Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Contract for Tokamak Complex excavation awarded

Samina Shamsie, Fusion for Energy

''Once upon a time,'' it will read in the history books, there was a flagpole marking the centre of the ITER Tokamak Pit. (Click to view larger version...)
''Once upon a time,'' it will read in the history books, there was a flagpole marking the centre of the ITER Tokamak Pit.
The contract giving the go-ahead for the first steps in constructing the building which will host the ITER Tokamak, the heart of the project, was signed by the European Domestic Agency Fusion for Energy (F4E) and GTM Consortium on 20 May. Titled "Construction of the Tokamak Complex Seismic Isolation Pit," this contract is worth approximately EUR 36 million.

As a first step in the construction, a 20-metre-deep excavation will be carried out. The foundation of the building will include a system to isolate the building from the rock on which it is built in order to protect against the effects of possible seismic activity. Approximately 200,000 m³ of rock will be excavated—equivalent in volume to 43 of London's Big Ben towers. The construction of the reinforced concrete basemat and walls forming the seismic isolation pit structure will involve the casting of approximately 35,000 m³ of reinforced concrete.

The contract also includes options on the construction of the tokamak upper basemat with 19,200 m³ of reinforced concrete, the Assembly Hall basemat with around 18,000 m³ of reinforced concrete, and 13,500 m³ of excavation. It is foreseen that when finished, the entire Tokamak Building will measure 63 metres in height and 600,000 m³ in volume.

The construction of the foundation for the Tokamak Building will start in mid-June this year and will be completed by November 2011. The contract signature markes the beginning of the process, and is a significant sign of the ITER Project moving forward.

For more information, visit the F4E website.



return to the latest published articles