Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Tokamak cooling system | Final design achieved

    To remove the heat from the components closest to the plasma, the tokamak cooling water system will rely on over 36 kilometres of nuclear-grade piping and fitti [...]

    Read more

  • Worksite progress | Spot the differences

    Let's play the "spot the differences" game between these two general views of the ITER site, one taken last Thursday 18 January, the other three month [...]

    Read more

  • Inventions | Where have all the neutrons gone?

    It is not unusual in the course of a work day at the world's largest scientific experiment to rely on creativity to resolve the challenge at hand. But less comm [...]

    Read more

  • Neutral beam test facility | Europe delivers first-of-a-kind equipment

    Tullio Bonicelli, in charge of Europe's contributions to the ITER neutral beam heating system, calls them "beyond state-of-the-art components." The hi [...]

    Read more

  • Vacuum vessel | First segment completed in Korea

    The technically challenging fabrication of the ITER vacuum vessel is progressing in Korea, where Hyundai Heavy Industries has completed the first poloidal segme [...]

    Read more

Of Interest

See archived articles

A wide angle on progress

Whether captured from the top of a crane or from a drone hovering at an altitude of a few dozen metres, the ITER site is always spectacular.
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level). (Click to view larger version...)
Workers are preparing to pour the last segments of the Tokamak Building L1 slab ... laying rebar, positioning anchor plates, setting up scaffolding. Visitors to ITER's Open Doors Day in May will be able to walk out over the finished concrete (L1 is the equivalent of ground level).
After almost seven years of construction most of the elements of the ITER scientific installation are visible, albeit in various stages of completion.

Progress has been strong in the centre of the Tokamak Complex, where the bioshield now rises two storeys above the level of the platform and has become one of the most noticeable features of the worksite from overhead. Construction progress is also evident in the zones reserved for the ITER cryoplant and the cooling towers/basins.

Other milestones have been achieved that aren't so visible from the sky, however. On 30 March, one of the four transformers for steady-state electrical network was briefly connected to the French grid—opening the way for full switchyard "energization" in the coming months.

And that's not all: inside the Poloidal Field Coils Winding Facility teams are about to start on the first production winding for poloidal field coil #5; in the Radio Frequency Building 80 percent of the steel structure of has been installed and the intermediate floor slabs realized; and in the magnet power conversion area the first "top beam" was installed on columns last week.

But better see it with your own eyes in the photo gallery below ...


return to the latest published articles