Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Thermal shield repair | Where are we at?

    Fitting the vacuum vessel sectors like a jacket, lining the inner wall of the cryostat, or covering the sides of vertical coil gravity supports, ITER's thermal [...]

    Read more

  • Assembly prep | Reviewing plans for in-vessel installation

    A thorough review of all 'in-vessel' assembly scope was organized by the ITER Machine Assembly Program in early February, with the active participation of senio [...]

    Read more

  • Image of the week | Last measurements before campaign

    In order to precisely identify the bevel regions that need to be rectified, metrologists from the SIMANN (SIMIC-Ansaldo) consortium are performing ultra-precise [...]

    Read more

  • Neutral Beam Test Facility | After upgrades, SPIDER testbed set to restart

    After a two-year shutdown for upgrades, the SPIDER testbed at the ITER Neutral Beam Test Facility in Padua, Italy, is preparing for commissioning and operation. [...]

    Read more

  • ITER Research Plan | Jointly preparing a new blueprint

    As part of work underway to update the ITER Project Baseline, a group of experts nominated by the Members met in February to evaluate the new blueprint for achi [...]

    Read more

Of Interest

See archived entries

Up go the girders (and trolleys)

It took 55 trucks to deliver the parts for the giant crawler crane and ten days to assemble them.
 
The red monster, with crawlers as big as a school bus and a mast reaching high above the roof of the Assembly Hall, was invested with a delicate mission: lifting and installing the elements of the double overhead bridge crane that will handle the massive ITER components during pre-assembly activities.

Positioned above the Assembly Hall, the crane's boom holds a man-sized hook that passes through the roof. The crane, delivered from Saudi Arabia for this lifting task, is operated by personnel from the Dutch company Mammoet. (Click to view larger version...)
Positioned above the Assembly Hall, the crane's boom holds a man-sized hook that passes through the roof. The crane, delivered from Saudi Arabia for this lifting task, is operated by personnel from the Dutch company Mammoet.
In order to lift the four girders and their corresponding trolleys into position 43 metres above the Assembly Hall basemat, the crawler crane was positioned outside the building. Its boom, high above the building, held a man-sized hook that passed through an opening in the roof and reached down to the waiting components.

Below, workers were busy adjusting cables, slings, braces and shackles in order to perfectly balance the first load to be lifted—one of the four girders, now fully equipped with 30 tonnes of gear motors, wheels, braces, and electrical equipment and weighing 186 tonnes.

Despite the spectacular setting and the size of the components, the professionals appeared unfazed. "It's a standard operation," says Roberto Lanza of the ITER Building & Civil Works Section. "We'll first lift then slightly tilt each girder in order to align it with the rails above."

The operation is a mix of brute force, high technology and worker know-how. Connected by radio to the lifting supervisor, the crane operator sitting in his cabin outside the building slowly lifts the load. Surveyors direct their laser beams to ensure that everything is proceeding nominally, and men on the ground and up in the rafters use ropes to adjust the component's position.

As with all things ITER, tolerances are stringent. "The final adjustment must be ... and will be ... perfect," says Roberto.

Two of the four girders are now in place as well as one of the four 100-tonne trolleys. Lift operations will continue and by the end of this week the Assembly Hall will be fitted out with one of the most spectacular tools required for the assembly of the machine.

Click here to view a video of the lift operations.


return to the latest published articles