Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Vacuum vessel| Windows with tailored appendages

    Each of the vacuum vessel's 44 openings will have custom-made 'extensions' to create the junction to the cryostat. The first link in the two-part chain—the port [...]

    Read more

  • Image of the week | Hooked!

    Big, powerful cranes need big, powerful hooks. The hook pictured in this image is one of four that belong to the double overhead bridge crane installed 43 metr [...]

    Read more

  • Project management | The elephant must be sliced

    Any way you cut it, ITER is fantastically complex. Whether you're counting components or the lines in the machine assembly schedule, or taking a closer look at [...]

    Read more

  • Open Doors Day | Front-row experience

    Craning their necks to take in the full size of what will be the ITER Tokamak, the crowd reacted spontaneously: 'This is much bigger than I thought.' 'Really im [...]

    Read more

  • Electrical system| Aiming for "zero fail"

    If something goes wrong in your electrical installation at home you might lose the contents of your freezer—an aggravating occurrence but not a disastrous one. [...]

    Read more

Of Interest

See archived articles

Three more segments for the cryostat

One by one the elements that make up the base of the ITER cryostat—the single largest load of Tokamak assembly—are being delivered to the ITER site from India and safely stored in the Cryostat Workshop.

By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground. (Click to view larger version...)
By late afternoon Friday, all three segments had been unloaded, unpacked and inspected. Elements of the support and transport frame are visible in the foreground.
Twelve segments were delivered in December 2015 for tier 1 of the 1,250-tonne base section. Three further segments, weighing approximately 120 tonnes each and representing half of the elements needed to assemble tier 2, arrived at ITER in the early hours of Friday 24 June.

Work will begin this week on the assembly of the first support and transport frame—one of a set of three large steel structures that will support components, jigs and fixtures during the cryostat assembly process. The 30 x 30 metre frames will also act as transporters for the completed cryostat sections.

By mid-July, the welding machines should be installed in the Cryostat Workshop in time for welding operations to begin in August.

The final three segments of the cryostat base are scheduled for delivery in the first week of September.


return to the latest published articles