Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Crane operator | A cabin in the sky

    There are times, at dusk, when the ITER construction platform resembles an airport, with roads and buildings illuminated by yellow and white lights. From their [...]

    Read more

  • Assembly | A colossal task made manageable

    For the execution of work during the next project phase—machine and plant assembly up to First Plasma—the ITER Organization has chosen a contractual approach th [...]

    Read more

  • Neutral Beam Test Facility | A new agreement for a new era

    The ITER Organization and the Italian consortium Consorzio RFX* have signed a new agreement governing the construction and operation of the ITER Neutral Beam Te [...]

    Read more

Of Interest

See archived entries

Three more segments for the cryostat

One by one the elements that make up the base of the ITER cryostat—the single largest load of Tokamak assembly—are being delivered to the ITER site from India and safely stored in the Cryostat Workshop.

By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground. (Click to view larger version...)
By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground.
Twelve segments were delivered in December 2015 for tier 1 of the 1,250-tonne base section. Three further segments, weighing approximately 120 tonnes each and representing half of the elements needed to assemble tier 2, arrived at ITER in the early hours of Friday 24 June.

Work will begin this week on the assembly of the first support and transport frame—one of a set of three large steel structures that will support components, jigs and fixtures during the cryostat assembly process. The 30 x 30 metre frames will also act as transporters for the completed cryostat sections.

By mid-July, the welding machines should be installed in the Cryostat Workshop in time for welding operations to begin in August.

The final three segments of the cryostat base are scheduled for delivery in the first week of September.


return to the latest published articles