Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

One more tank into position

Installation on the tanks into the lower basement level (B2) began in late March and will continue until all six plant components are in place. (Click to view larger version...)
Installation on the tanks into the lower basement level (B2) began in late March and will continue until all six plant components are in place.
In the basement of the ITER Tritium Plant, four storage tanks and two security tanks procured by Europe will handle the water involved in the recycling process of tritium. Installation on the tanks into the lower basement level (B2) began in late March and will continue until all six plant components are in place.

In the short video shot on 7 April, we watch as one of the 100 m³ security tanks is removed from temporary storage, transported to the platform, and lifted by crane into place.

The six water detritiation tanks (four 20 m³ tanks and two 100 m³ tanks) are the first plant components to be installed in the ITER Tokamak Complex. 

Watch the short video here.


return to the latest published articles