Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Interview | Michel Huguet on the long chain of "fusion builders"

    Some thirty years ago, the ITER Project entered what is called the Engineering Design Activities, a phase which aimed at providing the engineering drawings and [...]

    Read more

  • Assembly | Long-term coil park

    Manufactured in China under a European contract, poloidal field coil #6 (PF6) was the first magnet to be installed in the assembly pit in late April 2021. Saili [...]

    Read more

  • On site | Safety comes first

    Whether they spend their day in an office at ITER or on one of the upper floors of the Tokamak Complex, driving a vehicle or manoeuvring a crane, every per [...]

    Read more

  • Visitors | EU Commissioner for Energy: "ITER is a unique project in frontier science"

    Kadri Simson, European Union Commissioner for Energy, spent Friday 17 September at ITER. In the course of her visit to key site installations and during the pre [...]

    Read more

  • Image of the week | 2nd vacuum vessel sector passes site tests

    On 27 August, the ITER community celebrated the safe arrival of vacuum vessel sector #1(7)—the second of four sectors expected from the Korean Domestic Agency. [...]

    Read more

Of Interest

See archived entries

And now the "finishing" touch

The main elements of the 1,500-tonne double overhead bridge crane—four girders and their corresponding trolleys—are now in place in the Assembly Hall. The big red crawler crane has been dismantled and is on its way to Sweden, where a 330-tonne "sphere" for liquid gas storage is waiting for a lift.

 (Click to view larger version...)
The most spectacular part of the operation is over. However, a considerable amount of work remains to be done, most of it at height, to finalize cabling connections, platform and walkway fittings, and the like--the "finishing" activities of the bridge crane installation.

By late September or early October, the two auxiliary cranes, each with a lifting capacity of 50 metric tonnes, will be delivered and installed. This time, there will be no need for a monster crawler crane operating from outside the building ...

Preliminary testing and commissioning are scheduled to begin in January/February 2017 for the large crane, and a few months later for the smaller one.


return to the latest published articles