Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Remembering Bernard Bigot, ITER Director-General 2015-2022

    On the ITER site, the machinery of construction was humming just like on any weekday. Workers were concentrating on their tasks, laying rebar for new buildings [...]

    Read more

  • Tokamak assembly | Preparing for the Big Lift

    The distance was short but the challenge daunting: on Thursday last week, the first section of the plasma chamber was lifted 50 centimetres above its suppor [...]

    Read more

  • Image of the week | 13th toroidal field coil arrives from Europe

    The toroidal field coil procurement effort has been one of the longest of the ITER program, initiated by Procurement Arrangements signed in 2007 and 2008. Manuf [...]

    Read more

  • Diagnostics | Final Procurement Arrangement signed

    ITER Diagnostics reached an important milestone in December 2021 when it concluded the last Procurement Arrangement of the diagnostics program. After signing a [...]

    Read more

  • On site | A quick visit to the Control Building

    Work is progressing on the ITER Control Building, ergonomically designed for the 60 to 80 operators, engineers and researchers who will call it home.  [...]

    Read more

Of Interest

See archived entries

It's all happening inside

Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has looked from afar like a finished project. But inside, teams have been advancing on finishing works—installing plasterboard, lighting, fire protection, cable trays; jointing and painting; and creating stairwells and a lift. Most recently, a first coat of varnish was applied to the floor to limit dust, testing of the overhead cranes started, and a special zone was prepared for the building's first and most impressive assembly tools, the twin vacuum vessel sector sub-assembly tools. European contractors successfully achieved an ITER Council milestone in late June by making one part of the Assembly Hall "ready for equipment."

In the 60-metre-tall building for pre-assembly activities, workers go over the painted surface of the basemat. Later, when construction activities on the Tokamak Building are finalized, the temporary wall seen at the end of the building will come down and the cranes will operate along a 170-metre crane bay. The double building will operated as a clean space during the assembly of the machine. (Click to view larger version...)
In the 60-metre-tall building for pre-assembly activities, workers go over the painted surface of the basemat. Later, when construction activities on the Tokamak Building are finalized, the temporary wall seen at the end of the building will come down and the cranes will operate along a 170-metre crane bay. The double building will operated as a clean space during the assembly of the machine.
 

These anchor bolts are ready to receive the wing rails and columns of the vacuum vessel sector sub-assembly tools. On this reinforced area of the Assembly Building basemat, contractors will begin tool installation activities in August. By the end of the year, the first tool should be standing 22 metres tall. (Click to view larger version...)
These anchor bolts are ready to receive the wing rails and columns of the vacuum vessel sector sub-assembly tools. On this reinforced area of the Assembly Building basemat, contractors will begin tool installation activities in August. By the end of the year, the first tool should be standing 22 metres tall.

In this image, the Tokamak Building has been finalized and the temporary wall that closes it off from the Assembly Building has come down. We see the full crane bay, with the machine assembly area in the background. Also evident, the semicircular ''footprint'' of the sector sub-assembly tools, which is already traced out on the reinforced basemat of the Assemly Hall (see second photo). (Click to view larger version...)
In this image, the Tokamak Building has been finalized and the temporary wall that closes it off from the Assembly Building has come down. We see the full crane bay, with the machine assembly area in the background. Also evident, the semicircular ''footprint'' of the sector sub-assembly tools, which is already traced out on the reinforced basemat of the Assemly Hall (see second photo).

This 10-metre-tall ''box-in-a-box'' has been erected in the Cleaning Facility (at the entrance to the Assembly Hall) to store the elements of the sector sub-assembly tools. Crates of tool components have been arriving since June from Korea (the first are pictured here). (Click to view larger version...)
This 10-metre-tall ''box-in-a-box'' has been erected in the Cleaning Facility (at the entrance to the Assembly Hall) to store the elements of the sector sub-assembly tools. Crates of tool components have been arriving since June from Korea (the first are pictured here).


return to the latest published articles