Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Real-time collaboration delivers for fusion computing

    A key computing system for ITER is now being trialled at the European tokamak JET, following collaboration betweenteams at the UK's Culham Centre for Fusion Ene [...]

    Read more

  • The balance of power

    It comes as no surprise that the French railway operator SNCF is the largest consumer of electricity in the country—it takes a lot of megawatts to power 500 sup [...]

    Read more

  • "Dummy" winding takes shape

    As orange lights flash and machines softly hum, layer one of a 'dummy' pancake winding (the building block of a poloidal field coil) is taking shape on the wind [...]

    Read more

  • As big (and heavy) as a whale

    It was pouring when the two 35-metre-long quench tanks were delivered to the ITER site at 2:12 a.m. on Thursday 24 November. And it was still raining heavily on [...]

    Read more

  • A passage to India

    108 days, 10,200 kilometres, 16 countries, and only two flat tires. These are the remarkable statistics of a no-less-remarkable journey: a father and son who tr [...]

    Read more

Of Interest

See archived articles

Three more segments for the cryostat

One by one the elements that make up the base of the ITER cryostat—the single largest load of Tokamak assembly—are being delivered to the ITER site from India and safely stored in the Cryostat Workshop.

By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground. (Click to view larger version...)
By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground.
Twelve segments were delivered in December 2015 for tier 1 of the 1,250-ton base section. Three further segments, weighing approximately 120 tons each and representing half of the elements needed to assemble tier 2, arrived at ITER in the early hours of Friday 24 June.

Work will begin this week on the assembly of the first support and transport frame—one of a set of three large steel structures that will support components, jigs and fixtures during the cryostat assembly process. The 30 x 30 metre frames will also act as transporters for the completed cryostat sections.

By mid-July, the welding machines should be installed in the Cryostat Workshop in time for welding operations to begin in August.

The final three segments of the cryostat base are scheduled for delivery in the first week of September.


return to the latest published articles