Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Tokamak assembly | The "module" has landed

    This 'module' was not designed to land on the Moon. But it was as complex a piece of technology, requiring as much precision in its handling as the famed 'lunar [...]

    Read more

  • Remembering Bernard Bigot, ITER Director-General 2015-2022

    On the ITER site, the machinery of construction was humming just like on any weekday. Workers were concentrating on their tasks, laying rebar for new buildings [...]

    Read more

  • Tokamak assembly | Preparing for the Big Lift

    The distance was short but the challenge daunting: on Thursday last week, the first section of the plasma chamber was lifted 50 centimetres above its suppor [...]

    Read more

  • Image of the week | 13th toroidal field coil arrives from Europe

    The toroidal field coil procurement effort has been one of the longest of the ITER program, initiated by Procurement Arrangements signed in 2007 and 2008. Manuf [...]

    Read more

  • Diagnostics | Final Procurement Arrangement signed

    ITER Diagnostics reached an important milestone in December 2021 when it concluded the last Procurement Arrangement of the diagnostics program. After signing a [...]

    Read more

Of Interest

See archived entries

Deliveries

Last cryogenic tanks from Europe

Eleven storage tanks have been delivered by the European Domestic Agency in the past year for the ITER cryoplant, including two this past week.

The European-procured tanks are all stored horizontally on the ITER platform for the moment. However as seen in the image below, many of them will move to a vertical position when installed in their final location. (Click to view larger version...)
The European-procured tanks are all stored horizontally on the ITER platform for the moment. However as seen in the image below, many of them will move to a vertical position when installed in their final location.
The fabrication of the tanks for the ITER cryoplant was undertaken by European contractor Air Liquide and its subcontractors in such faraway locations as Sweden, the Czech Republic, China and Turkey, while logistics were handled by ITER's global logistics provider, DAHER.

One of the most technically challenging tanks will be capable of storing up to 20 tonnes of liquid helium (LHe), or 85 percent of the 24 tonnes of liquid helium that will be circulating in the ITER installation during operation. The double-wall vessel measures 25 metres in length.

The ITER cryoplant, under construction now, comprises 5,400 m² of covered buildings plus a large exterior area for the storage of helium and nitrogen. (Click to view larger version...)
The ITER cryoplant, under construction now, comprises 5,400 m² of covered buildings plus a large exterior area for the storage of helium and nitrogen.
Ten other tanks—six gaseous helium (GHe) tanks, one liquid nitrogen tank (LN2), one gaseous nitrogen tank (GN2), and two quench tanks for the storage of helium expelled from the ITER magnets in the case of a quench—are also needed as part of the cryoplant infrastructure.

The ITER cryoplant will provide liquid helium and liquid nitrogen to major clients for cooling. Cooling fluids generated in the cryoplant will travel along process lines installed 13 metres above platform level on a bridge that runs to the Tokamak Building; from there, approximately five kilometres of cryolines will distribute gas and liquid helium to the different "users." The ITER magnets will consume 45 percent of cryogenic power followed by the thermal shield (40 percent) and the cryopumps (15 percent).

The tanks will be installed in a 2,600 m² exterior storage area near the cryoplant, where a concrete platform has been prepared.

Read the full report on the European Domestic Agency website.


return to the latest published articles