Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Thermal shield repair | Where are we at?

    Fitting the vacuum vessel sectors like a jacket, lining the inner wall of the cryostat, or covering the sides of vertical coil gravity supports, ITER's thermal [...]

    Read more

  • Assembly prep | Reviewing plans for in-vessel installation

    A thorough review of all 'in-vessel' assembly scope was organized by the ITER Machine Assembly Program in early February, with the active participation of senio [...]

    Read more

  • Image of the week | Last measurements before campaign

    In order to precisely identify the bevel regions that need to be rectified, metrologists from the SIMANN (SIMIC-Ansaldo) consortium are performing ultra-precise [...]

    Read more

  • Neutral Beam Test Facility | After upgrades, SPIDER testbed set to restart

    After a two-year shutdown for upgrades, the SPIDER testbed at the ITER Neutral Beam Test Facility in Padua, Italy, is preparing for commissioning and operation. [...]

    Read more

  • ITER Research Plan | Jointly preparing a new blueprint

    As part of work underway to update the ITER Project Baseline, a group of experts nominated by the Members met in February to evaluate the new blueprint for achi [...]

    Read more

Of Interest

See archived entries

Three more segments for the cryostat

One by one the elements that make up the base of the ITER cryostat—the single largest load of Tokamak assembly—are being delivered to the ITER site from India and safely stored in the Cryostat Workshop.

By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground. (Click to view larger version...)
By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground.
Twelve segments were delivered in December 2015 for tier 1 of the 1,250-tonne base section. Three further segments, weighing approximately 120 tonnes each and representing half of the elements needed to assemble tier 2, arrived at ITER in the early hours of Friday 24 June.

Work will begin this week on the assembly of the first support and transport frame—one of a set of three large steel structures that will support components, jigs and fixtures during the cryostat assembly process. The 30 x 30 metre frames will also act as transporters for the completed cryostat sections.

By mid-July, the welding machines should be installed in the Cryostat Workshop in time for welding operations to begin in August.

The final three segments of the cryostat base are scheduled for delivery in the first week of September.


return to the latest published articles