Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryolines | Another day, another spool

    Having wedged his body and equipment into the cramped space between the ceiling and the massive pipe, a worker is busy welding two cryolines spools. A few metre [...]

    Read more

  • Image of the week | Bearings unveiled

    The construction teams are in the last stages of preparing the Tokamak pit for the first major operation of ITER machine assembly: the lowering of the cryostat [...]

    Read more

  • Technology | Perfecting tritium breeding for DEMO and beyond

    While ITER will never breed tritium for its own consumption, it will test breeding blanket concepts—the tools and techniques that designers of future DEMO react [...]

    Read more

  • Fusion world | Japan and Europe complete the assembly of JT-60SA

    The JT-60SA fusion experiment in Naka, Japan, is designed to explore advanced plasma physics in support of the operation of ITER and next-phase devices. After s [...]

    Read more

  • Manufacturing | Thermal shield milestone in Korea

    Six years after the start of fabrication, Korean contractor SFA has completed the last 40° sector of vacuum vessel thermal shield. The stainless steel panels, c [...]

    Read more

Of Interest

See archived entries

Up go the girders (and trolleys)

It took 55 trucks to deliver the parts for the giant crawler crane and ten days to assemble them.
 
The red monster, with crawlers as big as a school bus and a mast reaching high above the roof of the Assembly Hall, was invested with a delicate mission: lifting and installing the elements of the double overhead bridge crane that will handle the massive ITER components during pre-assembly activities.

Positioned above the Assembly Hall, the crane's boom holds a man-sized hook that passes through the roof. The crane, delivered from Saudi Arabia for this lifting task, is operated by personnel from the Dutch company Mammoet. (Click to view larger version...)
Positioned above the Assembly Hall, the crane's boom holds a man-sized hook that passes through the roof. The crane, delivered from Saudi Arabia for this lifting task, is operated by personnel from the Dutch company Mammoet.
In order to lift the four girders and their corresponding trolleys into position 43 metres above the Assembly Hall basemat, the crawler crane was positioned outside the building. Its boom, high above the building, held a man-sized hook that passed through an opening in the roof and reached down to the waiting components.

Below, workers were busy adjusting cables, slings, braces and shackles in order to perfectly balance the first load to be lifted—one of the four girders, now fully equipped with 30 tonnes of gear motors, wheels, braces, and electrical equipment and weighing 186 tonnes.

Despite the spectacular setting and the size of the components, the professionals appeared unfazed. "It's a standard operation," says Roberto Lanza of the ITER Building & Civil Works Section. "We'll first lift then slightly tilt each girder in order to align it with the rails above."

The operation is a mix of brute force, high technology and worker know-how. Connected by radio to the lifting supervisor, the crane operator sitting in his cabin outside the building slowly lifts the load. Surveyors direct their laser beams to ensure that everything is proceeding nominally, and men on the ground and up in the rafters use ropes to adjust the component's position.

As with all things ITER, tolerances are stringent. "The final adjustment must be ... and will be ... perfect," says Roberto.

Two of the four girders are now in place as well as one of the four 100-tonne trolleys. Lift operations will continue and by the end of this week the Assembly Hall will be fitted out with one of the most spectacular tools required for the assembly of the machine.

Click here to view a video of the lift operations.


return to the latest published articles