Latest ITER Newsline

  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Large components on their way

Two shipments of "oversize" components for ITER's cryoplant are currently making their way to ITER. The first consists of two 35-metre long quench tanks procured by Europe. The tanks were first transported along the Elbe by barge from the Czech Republic where they were fabricated to Germany, before being loaded on board a shipping vessel in Hamburg.

Two 35-metre long quench tanks leave today for three nights along the ITER Itinerary. They are scheduled to reach ITER in the early hours of Thursday 24 November. © Emmanuel Bonici (Click to view larger version...)
Two 35-metre long quench tanks leave today for three nights along the ITER Itinerary. They are scheduled to reach ITER in the early hours of Thursday 24 November. © Emmanuel Bonici
One month later they reached the Mediterranean port of Fos-sur-Mer, where they were unloaded earlier this month and transported across the inland sea of Berre. They leave today for three nights along the ITER Itinerary, and are scheduled to reach ITER in the early hours of Thursday 24 November.

Two out of three ''cold boxes'' for the ITER cryoplant have left their fabrication site and will soon be loaded onto a sea-river vessel in Lyon. © AirLiquide - Laurent Lelong (Click to view larger version...)
Two out of three ''cold boxes'' for the ITER cryoplant have left their fabrication site and will soon be loaded onto a sea-river vessel in Lyon. © AirLiquide - Laurent Lelong
The second shipment is made of slightly smaller loads procured by the ITER Organization—three 21-metre long "cold boxes" that house key components for ITER's liquid helium plants. They  have left their fabrication site and will soon be loaded onto a sea-river vessel in Lyon to sail down the Rhône River all the way to Fos-sur-Mer. They will also travel along the ITER Itinerary, reaching ITER by mid-December.

Fully 90 percent of cryoplant components are expected on site by the end of the year to be stored until the building and technical areas become available for the start of installation activities.


return to the latest published articles