the vacuum vessel and the cryostat to minimize heat loads transferred by thermal radiation. Sam Hong Machinery, which is working under contract with the main supplier SFA, is responsible for welding, machining, silver coating and pre-assembly activities. The fabrication is progressing simultaneously on all nine 40° thermal shield sectors.

Next month, the cooling tube will be welded on the inboard section of sector #6—one of the first components of the thermal shield scheduled for delivery to ITER. A special facility has also been constructed at Sam Hong Machinery for silver coating operations. Coating baths measuring 9 x 3 x 6 metres—the largest in the world—will be used to apply low-emissivity silver coating to both sides of the shield plates. Silver coating of the first sectors will begin in November.


return to the latest published articles