Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Worksite | First pillars for the crane hall

    For the overhead cranes to deliver machine components into the Tokamak assembly pit, the rails that carry them need to be extended some 80 metres beyond the tem [...]

    Read more

  • Transport | 300 tonnes of equipment on its way to ITER

    A specially designed assembly tool and elements of the cryostat and vacuum vessel thermal shields are part of the shipments travelling now from Korea to ITER. W [...]

    Read more

  • Fusion world | A new tokamak in town

    After EAST in China and WEST in France, another of the cardinal points of the compass has been chosen to name a tokamak. Introducing NORTH—the NORdic Tokamak de [...]

    Read more

  • Opportunities | Bringing the ITER Business Forum to Washington

    Every second year, a two-day ITER Business Forum is held to invite existing and potential suppliers for the ITER Project—laboratories, universities, and compani [...]

    Read more

  • World Energy Congress | Fusion "at a time of transition"

    In the United Arab Emirates, Abu Dhabi is often referred to as a tourism hotspot that combines luxury and ancient traditions. In September, Abu Dhabi was in the [...]

    Read more

Of Interest

See archived entries

Activity on every floor

At every floor of the Tokamak Complex—from the lowest underground level (B2) all the way to the second regular level of the bioshield (L2)—there is intense activity.

Civil works at Tokamak Building basement levels B2 and B1 are now fully complete and finishing works have started. Just overhead, flush with the level of the construction platform, three out of the nine plots for the L1 basemat have been poured.

From the lowest underground level (B2) all the way to the second regular level of the bioshield (L2) there is intense activity in the Tokamak Complex. (Click to view larger version...)
From the lowest underground level (B2) all the way to the second regular level of the bioshield (L2) there is intense activity in the Tokamak Complex.
At the centre of this photo taken last Thursday, as night descended, the first of 18 embedded plates are clearly visible. Anchored in the massive columns at L2 level, these 4.5-tonne plates will support the brackets of a temporary in-pit tool, necessary during the assembly of the vacuum vessel sectors. In one month, work is scheduled to start at the L3 level of the bioshield.

Work is progressing rapidly on the less complex Diagnostics Building, to the right of the image, where civil works have been completed up to L1 level and reinforcement is underway for the L2 concrete slab.

The B1-level walls of the Tritium Building, at the opposite end of the Tokamak Complex, are nearly complete and the installation of L1 formwork is imminent.

Finally, the steel structure has been erected for the Radio Frequency Heating Building adjacent to the Assembly Hall. Two concrete slabs are planned to create the three storeys of the building.


return to the latest published articles