Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Neighbours | In goes the antenna

    Just a short distance from the ITER site, the Institute for Magnetic Fusion Research (IRFM) is modifying the Tore Supra plasma facility which, once transformed, [...]

    Read more

  • Remote handling | Off-site test facility for design evaluation

    Through a technical collaboration established between the ITER Organization and the UK Atomic Energy Authority (UKAEA) in 2017, the UKAEA's centre for Remote Ap [...]

    Read more

  • Poloidal field coils | A tailor-made ring

    They work like tailors, carefully taking measurements and cutting immaculate fabric with large pairs of scissors. But they're not making a white three-piece sui [...]

    Read more

  • Fusion world | Record results at KSTAR

    Experiments in the Korean tokamakKSTAR in 2017 achieved record-length periods of ELM suppression by the application of three-dimensional magnetic fields with in [...]

    Read more

  • JT-60 SA| Cryostat ready for Europe-Japan tokamak

    The cryostat vessel body of the JT-60SA tokamakhas been successfully manufactured and pre-assembled at a factory in Spain, and will soon be transferred to the J [...]

    Read more

Of Interest

See archived articles

Up go the girders (and trolleys)

It took 55 trucks to deliver the parts for the giant crawler crane and ten days to assemble them.
 
The red monster, with crawlers as big as a school bus and a mast reaching high above the roof of the Assembly Hall, was invested with a delicate mission: lifting and installing the elements of the double overhead bridge crane that will handle the massive ITER components during pre-assembly activities.

Positioned above the Assembly Hall, the crane's boom holds a man-sized hook that passes through the roof. The crane, delivered from Saudi Arabia for this lifting task, is operated by personnel from the Dutch company Mammoet. (Click to view larger version...)
Positioned above the Assembly Hall, the crane's boom holds a man-sized hook that passes through the roof. The crane, delivered from Saudi Arabia for this lifting task, is operated by personnel from the Dutch company Mammoet.
In order to lift the four girders and their corresponding trolleys into position 43 metres above the Assembly Hall basemat, the crawler crane was positioned outside the building. Its boom, high above the building, held a man-sized hook that passed through an opening in the roof and reached down to the waiting components.

Below, workers were busy adjusting cables, slings, braces and shackles in order to perfectly balance the first load to be lifted—one of the four girders, now fully equipped with 30 tonnes of gear motors, wheels, braces, and electrical equipment and weighing 186 tonnes.

Despite the spectacular setting and the size of the components, the professionals appeared unfazed. "It's a standard operation," says Roberto Lanza of the ITER Building & Civil Works Section. "We'll first lift then slightly tilt each girder in order to align it with the rails above."

The operation is a mix of brute force, high technology and worker know-how. Connected by radio to the lifting supervisor, the crane operator sitting in his cabin outside the building slowly lifts the load. Surveyors direct their laser beams to ensure that everything is proceeding nominally, and men on the ground and up in the rafters use ropes to adjust the component's position.

As with all things ITER, tolerances are stringent. "The final adjustment must be ... and will be ... perfect," says Roberto.

Two of the four girders are now in place as well as one of the four 100-tonne trolleys. Lift operations will continue and by the end of this week the Assembly Hall will be fitted out with one of the most spectacular tools required for the assembly of the machine.

Click here to view a video of the lift operations.


return to the latest published articles