Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • A wide angle on progress

    Whether captured from the top of a crane or from a drone hovering at an altitude of a few dozen metres, the ITER site isalways spectacular. After almost seven y [...]

    Read more

  • Inside the arena

    A visit to the deep "well" where the ITER Tokamak assembly will begin next year begins with a journey underground ... through a maze of giant pillars, [...]

    Read more

  • 10,000 tonnes of magnets to cool

    In ITER, huge volumesof liquid helium will be circulated throughout a complex, five-kilometre network of pipes, pumps and valves to keep the 10,000-tonne magnet [...]

    Read more

  • Heaviest convoy yet

    The triple convoy that reached ITER on Thursday 13 April wasthe heaviest ever organized since the beginning of "highly exceptional" deliveries in Janu [...]

    Read more

  • Gouging the giant's eye

    On the side of the ITER bioshield that faces the main ITER office building, four large openings have been preserved to allow passage for the neutral beam inject [...]

    Read more

Of Interest

See archived articles

Three more segments for the cryostat

One by one the elements that make up the base of the ITER cryostat—the single largest load of Tokamak assembly—are being delivered to the ITER site from India and safely stored in the Cryostat Workshop.

By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground. (Click to view larger version...)
By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground.
Twelve segments were delivered in December 2015 for tier 1 of the 1,250-tonne base section. Three further segments, weighing approximately 120 tonnes each and representing half of the elements needed to assemble tier 2, arrived at ITER in the early hours of Friday 24 June.

Work will begin this week on the assembly of the first support and transport frame—one of a set of three large steel structures that will support components, jigs and fixtures during the cryostat assembly process. The 30 x 30 metre frames will also act as transporters for the completed cryostat sections.

By mid-July, the welding machines should be installed in the Cryostat Workshop in time for welding operations to begin in August.

The final three segments of the cryostat base are scheduled for delivery in the first week of September.


return to the latest published articles