Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • 23rd ITER Council | Pace and performance on track

    Working as an integrated team, the ITER Organization and seven Domestic Agencies are continuing to meet the project's demanding schedule to First Plasma in 2025 [...]

    Read more

  • Fusion Doctors | ITER hosts the future

    For three days last week, the ITER building was brimming with energy, inspiration and enthusiasm. One hundred and thirty-five young fusion aficionados took over [...]

    Read more

  • Fusion world | What's next for the stellarator?

    Earlier this year, the Wendelstein 7-X stellarator fusion project reported record achievements from its most recent experimental campaign. Newsline spoke with t [...]

    Read more

  • Metrology and the ITER machine | Perfectly planned points

    Inside of the Tokamak Complex, a network of 2,000 small 'fiducial target nests' will provide the reference datum for the dimensional control and alignment of ma [...]

    Read more

  • Breaking news | First component installed next week

    In the third week of November, the ITER Organization will be installing the first component of the machine in the basement of the Tokamak Building. The 10-met [...]

    Read more

Of Interest

See archived entries

It's all happening inside

Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has looked from afar like a finished project. But inside, teams have been advancing on finishing works—installing plasterboard, lighting, fire protection, cable trays; jointing and painting; and creating stairwells and a lift. Most recently, a first coat of varnish was applied to the floor to limit dust, testing of the overhead cranes started, and a special zone was prepared for the building's first and most impressive assembly tools, the twin vacuum vessel sector sub-assembly tools. European contractors successfully achieved an ITER Council milestone in late June by making one part of the Assembly Hall "ready for equipment."

In the 60-metre-tall building for pre-assembly activities, workers go over the painted surface of the basemat. Later, when construction activities on the Tokamak Building are finalized, the temporary wall seen at the end of the building will come down and the cranes will operate along a 170-metre crane bay. The double building will operated as a clean space during the assembly of the machine. (Click to view larger version...)
In the 60-metre-tall building for pre-assembly activities, workers go over the painted surface of the basemat. Later, when construction activities on the Tokamak Building are finalized, the temporary wall seen at the end of the building will come down and the cranes will operate along a 170-metre crane bay. The double building will operated as a clean space during the assembly of the machine.
 

These anchor bolts are ready to receive the wing rails and columns of the vacuum vessel sector sub-assembly tools. On this reinforced area of the Assembly Building basemat, contractors will begin tool installation activities in August. By the end of the year, the first tool should be standing 22 metres tall. (Click to view larger version...)
These anchor bolts are ready to receive the wing rails and columns of the vacuum vessel sector sub-assembly tools. On this reinforced area of the Assembly Building basemat, contractors will begin tool installation activities in August. By the end of the year, the first tool should be standing 22 metres tall.

In this image, the Tokamak Building has been finalized and the temporary wall that closes it off from the Assembly Building has come down. We see the full crane bay, with the machine assembly area in the background. Also evident, the semicircular ''footprint'' of the sector sub-assembly tools, which is already traced out on the reinforced basemat of the Assemly Hall (see second photo). (Click to view larger version...)
In this image, the Tokamak Building has been finalized and the temporary wall that closes it off from the Assembly Building has come down. We see the full crane bay, with the machine assembly area in the background. Also evident, the semicircular ''footprint'' of the sector sub-assembly tools, which is already traced out on the reinforced basemat of the Assemly Hall (see second photo).

This 10-metre-tall ''box-in-a-box'' has been erected in the Cleaning Facility (at the entrance to the Assembly Hall) to store the elements of the sector sub-assembly tools. Crates of tool components have been arriving since June from Korea (the first are pictured here). (Click to view larger version...)
This 10-metre-tall ''box-in-a-box'' has been erected in the Cleaning Facility (at the entrance to the Assembly Hall) to store the elements of the sector sub-assembly tools. Crates of tool components have been arriving since June from Korea (the first are pictured here).


return to the latest published articles