Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Contract for Tokamak Complex excavation awarded

Samina Shamsie, Fusion for Energy

''Once upon a time,'' it will read in the history books, there was a flagpole marking the centre of the ITER Tokamak Pit. (Click to view larger version...)
''Once upon a time,'' it will read in the history books, there was a flagpole marking the centre of the ITER Tokamak Pit.
The contract giving the go-ahead for the first steps in constructing the building which will host the ITER Tokamak, the heart of the project, was signed by the European Domestic Agency Fusion for Energy (F4E) and GTM Consortium on 20 May. Titled "Construction of the Tokamak Complex Seismic Isolation Pit," this contract is worth approximately EUR 36 million.

As a first step in the construction, a 20-metre-deep excavation will be carried out. The foundation of the building will include a system to isolate the building from the rock on which it is built in order to protect against the effects of possible seismic activity. Approximately 200,000 m³ of rock will be excavated—equivalent in volume to 43 of London's Big Ben towers. The construction of the reinforced concrete basemat and walls forming the seismic isolation pit structure will involve the casting of approximately 35,000 m³ of reinforced concrete.

The contract also includes options on the construction of the tokamak upper basemat with 19,200 m³ of reinforced concrete, the Assembly Hall basemat with around 18,000 m³ of reinforced concrete, and 13,500 m³ of excavation. It is foreseen that when finished, the entire Tokamak Building will measure 63 metres in height and 600,000 m³ in volume.

The construction of the foundation for the Tokamak Building will start in mid-June this year and will be completed by November 2011. The contract signature markes the beginning of the process, and is a significant sign of the ITER Project moving forward.

For more information, visit the F4E website.



return to the latest published articles