Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Summer postcards from the ITER worksite

    The latest harvest of ITER construction photos may be taken from the same point—the tallest crane on site—but there is always an abundance of new detail to be g [...]

    Read more

  • The ring fortress

    ITER'ssteel-and-concretebioshield has become the definingfeature of Tokamak Complex construction. Twolevels only remain to be poured (out of six). It is a 'rin [...]

    Read more

  • The wave factory

    A year ago, work was just beginning on the steel reinforcement for the building's foundation slab. The Radio Frequency Heating Building is now nearing the last [...]

    Read more

  • It's all happening inside

    Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has lookedfrom afar like a finished project. Butinside, tea [...]

    Read more

  • Along skid row

    They look like perfectly aligned emergency housing units. But of course they're not: the 18 concrete structures in the ITER cryoplant are massive pads that will [...]

    Read more

Of Interest

See archived articles

Vacuum vessel component passes pressure equipment tests

-Sabina Griffith

Extending out from the openings in the ITER vacuum vessel (or "ports") are components called port stub extensions that will be welded to the vacuum vessel sectors before the assembly of the main vessel in the pit. The first completed port stub extension—for upper port #12—has successfully passed pressure and helium leak tightness tests.

This 20-tonne component will ''fit'' onto upper port #12. Following final machining and testing, it will be shipped to Korea to be welded to vacuum vessel sector 6. (Click to view larger version...)
This 20-tonne component will ''fit'' onto upper port #12. Following final machining and testing, it will be shipped to Korea to be welded to vacuum vessel sector 6.
There was tangible tension among the observers assembled at the test stand when the pressure gauge reached the 3.78 MPa mark.

Would there be any trace of pressurized water escaping the system? The tolerances on the massive double-wall stainless steel structure were tight, the welding a challenge. After half an hour of mandated holding time, with all eyes on the gauge, there was a collective sigh of relief. The full pressure test of ITER's first completed upper port stub extension (#12) had been completed successfully.

The upper port stub extension is made of single and double-wall sections. Not pictured is the port extension that will be welded to the port stub in the the Tokamak Pit and that will connect to the cryostat through cryostat ducts. (Click to view larger version...)
The upper port stub extension is made of single and double-wall sections. Not pictured is the port extension that will be welded to the port stub in the the Tokamak Pit and that will connect to the cryostat through cryostat ducts.
The ITER vacuum vessel has 44 openings, or ports, on three levels (lower, equatorial and upper) that are used for equipment installation, utility feedthrough, vacuum pumping, and access into the vessel for maintenance. The upper ports are characterized by a trapezoidal/rectangular cross-section due to a slight upward slant. This has to be taken into account in the design of their port structures, including port stub extensions and port extensions. Each port stub extension includes double-wall and single-wall parts (see diagram).

In respect of French regulations on pressure equipment (ESPN), which apply to the ITER vacuum vessel, a full pressure test followed by a helium leak test to confirm the high vacuum tightness of the component were performed in the presence of an Agreed Notified Body* (ANB) before the final machining of upper port stub extension #12.

The tests were carried out at MAN Diesel and Turbo in Deggendorf, Germany, subcontractor to the Efremov Institute in Russia. Russia is responsible for the supply of 100% of the upper ports. (Click to view larger version...)
The tests were carried out at MAN Diesel and Turbo in Deggendorf, Germany, subcontractor to the Efremov Institute in Russia. Russia is responsible for the supply of 100% of the upper ports.
The tests were performed at the end of last year on the premises of the German company MAN Diesel and Turbo in Deggendorf (the main sub-supplier for the port stub extensions) as part of Russia's procurement of the upper ports. The main supplier for this procurement is the Efremov Institute in Saint Petersburg.

The test campaign will be followed by some final machining and the integration of the single wall part before the comprehensive final testing of the complete assembly. When completed, the 20-tonne stub extension will be shipped to Hyundai Heavy Industries in South Korea where it will be mounted on vacuum vessel sector 6. It is expected to arrive by June of this year. 

*An Agreed Notified Body (ANB) is a private company authorized by the French Nuclear Regulator ASN to assess the conformity of components in the pressure equipment category (ESPN).


return to the latest published articles