Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryoplant | First steps toward commissioning

    Every week since the beginning of November, a tube trailer filled with approximately 4,600 cubic metres (750 kg) of compressed gaseous helium delivers its load [...]

    Read more

  • Training | Seeking the next group of Monaco-ITER Fellows

    Recruitment opens for the next Monaco-ITER Postdoctoral Fellowship campaign on 17 January 2022. If your PhD was awarded after 1 January 2019—or you are about to [...]

    Read more

  • Contemporary art | Venet's "arcs" are as heavy as ITER coils

    A 'conceptual artist' among the most prominent on the art scene today, Bernar Venet is not impressed by massive towering steel structures like those in the ITER [...]

    Read more

  • Image of the week | Final activities on Europe's first sector

    The first vacuum vessel sector produced in Europe will arrive at ITER next year. Five of ITER's nine vacuum vessel sectors are the responsibility of Europe's AM [...]

    Read more

  • Vacuum vessel sector preparation | Lessons learned reduce work time by half

    In life as in the assembly of the ITER machine, 'lessons learned' are what makes progress possible. Gains in wisdom, time, skill, investment can be incremental; [...]

    Read more

Of Interest

See archived entries

Activity on every floor

At every floor of the Tokamak Complex—from the lowest underground level (B2) all the way to the second regular level of the bioshield (L2)—there is intense activity.

Civil works at Tokamak Building basement levels B2 and B1 are now fully complete and finishing works have started. Just overhead, flush with the level of the construction platform, three out of the nine plots for the L1 basemat have been poured.

From the lowest underground level (B2) all the way to the second regular level of the bioshield (L2) there is intense activity in the Tokamak Complex. (Click to view larger version...)
From the lowest underground level (B2) all the way to the second regular level of the bioshield (L2) there is intense activity in the Tokamak Complex.
At the centre of this photo taken last Thursday, as night descended, the first of 18 embedded plates are clearly visible. Anchored in the massive columns at L2 level, these 4.5-tonne plates will support the brackets of a temporary in-pit tool, necessary during the assembly of the vacuum vessel sectors. In one month, work is scheduled to start at the L3 level of the bioshield.

Work is progressing rapidly on the less complex Diagnostics Building, to the right of the image, where civil works have been completed up to L1 level and reinforcement is underway for the L2 concrete slab.

The B1-level walls of the Tritium Building, at the opposite end of the Tokamak Complex, are nearly complete and the installation of L1 formwork is imminent.

Finally, the steel structure has been erected for the Radio Frequency Heating Building adjacent to the Assembly Hall. Two concrete slabs are planned to create the three storeys of the building.


return to the latest published articles