Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The magnet lab next door

    Two and a half years ago ITER and the French Alternative Energies and Atomic Energy Commission (CEA) entered a collaborationto prepare for the challenging task [...]

    Read more

  • Activity on every floor

    At every floor of the Tokamak Complex—from the lowest underground level (B2) all the way to the second regular level of the bioshield (L2)—there is intense acti [...]

    Read more

  • Bringing the Research Plan up to date

    The ITER Research Plan is an ITER baseline document which outlines the main lines of science and technology research derived from the project's mission goals. [...]

    Read more

  • Further validation for ring magnet fabrication

    Once a component mockup has been produced—and before fabrication can begin on the actual component or system—a manufacturing readiness review is required to ens [...]

    Read more

  • First central solenoid module ready for heat treatment

    In a major milestone, the US contractor responsible for the fabrication of the ITER central solenoid has successfully joined seven individual coil sections, or [...]

    Read more

Of Interest

See archived articles

Three more segments for the cryostat

One by one the elements that make up the base of the ITER cryostat—the single largest load of Tokamak assembly—are being delivered to the ITER site from India and safely stored in the Cryostat Workshop.

By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground. (Click to view larger version...)
By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground.
Twelve segments were delivered in December 2015 for tier 1 of the 1,250-tonne base section. Three further segments, weighing approximately 120 tonnes each and representing half of the elements needed to assemble tier 2, arrived at ITER in the early hours of Friday 24 June.

Work will begin this week on the assembly of the first support and transport frame—one of a set of three large steel structures that will support components, jigs and fixtures during the cryostat assembly process. The 30 x 30 metre frames will also act as transporters for the completed cryostat sections.

By mid-July, the welding machines should be installed in the Cryostat Workshop in time for welding operations to begin in August.

The final three segments of the cryostat base are scheduled for delivery in the first week of September.


return to the latest published articles