Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • 23rd ITER Council | Pace and performance on track

    Working as an integrated team, the ITER Organization and seven Domestic Agencies are continuing to meet the project's demanding schedule to First Plasma in 2025 [...]

    Read more

  • Fusion Doctors | ITER hosts the future

    For three days last week, the ITER building was brimming with energy, inspiration and enthusiasm. One hundred and thirty-five young fusion aficionados took over [...]

    Read more

  • Fusion world | What's next for the stellarator?

    Earlier this year, the Wendelstein 7-X stellarator fusion project reported record achievements from its most recent experimental campaign. Newsline spoke with t [...]

    Read more

  • Metrology and the ITER machine | Perfectly planned points

    Inside of the Tokamak Complex, a network of 2,000 small 'fiducial target nests' will provide the reference datum for the dimensional control and alignment of ma [...]

    Read more

  • Breaking news | First component installed next week

    In the third week of November, the ITER Organization will be installing the first component of the machine in the basement of the Tokamak Building. The 10-met [...]

    Read more

Of Interest

See archived entries

And now the "finishing" touch

The main elements of the 1,500-tonne double overhead bridge crane—four girders and their corresponding trolleys—are now in place in the Assembly Hall. The big red crawler crane has been dismantled and is on its way to Sweden, where a 330-tonne "sphere" for liquid gas storage is waiting for a lift.

 (Click to view larger version...)
The most spectacular part of the operation is over. However, a considerable amount of work remains to be done, most of it at height, to finalize cabling connections, platform and walkway fittings, and the like--the "finishing" activities of the bridge crane installation.

By late September or early October, the two auxiliary cranes, each with a lifting capacity of 50 metric tonnes, will be delivered and installed. This time, there will be no need for a monster crawler crane operating from outside the building ...

Preliminary testing and commissioning are scheduled to begin in January/February 2017 for the large crane, and a few months later for the smaller one.


return to the latest published articles