Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • FEC 2020 | E-conference opens, participation never higher

    The 28th IAEA Fusion Energy Conference (FEC) is off to an auspicious start. Open to the public for the first time thanks to the technical possibilities of an al [...]

    Read more

  • Vacuum vessel in Europe | Fitting the pieces virtually

    A 'virtual fit' tool developed by the European Domestic Agency is helping the vacuum vessel manufacturing team anticipate the challenge of final assembly—the mo [...]

    Read more

  • Gas injection system | Last manifolds completed in China

    Contractors to the Chinese Domestic Agency have completed an important part of the gas injection system—the distribution manifolds that carry gas species from t [...]

    Read more

  • Magnets | Seventh vertical coil reaches ITER

    Seven toroidal field coils have reached ITER in the past year. The latest, TF3 from Europe, passed through the ITER gates on Friday 3 May. The European and Japa [...]

    Read more

  • Tritium Building | Work resumes

    The energy-producing plasmas in ITER will be fuelled in equal measure by the hydrogen isotopes deuterium and tritium. Deuterium is a stable element that industr [...]

    Read more

Of Interest

See archived entries

A wide angle on progress

Whether captured from the top of a crane or from a drone hovering at an altitude of a few dozen metres, the ITER site is always spectacular.
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level). (Click to view larger version...)
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level).
After almost seven years of construction most of the elements of the ITER scientific installation are visible, albeit in various stages of completion.

Progress has been strong in the centre of the Tokamak Complex, where the bioshield now rises two storeys above the level of the platform and has become one of the most noticeable features of the worksite from overhead. Construction progress is also evident in the zones reserved for the ITER cryoplant and the cooling towers/basins.

Other milestones have been achieved that aren't so visible from the sky, however. On 30 March, one of the four transformers for steady-state electrical network was briefly connected to the French grid—opening the way for full switchyard "energization" in the coming months.

And that's not all: inside the Poloidal Field Coils Winding Facility teams are about to start on the first production winding for poloidal field coil #5; in the Radio Frequency Building 80 percent of the steel structure of has been installed and the intermediate floor slabs realized; and in the magnet power conversion area the first "top beam" was installed on columns last week.

But better see it with your own eyes in the photo gallery below ...


return to the latest published articles