Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Challenges | Managing risk in a first-of-a-kind project like ITER

    The classic approach to project management is to group risks into three separate categories. The first consists of known risks, the second of unknown risks, and [...]

    Read more

  • "Friendship Award"| China honours ITER Director-General

    Last week, ITER Director-General Bernard Bigot was one of 100 foreign experts from 31 countries to be awarded China's Government Friendship Award. The Governm [...]

    Read more

  • Disruption mitigation | First tests with JET's shattered pellet injector

    A shattered pellet injector—a device which pre-empts plasma disruptions by releasing a spray of frozen deuterium-neon pellets into a plasma—is now in testing on [...]

    Read more

  • Image of the week | 12 pillars and counting

    Two rows of pillars have now appeared at the top of the ITER Tokamak Building—12 out of 20 base pillars that will soon be topped by a second level of pillars, a [...]

    Read more

  • Blanket first wall | Qualification program concludes in Europe

    Directly facing the heat and high-energy neutrons produced during fusion is the first wall of the ITER blanket—440 beryllium-coated, detachable panels that will [...]

    Read more

Of Interest

See archived entries

It's all happening inside

Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has looked from afar like a finished project. But inside, teams have been advancing on finishing works—installing plasterboard, lighting, fire protection, cable trays; jointing and painting; and creating stairwells and a lift. Most recently, a first coat of varnish was applied to the floor to limit dust, testing of the overhead cranes started, and a special zone was prepared for the building's first and most impressive assembly tools, the twin vacuum vessel sector sub-assembly tools. European contractors successfully achieved an ITER Council milestone in late June by making one part of the Assembly Hall "ready for equipment."

In the 60-metre-tall building for pre-assembly activities, workers go over the painted surface of the basemat. Later, when construction activities on the Tokamak Building are finalized, the temporary wall seen at the end of the building will come down and the cranes will operate along a 170-metre crane bay. The double building will operated as a clean space during the assembly of the machine. (Click to view larger version...)
In the 60-metre-tall building for pre-assembly activities, workers go over the painted surface of the basemat. Later, when construction activities on the Tokamak Building are finalized, the temporary wall seen at the end of the building will come down and the cranes will operate along a 170-metre crane bay. The double building will operated as a clean space during the assembly of the machine.
 

These anchor bolts are ready to receive the wing rails and columns of the vacuum vessel sector sub-assembly tools. On this reinforced area of the Assembly Building basemat, contractors will begin tool installation activities in August. By the end of the year, the first tool should be standing 22 metres tall. (Click to view larger version...)
These anchor bolts are ready to receive the wing rails and columns of the vacuum vessel sector sub-assembly tools. On this reinforced area of the Assembly Building basemat, contractors will begin tool installation activities in August. By the end of the year, the first tool should be standing 22 metres tall.

In this image, the Tokamak Building has been finalized and the temporary wall that closes it off from the Assembly Building has come down. We see the full crane bay, with the machine assembly area in the background. Also evident, the semicircular ''footprint'' of the sector sub-assembly tools, which is already traced out on the reinforced basemat of the Assemly Hall (see second photo). (Click to view larger version...)
In this image, the Tokamak Building has been finalized and the temporary wall that closes it off from the Assembly Building has come down. We see the full crane bay, with the machine assembly area in the background. Also evident, the semicircular ''footprint'' of the sector sub-assembly tools, which is already traced out on the reinforced basemat of the Assemly Hall (see second photo).

This 10-metre-tall ''box-in-a-box'' has been erected in the Cleaning Facility (at the entrance to the Assembly Hall) to store the elements of the sector sub-assembly tools. Crates of tool components have been arriving since June from Korea (the first are pictured here). (Click to view larger version...)
This 10-metre-tall ''box-in-a-box'' has been erected in the Cleaning Facility (at the entrance to the Assembly Hall) to store the elements of the sector sub-assembly tools. Crates of tool components have been arriving since June from Korea (the first are pictured here).


return to the latest published articles